Imperial Reports Second Quarter Production and Red Chris Construction Progress

VANCOUVER, BRITISH COLUMBIA -- (Marketwired) -- 07/15/14 -- Imperial Metals Corporation (TSX: III) reports that metal production for the second quarter 2014 from its Mount Polley, Huckleberry(1) and Sterling mines was, on an aggregate basis, 16.6 million pounds copper, 13,867 ounces gold and 59,289 ounces silver.

At Mount Polley the second quarter average daily throughput was 23,404 tonnes per day, up by 23% compared to the first quarter. Metal production totalled 12.0 million pounds copper, 11,867 ounces gold and 33,813 ounces silver; increases of 46%, 24% and 35% respectively compared to the first quarter 2014.

Huckleberry copper production was up 67% in the second quarter 2014 compared to the first quarter, from 5.5 million pounds to 9.2 million pounds. The SAG mill has performed well since the restart on April 5, with throughput averaging 15,213 tonnes per day for the second quarter, up from the first quarter average of 9,967 tonnes per day. Softer ore from the Main Zone pit and adjustments in the mill resulted in a steady increase in the mill throughput rate during the second quarter. In the first week of July, the mill throughput averaged 20,433 tonnes per day.

Sterling mining operations resumed on June 17, 2014 after the mine received an air emissions permit issued in accordance with new regulations. Due to the suspension of operations no gold was shipped during the second quarter compared to 2,104 ounces gold shipped during the first quarter. Subsequent to the end of the second quarter, approximately 1,500 ounces gold was shipped in early July.

On-site construction at Red Chris is well advanced. Interior steel, mechanical installation, and the tailings and reclaim water systems are 93% complete. Piping and electrical work (including the powerline from Tatogga to the minesite) continues to progress at a satisfactory rate, and will be completed on time for the commissioning and start-up of milling operations at Red Chris. Mining operations have already commenced at Red Chris with the first excavation of ore grade material from the East zone. This material is being stockpiled for commencement of milling operations.

The 287kv Northwest Transmission Line (NTL) from Skeena substation near Terrace to Bob Quinn is now complete, and BC Hydro reports the Bob Quinn substation was energized today. Construction of the 93km Iskut extension of the NTL from Bob Quinn to Tatogga continues to progress. All towers for the Iskut extension are targeted to be in place by the end of July. Energization of the Iskut extension has been delayed somewhat as a result of the delivery of faulty implosion sleeves. These sleeves are used to splice the conductors. Implosion sleeves are specifically designed metallic sleeves with a small engineered charge wrapped around the sleeve. The charge creates an implosive compression, seamlessly joining two conductor ends. At present the new implosion sleeves are targeted to be on site by the end of July. Due to delays associated with the faulty implosion sleeves, the completion and energization of the Iskut extension is now anticipated to be in September 2014. Commissioning and start up of the Red Chris milling operations will follow.

(1) stated as Imperial's 50% allocation of Huckleberry production

About Imperial

Imperial is an exploration, mine development and operating company based in Vancouver, British Columbia. The Company operates the Mount Polley copper/gold mine in British Columbia and the Sterling gold mine in Nevada. Imperial has 50% interest in the Huckleberry copper mine and has 50% interest in the Ruddock Creek lead/zinc property, both in British Columbia. Imperial is in development of its wholly owned Red Chris copper/gold property in British Columbia.

Cautionary Note Regarding "Forward-Looking Information"

This press release contains "forward-looking information" or "forward-looking statements" within the meaning of Canadian and United States Securities Laws, which we will refer to as "forward-looking information". Except for statements of historical fact relating to the Company, certain information contained herein constitutes forward-looking information. If we discuss mine plans; costs and timing of current and proposed exploration, development, production and marketing; capital expenditures; construction of transmission lines; cash flow; working capital requirements and the requirement for additional capital; operations; revenue; margins and earnings; future prices of copper and gold; future foreign currency exchange rates; future accounting changes; future prices for marketable securities; future resolution of contingent liabilities; receipt of permits; or other matters that have not yet occurred, we are making statements considered to be forward-looking information or forward-looking statements under Canadian and United States Securities Laws.

The forward-looking information in this press release may include words and phrases about the future, such as: plan, expect, forecast, intend, anticipate, estimate, budget, scheduled, believe, may, could, would, might or will. We can give no assurance the forward-looking information will prove to be accurate. It is based on a number of assumptions management believes to be reasonable, including but not limited to: the continued operation of the Company's mining operations, no material adverse change in the market price of commodities or exchange rates, that the mining operations will operate and the mining projects will be completed in accordance with their estimates and achieve stated production outcomes and such other assumptions and factors as set out herein. It is also subject to risks associated with our business, including but not limited to: risks inherent in the mining and metals business; commodity price fluctuations and hedging; competition for mining properties; sale of products and future market access; mineral reserves and recovery estimates; currency fluctuations; interest rate risks; financing risks; regulatory and permitting risks; environmental risks; joint venture risks; foreign activity risks; legal proceedings; and other risks that are set out in the Company's current Management's Discussion & Analysis. If our assumptions prove to be incorrect or risks materialize, our actual results and events may vary materially from what we currently expect as provided in this press release. We recommend review of the Company's current Management's Discussion & Analysis, which includes discussion of material risks that could cause actual results to differ materially from our current expectations. Forward-looking information is designed to help you understand management's current views of our near and longer term prospects, and it may not be appropriate for other purposes. We will not necessarily update this information unless we are required to by securities laws.

Contacts:
Brian Kynoch
President
604.669.8959

Andre Deepwell
Chief Financial Officer
604.488.2666

Gordon Keevil
Vice President Corporate Development
604.488.2677

Sabine Goetz
Shareholder Communications
604.488.2657
[email protected]

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
With more than 30 Kubernetes solutions in the marketplace, it's tempting to think Kubernetes and the vendor ecosystem has solved the problem of operationalizing containers at scale or of automatically managing the elasticity of the underlying infrastructure that these solutions need to be truly scalable. Far from it. There are at least six major pain points that companies experience when they try to deploy and run Kubernetes in their complex environments. In this presentation, the speaker will d...
While DevOps most critically and famously fosters collaboration, communication, and integration through cultural change, culture is more of an output than an input. In order to actively drive cultural evolution, organizations must make substantial organizational and process changes, and adopt new technologies, to encourage a DevOps culture. Moderated by Andi Mann, panelists discussed how to balance these three pillars of DevOps, where to focus attention (and resources), where organizations might...
The deluge of IoT sensor data collected from connected devices and the powerful AI required to make that data actionable are giving rise to a hybrid ecosystem in which cloud, on-prem and edge processes become interweaved. Attendees will learn how emerging composable infrastructure solutions deliver the adaptive architecture needed to manage this new data reality. Machine learning algorithms can better anticipate data storms and automate resources to support surges, including fully scalable GPU-c...
When building large, cloud-based applications that operate at a high scale, it's important to maintain a high availability and resilience to failures. In order to do that, you must be tolerant of failures, even in light of failures in other areas of your application. "Fly two mistakes high" is an old adage in the radio control airplane hobby. It means, fly high enough so that if you make a mistake, you can continue flying with room to still make mistakes. In his session at 18th Cloud Expo, Le...
Machine learning has taken residence at our cities' cores and now we can finally have "smart cities." Cities are a collection of buildings made to provide the structure and safety necessary for people to function, create and survive. Buildings are a pool of ever-changing performance data from large automated systems such as heating and cooling to the people that live and work within them. Through machine learning, buildings can optimize performance, reduce costs, and improve occupant comfort by ...
As Cybric's Chief Technology Officer, Mike D. Kail is responsible for the strategic vision and technical direction of the platform. Prior to founding Cybric, Mike was Yahoo's CIO and SVP of Infrastructure, where he led the IT and Data Center functions for the company. He has more than 24 years of IT Operations experience with a focus on highly-scalable architectures.
CI/CD is conceptually straightforward, yet often technically intricate to implement since it requires time and opportunities to develop intimate understanding on not only DevOps processes and operations, but likely product integrations with multiple platforms. This session intends to bridge the gap by offering an intense learning experience while witnessing the processes and operations to build from zero to a simple, yet functional CI/CD pipeline integrated with Jenkins, Github, Docker and Azure...
The explosion of new web/cloud/IoT-based applications and the data they generate are transforming our world right before our eyes. In this rush to adopt these new technologies, organizations are often ignoring fundamental questions concerning who owns the data and failing to ask for permission to conduct invasive surveillance of their customers. Organizations that are not transparent about how their systems gather data telemetry without offering shared data ownership risk product rejection, regu...
René Bostic is the Technical VP of the IBM Cloud Unit in North America. Enjoying her career with IBM during the modern millennial technological era, she is an expert in cloud computing, DevOps and emerging cloud technologies such as Blockchain. Her strengths and core competencies include a proven record of accomplishments in consensus building at all levels to assess, plan, and implement enterprise and cloud computing solutions. René is a member of the Society of Women Engineers (SWE) and a m...
Dhiraj Sehgal works in Delphix's product and solution organization. His focus has been DevOps, DataOps, private cloud and datacenters customers, technologies and products. He has wealth of experience in cloud focused and virtualized technologies ranging from compute, networking to storage. He has spoken at Cloud Expo for last 3 years now in New York and Santa Clara.
Enterprises are striving to become digital businesses for differentiated innovation and customer-centricity. Traditionally, they focused on digitizing processes and paper workflow. To be a disruptor and compete against new players, they need to gain insight into business data and innovate at scale. Cloud and cognitive technologies can help them leverage hidden data in SAP/ERP systems to fuel their businesses to accelerate digital transformation success.
Containers and Kubernetes allow for code portability across on-premise VMs, bare metal, or multiple cloud provider environments. Yet, despite this portability promise, developers may include configuration and application definitions that constrain or even eliminate application portability. In this session we'll describe best practices for "configuration as code" in a Kubernetes environment. We will demonstrate how a properly constructed containerized app can be deployed to both Amazon and Azure ...
Poor data quality and analytics drive down business value. In fact, Gartner estimated that the average financial impact of poor data quality on organizations is $9.7 million per year. But bad data is much more than a cost center. By eroding trust in information, analytics and the business decisions based on these, it is a serious impediment to digital transformation.
Digital Transformation: Preparing Cloud & IoT Security for the Age of Artificial Intelligence. As automation and artificial intelligence (AI) power solution development and delivery, many businesses need to build backend cloud capabilities. Well-poised organizations, marketing smart devices with AI and BlockChain capabilities prepare to refine compliance and regulatory capabilities in 2018. Volumes of health, financial, technical and privacy data, along with tightening compliance requirements by...
Predicting the future has never been more challenging - not because of the lack of data but because of the flood of ungoverned and risk laden information. Microsoft states that 2.5 exabytes of data are created every day. Expectations and reliance on data are being pushed to the limits, as demands around hybrid options continue to grow.