ATAC Announces Positive PEA Results for the High-Grade Oxide Gold Tiger Deposit, Rackla Gold Project-Yukon

VANCOUVER, BRITISH COLUMBIA -- (Marketwired) -- 07/23/14 -- ATAC Resources Ltd. (TSX VENTURE:ATC) is pleased to announce the completion of a positive Preliminary Economic Assessment ("PEA") for the oxide portion of the Tiger Deposit located at the western end of the Company's 100% owned Rackla Gold Project, Yukon. The Tiger Deposit was discovered in 2007 and is distinct from the more recent larger scale Carlin-type discoveries located 100 km to the east, which remain the exploration focus of the Company.

The lead engineering firm for the PEA was Kappes Cassiday & Associates ("KCA") (metallurgy, processing, infrastructure, financial analysis) in cooperation with Tetra Tech, Inc. ("Tetra Tech") (mining), Giroux Consultants Ltd. (mineral resource), Resource Strategies (environmental and permitting) and Gerald G. Carlson, Ph.D., P.Eng. (history, geology, drilling). Unless specified otherwise, all values are shown in Canadian dollars, where 1 CAD = 0.92 USD.

PEA HIGHLIGHTS (using US$1,250 per ounce gold price):


--  Conventional open-pit mining with single-stage, low intensity crushing
    followed by size classification - no grinding or agglomeration needed; 
--  Life of mine ("LOM") production of 2.06 million tonnes of oxide material
    at an average diluted grade of 3.72 g/t gold; 
--  Overall gold recoveries of 89.8% from hybrid heap-leach (87.8% recovery)
    and agitated tank (91.0% recovery) carbon-in-leach ("CIL") process; 
--  Four year, seasonal operation with LOM production of 221,558 ounces of
    gold; 
--  Pre-tax net present value ("NPV") of $52.1 million at a 5% discount rate
    and internal rate of return ("IRR") of 30% with an all-in sustaining
    cash cost of $626(i); 
--  At a US$1,350 per ounce gold price the pre-tax NPV increases to $72.6
    million at a 5% discount rate and IRR of 39.5%; and, 
--  Pit slope engineering, Tiger Deposit infill drilling and exploration of
    numerous untested nearby oxide targets have the potential to enhance the
    value of the project economics.
    (i)All-in sustaining costs are presented as defined by the World Gold
    Council less corporate G&A. 

"Although we remain focused on the Carlin-type gold targets 100 km to the east, we are very pleased with the results of the comprehensive Tiger Deposit PEA. It gives the Company a clear understanding of the potential viability and value of our first Rackla Gold Project discovery, and highlights the advantages of a rare high-grade, at surface, oxide gold deposit that is located in one of the most favourable mining jurisdictions in the world," states Graham Downs, CEO of ATAC. "The simplicity of the mining and processing combined with the approach of modular design and construction for the on-site facilities has resulted in an optimized development scenario for this size of deposit. Additional geotechnical and resource drilling at the Tiger Deposit combined with exploration drilling at over six untested satellite oxide targets has the potential to significantly enhance the PEA and the district potential of the Rackla Gold Project."

Economic Results and Sensitivities

The following table demonstrates the sensitivity of the Tiger Deposit economics to the price of gold. US$1,250 per ounce gold price was used as the base case and is highlighted in the table.

Summary of gold price sensitivity


----------------------------------------------------------------------------
Gold Price US$/oz                             $1,100  $1,250  $1,350  $1,500
----------------------------------------------------------------------------
Pre-Tax Cumulative Net Cash Flow $M            $36.7   $72.7   $96.6  $132.6
----------------------------------------------------------------------------
Pre-Tax NPV (5% discount rate) $M              $21.4   $52.1   $72.6  $103.3
----------------------------------------------------------------------------
Pre-Tax IRR                                    15.5%   30.0%   39.5%   53.5%
----------------------------------------------------------------------------
Pre-Tax Payback (years)                          2.9     2.2     1.8     1.3
----------------------------------------------------------------------------
                                                                            
----------------------------------------------------------------------------
After-Tax Cumulative Net Cash Flow             $10.4   $51.0   $67.3   $91.5
----------------------------------------------------------------------------
After-Tax NPV (5% discount rate) $M            $12.6   $33.7   $47.5   $68.0
----------------------------------------------------------------------------
After-Tax IRR                                  11.2%   21.5%   27.9%   37.2%
----------------------------------------------------------------------------
After-Tax Payback (years)                        3.2     2.6     2.3     1.9
----------------------------------------------------------------------------

Mining and Processing

The Tiger Deposit has been modeled as an open-pit mining operation with a hybrid heap leach and CIL gold recovery process. A summary of: (i) gold production and processing metrics; (ii) pre-production costs; and (iii) operating costs are presented in the following tables.

Projected Production and Processing Summary


----------------------------------------------------------------------------
Total Process Feed                          2.06 million tonnes             
----------------------------------------------------------------------------
Processing Rate                                                             
(158 days per year)                           3,300 tonnes/day              
----------------------------------------------------------------------------
LOM Strip Ratio                                    5.6:1                    
----------------------------------------------------------------------------
                                                                    Combined
                                    Heap Leach                    Average or
Proportional Processing Feed             (42%)      CIL (58%)          Total
----------------------------------------------------------------------------
Average Process Feed Grade         3.45 g/t Au    3.91 g/t Au    3.72 g/t Au
----------------------------------------------------------------------------
Average Recovery                         87.8%          91.0%          89.8%
----------------------------------------------------------------------------
Average Annual Production LOM                                               
 (oz)                                   21,132         34,257         55,389
----------------------------------------------------------------------------
Total Production (oz)                   84,528        137,029        221,558
----------------------------------------------------------------------------
Silver is a minor by-product of gold production with an assumed recovery of 
 19% and process feed grade of 5 g/t. Total recovered silver ounces over LOM
 is 63,057 oz.                                                              

Pre-Production and Sustaining Capital Costs (Millions)


----------------------------------------------------------------------------
                                          Pre-     Sustaining               
Capital Costs                       Production        capital            LOM
----------------------------------------------------------------------------
Site Infrastructure                       $1.7                          $1.7
----------------------------------------------------------------------------
Heap Leach/Tailings(i)                    $5.7          $20.4          $26.1
----------------------------------------------------------------------------
Mining Equipment                         $10.1           $1.7          $11.8
----------------------------------------------------------------------------
Pre-Stripping & Stockpiling              $10.5                         $10.5
----------------------------------------------------------------------------
Process Plant                            $40.3                         $40.3
----------------------------------------------------------------------------
Contingency (20%)                        $11.6           $4.4          $16.0
----------------------------------------------------------------------------
Indirect costs                           $12.3                         $12.3
----------------------------------------------------------------------------
Total(ii)                                $92.3          $26.5         $118.8
----------------------------------------------------------------------------
(i) Pre-production and annual heap leach cell and tailings development      
(ii) Totals may not add exactly due to rounding                             

Operating Costs


----------------------------------------------------------------------------
Operating Costs                                                  LOM Average
----------------------------------------------------------------------------
Mining Costs(i) ($/tonne mined)                                        $4.46
----------------------------------------------------------------------------
Processing ($/tonne processed)                                        $20.10
----------------------------------------------------------------------------
G & A ($/tonne processed)                                              $7.11
----------------------------------------------------------------------------
(i) Not including capitalized pre-production mining costs                   

Project Description

The Tiger Deposit is located approximately 55 km northeast of Keno City, Yukon. Access to the Tiger Deposit would be by a proposed 51.6 km winter road that utilizes 24.6 km of the existing and permitted Wind River Winter Trail. The deposit is currently accessed by air via a 2,500 foot airstrip located 8 km from the deposit.

An owner-operated open-pit mine, with one year of pre-stripping followed by four years of production is envisioned in the PEA. Average annual production would be approximately 55,389 oz gold with year one production projected to be 78,500 oz gold. A total of 2.06 million tonnes of oxide material at an average diluted grade of 3.72 g/t would be extracted by hydraulic excavator. Based on a geotechnical study, no blasting of mineralized material would be necessary due to its highly weathered and sandy nature. Mining and stockpiling would take place year-round, while processing of mineralized material would occur during May through September (158 days annually) at a rate of 3,300 tonnes per day.

Processing has been designed to begin near the open-pit where material would be fed into a single skid-mounted low-intensity mineral sizer. Material would then be transported downhill by overland conveyor to a modular processing facility to be scrubbed and sized into two size fractions. The study proposes a hybrid approach where approximately 42% of the material (+0.212 mm) would be sent to the heap leach facility. The remaining 58% (finer material) would be sent to the CIL plant. A 50 day heap leach cycle has an estimated gold recovery of 87.8% while the retention time for the CIL plant is 24 hours with an estimated gold recovery of 91.0%.

All major project components for the Tiger Deposit would be engineered and constructed to achieve efficient closure. Heap leach cells would be built annually and progressively reclaimed, while the tailings facilities would be expanded annually and fully reclaimed at closure.

Opportunities to Enhance the Project

ATAC is very pleased with the base case results from the detailed PEA and believes that opportunities exist that could greatly enhance the economics of the project. Some key opportunities include:


--  Future geotechnical studies may permit steeper pit slopes, which could
    potentially capture a greater percentage of the presently known resource
    and/or reduce the strip ratio; 
--  Trade-off studies between owner-operator and contract mining or mining
    fleet leasing could decrease pre-production capital; 
--  Resource expansion and upgrading inferred resources to the indicated
    category may be achieved with a modest drill program; and, 
--  Significant potential exists to increase the resource base and life
    expectancy of the project with the exploration of more than six untested
    satellite oxide gold targets and geochemical anomalies. 

Environment and Community Engagement

Since 2007, the Company has completed comprehensive environmental, water, heritage, geotechnical and metallurgical studies which have resulted in a highly advanced project at the PEA stage. Due to the nature of the geology of the deposit and environmental studies completed to date, permitting would likely be without significant problems.

Community and First Nation engagement began in 2008 with the first Exploration Cooperation Agreement with the First Nation of Na Cho Nyak Dun ("NND") signed in 2010. This Exploration Cooperation Agreement with the NND was recently renewed and provides a framework within which exploration activities and environmental regulatory processes on ATAC's Rackla Gold Project have been and will continue to be carried out. The Rackla Gold Project lies exclusively within the Traditional Territory of the NND.

Going forward

The Company will continue with environmental baseline work and ongoing studies while it explores opportunities to advance or monetize the Tiger Deposit through sole development, joint venture or outright sale.

Project Mineral Resources

Gold occurs in both sulphide and oxide mineralization within the Tiger Deposit. The PEA considers the oxide portion of the deposit. The following two tables show the oxide only resource used for the PEA and the oxide plus sulphide resources for reference only.

Tiger Deposit Oxide Only Resource


----------------------------------------------------------------------------
                  Cut-off grade                         Grade         Ounces
Category             (g/t) (Au)         Tonnes     (g/t) (Au)           (Au)
----------------------------------------------------------------------------
Indicated                  1.60      2,470,000           4.25        337,500
----------------------------------------------------------------------------
Inferred                   1.60        180,000           3.00         17,400
----------------------------------------------------------------------------

Tiger Deposit Oxide Plus Sulphide Resource


----------------------------------------------------------------------------
                  Cut-off grade                         Grade         Ounces
Category             (g/t) (Au)         Tonnes     (g/t) (Au)           (Au)
----------------------------------------------------------------------------
Indicated                  1.60      3,260,000           3.85        403,500
----------------------------------------------------------------------------
Inferred                   1.60      1,570,000           2.44        123,200
----------------------------------------------------------------------------

The PEA is based on a 43-101 compliant mineral resource estimate completed by Gary Giroux, P.Eng., M.A.Sc. (Giroux Consultants Ltd.) who is a qualified person and independent of ATAC, based on the criteria defined by National Instrument 43-101. Quality control data generated during the various drill programs conducted at the Tiger Deposit were independently reviewed by Giroux Consultants Ltd. as part of the resource study. The full report dated effective November 15, 2011 and titled "Preparation of the Tiger Zone Mineral Resource Estimate" was filed on SEDAR (http://www.sedar.com/) December 1, 2011.

It should be noted that this PEA is preliminary in nature and includes inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves. There is no certainty that the PEA forecast will be realized or that any of the resources will ever be upgraded to reserves. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. A NI 43-101 technical report for the Tiger Deposit PEA will be filed on SEDAR (www.sedar.com) and ATAC's website (www.atacresources.com) within 45 days.

Qualified Persons

The independent qualified persons responsible for preparing the Tiger Deposit Preliminary Economic Assessment are Dan Kappes, P.Eng., of KCA, Sabry Abdel Hafez, Ph.D., P.Eng., of Tetra Tech, Gary Giroux, M.A.Sc., P.Eng., of Giroux Consultants Ltd., Rob McIntyre, R.E.T. of Resource Strategies and Gerald G. Carlson, Ph.D., P.Eng., an independent consultant. All of the aforementioned qualified persons have reviewed and approved the contents of this news release.

Robert C. Carne, M.Sc., P.Geo., the President and a Director of ATAC Resources Ltd., is the company's designated QP for this news release within the meaning of NI 43-101 and has reviewed and validated that the information contained in the release is consistent with that provided by the QPs responsible for the PEA.

About ATAC

ATAC Resources Ltd. is a Yukon-based exploration company focused on developing Canada's only Carlin-type gold district at its 100% owned Rackla Gold Project. Recent work on the 1,700 sq/km project has resulted in a positive Preliminary Economic Assessment for the Tiger Deposit, drilling of multiple high-grade Carlin-type gold zones and the identification of numerous early-stage gold exploration targets. The Rackla Gold Project has no underlying royalties or third-party interests. ATAC is well financed with approximately $23 million in its treasury.

On behalf of Management and the Board of Directors of ATAC Resources Ltd.,

Graham Downs, CEO

ATAC Resources Ltd.

NEITHER THE TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER (AS THAT TERM IS DEFINED IN THE POLICIES OF THE TSX VENTURE EXCHANGE) ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THIS NEWS RELEASE.

This news release contains forward-looking information. Forward-looking information contained in this news release includes, but is not limited to, statements with respect to: (i) the estimation of inferred and indicated mineral resources; (ii) the success of exploration activities; (iii) the results of the PEA including statements about future production, future operating and capital costs, the projected IRR, NPV, payback period, and production timelines for the Tiger Deposit.

These statements are based on information currently available to the Company and the Company provides no assurance that actual results will meet management's expectations. In certain cases, forward-looking information may be identified by such terms as "anticipates", "believes", "could", "estimates", "expects", "may", "shall", "will", or "would". Forward-looking information contained in this news release is based on certain factors and assumptions regarding, among other things, the estimation of mineral resources, the realization of resource estimate, gold metal prices, the timing and amount of future exploration and development expenditures, the estimation of initial and sustaining capital requirements, the estimation of labour and operating costs, the availability of necessary financing and materials to continue to explore and develop the Tiger Deposit in the short and long-term, the progress of exploration and development activities, the receipt of necessary regulatory approvals, the completion of the environmental assessment process, and assumptions with respect to currency fluctuations, environmental risks, title disputes or claims, and other similar matters. While the Company considers these assumptions to be reasonable based on information currently available to it, they may prove to be incorrect.

Forward-looking information involves known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any future results, performance or achievements expressed or implied by the forward-looking information. Such factors include risks inherent in the exploration and development of mineral deposits, including risks relating to changes in project parameters as plans continue to be redefined including the possibility that mining operations may not commence at the Tiger Deposit, risks relating to variations in mineral resources, grade or recovery rates resulting from current exploration and development activities, risks relating to changes in gold prices and the worldwide demand for and supply of gold, risks related to increased competition in the mining industry generally, risks related to current global financial conditions, uncertainties inherent in the estimation of mineral resources, access and supply risks, reliance on key personnel, operational risks inherent in the conduct of mining activities, including the risk of accidents, labour disputes, increases in capital and operating costs and the risk of delays or increased costs that might be encountered during the development process, regulatory risks, including risks relating to the acquisition of the necessary licenses and permits, financing, capitalization and liquidity risks, including the risk that the financing necessary to fund the exploration and development activities at the Tiger Deposit may not be available on satisfactory terms, or at all, risks related to disputes concerning property titles and interest, and environmental risks. This list is not exhaustive of the factors that may affect any of the Company's forward-looking information. These and other factors should be considered carefully and readers should not place undue reliance on the Company's forward-looking information. The Company does not undertake to update any forward-looking information that may be made from time to time by the Company or on its behalf, except in accordance with applicable securities laws.

Contacts:
Vanessa Pickering, Manager, Corporate Communications
ATAC Resources Ltd.
T: 604-687-2522 ext. 260
vpickering@atacresources.com

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
The Internet of Things can drive efficiency for airlines and airports. In their session at @ThingsExpo, Shyam Varan Nath, Principal Architect with GE, and Sudip Majumder, senior director of development at Oracle, discussed the technical details of the connected airline baggage and related social media solutions. These IoT applications will enhance travelers' journey experience and drive efficiency for the airlines and the airports.
In his keynote at @ThingsExpo, Chris Matthieu, Director of IoT Engineering at Citrix and co-founder and CTO of Octoblu, focused on building an IoT platform and company. He provided a behind-the-scenes look at Octoblu’s platform, business, and pivots along the way (including the Citrix acquisition of Octoblu).
SYS-CON Events announced today that CA Technologies has been named “Platinum Sponsor” of SYS-CON's 20th International Cloud Expo®, which will take place on June 6-8, 2017, at the Javits Center in New York City, NY, and the 21st International Cloud Expo®, which will take place October 31-November 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. CA Technologies helps customers succeed in a future where every business – from apparel to energy – is being rewritten by software. From ...
The explosion of new web/cloud/IoT-based applications and the data they generate are transforming our world right before our eyes. In this rush to adopt these new technologies, organizations are often ignoring fundamental questions concerning who owns the data and failing to ask for permission to conduct invasive surveillance of their customers. Organizations that are not transparent about how their systems gather data telemetry without offering shared data ownership risk product rejection, regu...
In his keynote at 18th Cloud Expo, Andrew Keys, Co-Founder of ConsenSys Enterprise, provided an overview of the evolution of the Internet and the Database and the future of their combination – the Blockchain. Andrew Keys is Co-Founder of ConsenSys Enterprise. He comes to ConsenSys Enterprise with capital markets, technology and entrepreneurial experience. Previously, he worked for UBS investment bank in equities analysis. Later, he was responsible for the creation and distribution of life settle...
In his keynote at @ThingsExpo, Chris Matthieu, Director of IoT Engineering at Citrix and co-founder and CTO of Octoblu, focused on building an IoT platform and company. He provided a behind-the-scenes look at Octoblu’s platform, business, and pivots along the way (including the Citrix acquisition of Octoblu).
In his general session at 18th Cloud Expo, Lee Atchison, Principal Cloud Architect and Advocate at New Relic, discussed cloud as a ‘better data center’ and how it adds new capacity (faster) and improves application availability (redundancy). The cloud is a ‘Dynamic Tool for Dynamic Apps’ and resource allocation is an integral part of your application architecture, so use only the resources you need and allocate /de-allocate resources on the fly.
Containers have changed the mind of IT in DevOps. They enable developers to work with dev, test, stage and production environments identically. Containers provide the right abstraction for microservices and many cloud platforms have integrated them into deployment pipelines. DevOps and Containers together help companies to achieve their business goals faster and more effectively. In his session at DevOps Summit, Ruslan Synytsky, CEO and Co-founder of Jelastic, reviewed the current landscape of D...
The best way to leverage your Cloud Expo presence as a sponsor and exhibitor is to plan your news announcements around our events. The press covering Cloud Expo and @ThingsExpo will have access to these releases and will amplify your news announcements. More than two dozen Cloud companies either set deals at our shows or have announced their mergers and acquisitions at Cloud Expo. Product announcements during our show provide your company with the most reach through our targeted audiences.
Security, data privacy, reliability and regulatory compliance are critical factors when evaluating whether to move business applications from in-house client hosted environments to a cloud platform. In her session at 18th Cloud Expo, Vandana Viswanathan, Associate Director at Cognizant, In this session, will provide an orientation to the five stages required to implement a cloud hosted solution validation strategy.
SYS-CON Events announced today that Outlyer, a monitoring service for DevOps and operations teams, has been named “Bronze Sponsor” of SYS-CON's 20th International Cloud Expo®, which will take place on June 6-8, 2017, at the Javits Center in New York City, NY. Outlyer is a monitoring service for DevOps and Operations teams running Cloud, SaaS, Microservices and IoT deployments. Designed for today's dynamic environments that need beyond cloud-scale monitoring, we make monitoring effortless so you...
Cloud Expo, Inc. has announced today that Andi Mann and Aruna Ravichandran have been named Co-Chairs of @DevOpsSummit at Cloud Expo 2017. The @DevOpsSummit at Cloud Expo New York will take place on June 6-8, 2017, at the Javits Center in New York City, New York, and @DevOpsSummit at Cloud Expo Silicon Valley will take place Oct. 31-Nov. 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA.
DevOps is being widely accepted (if not fully adopted) as essential in enterprise IT. But as Enterprise DevOps gains maturity, expands scope, and increases velocity, the need for data-driven decisions across teams becomes more acute. DevOps teams in any modern business must wrangle the ‘digital exhaust’ from the delivery toolchain, "pervasive" and "cognitive" computing, APIs and services, mobile devices and applications, the Internet of Things, and now even blockchain.
Column Technologies exhibited at SYS-CON's @DevOpsSummit at Cloud Expo, which took place at the Javits Center in New York City, NY, in June 2016. Established in 1998, Column Technologies is a global technology solutions provider with over 400 employees, headquartered in the United States with offices in Canada, India, and the United Kingdom. Column Technologies provides “Best of Breed” technology solutions that automate the key DevOps principals and help our customers meet today’s DevOps and Dig...
20th Cloud Expo, taking place June 6-8, 2017, at the Javits Center in New York City, NY, will feature technical sessions from a rock star conference faculty and the leading industry players in the world. Cloud computing is now being embraced by a majority of enterprises of all sizes. Yesterday's debate about public vs. private has transformed into the reality of hybrid cloud: a recent survey shows that 74% of enterprises have a hybrid cloud strategy.