Elgin Mining Provides Update and Enters into Amended and Restated Arrangement Agreement with Mandalay Resources

VANCOUVER, BRITISH COLUMBIA -- (Marketwired) -- 07/25/14 -- Elgin Mining Inc. ("Elgin Mining" or the "Company") (TSX: ELG) is pleased to provide the following update on the previously announced transaction with Mandalay Resources Corporation ("Mandalay") (TSX: MND). Elgin Mining has now reached a resolution on all outstanding reclamation obligations relating to its former coal operations in Kentucky, and these are to Mandalay's satisfaction. Elgin Mining has filed amended and restated interim financial statements and management's discussion and analysis for the three months ended March 31, 2014 to reflect this settlement. The parties have also entered into an amended and restated arrangement agreement ("Amended and Restated Arrangement Agreement") dated July 25, 2014 with respect to the previously announced acquisition by Mandalay of all the outstanding common shares of Elgin Mining for consideration consisting of C$0.37 cash or 0.4111 of a Mandalay common share per Elgin Mining common share, subject to pro ration, by way of plan of arrangement (the "Arrangement").

The Amended and Restated Arrangement Agreement increases the amount of cash consideration available to C$27 million (from C$25 million as previously disclosed) in order to accommodate any exercise of Elgin Mining's outstanding share purchase warrants ("Warrants") as a result of Elgin Mining's acceleration of the expiry date of its Warrants to August 26, 2014. As a result of such acceleration, no Warrants will be outstanding after the close of business on August 26, 2014.

Q2-2014 Gold Production

The Bjorkdal mine had an excellent second quarter of production of 12,098 ounces of gold. Production was from the processing of a mix of open pit and underground ores. Gold production for Q3-2014 also started strongly in July, which is normally a low month for gold and ore production due to the vacation period in Sweden reducing the availability of both Company miners and mine contractors.

Shareholders' Meeting

Elgin's shareholders' meeting (the "Meeting") to approve the Arrangement is scheduled to occur on Wednesday, September 3, 2014 at 8:00 am EDT at the offices of Cassels Brock & Blackwell LLP, Scotia Plaza, 40 King Street West, Suite 2100, Toronto, Ontario. Relevant Meeting materials providing further details of the transaction are expected to be mailed on August 1, 2014. Assuming receipt of all necessary court and shareholder approvals and the satisfaction of all other conditions, closing is expected to occur on or about September 10, 2014.

Revised Interim Financial Reports for the Three Months ended March 31, 2014

The Company's previously filed interim financial statements for the three months ended March 31, 2014 reflected a provision for reclamation and closure for its former US coal operations in the amount of US$2,562,834. This reclamation estimate was based on the amount of reclamation bonds posted by the Company and held by the state of Kentucky as financial security for the performance of the Company's required reclamation activities.

Since April 2014, the Company has been working with an experienced local consultant and external counsel to reach a settlement whereby the Company would achieve a full and final release of all remaining coal reclamation obligations. The final amounts of the reclamation settlements with both the state of Kentucky and the US Army Corps of Engineers, and including consultant fees, are expected to total US$10,364,567. The Company has determined that the dollar amount of the settlements reached with the respective US government agencies provide a better estimate of the Company's reclamation liabilities that existed at March 31, 2014 than the amount previously provided for in the interim financial statements which were filed on May 13, 2014.

As a result, the Company has amended and restated its interim financial statements and management's discussion and analysis for the three months ended March 31, 2014 to increase its coal reclamation liability to the expected costs of the settlements of US$10,364,567, and to include disclosure of events occurring subsequent to the date of the filings on May 13, 2014.

Elgin Mining Inc.

Elgin Mining is a Canadian based company focused on production at the Bjorkdal gold mine in Sweden. In addition, Elgin Mining's portfolio includes the Lupin and Ulu gold projects located in Nunavut, Canada.

For further information, please visit the Company's web site at www.elginmining.com.

Forward-Looking Statements

This news release contains forward-looking statements within the meaning of securities legislation and which are based on the expectations, estimates and projections of management of Elgin as of the date of this news release unless otherwise stated. Forward-looking statements are generally identifiable by use of the words "expect", "anticipate", "continue", "estimate", "objective", "ongoing", "may", "will", "project", "should", "believe", "plans", "intends" or the negative of these words or other variations on these words or comparable terminology. More particularly, and without limitation, this news release contains forward-looking statements and information concerning expectations regarding the consideration to be issued pursuant to the transaction, the ability of Elgin to consummate the transaction on the terms and in the manner contemplated thereby and the expected timing of the closing of the Arrangement. Such forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause actual results, performance or achievements to be materially different from any future results, performance or achievements expressed or implied by the forward-looking statements. Such factors include, among others, the time required to prepare and mail meeting materials to Elgin shareholders, the ability of the parties to receive, in a timely manner and on satisfactory terms, the necessary court, shareholder, stock exchange and regulatory approvals and the ability of the parties to satisfy, in a timely manner, the conditions to the closing of the transaction, as well as other uncertainties and risk factors set out in filings made from time to time by Elgin with the Canadian securities regulators, including, without limitation, Elgin's annual information form dated March 21, 2014, which is available on SEDAR at www.sedar.com. Actual results, developments and timetables could vary significantly from the estimates presented. Readers are cautioned not to put undue reliance on forward-looking statements.

Contacts:
Elgin Mining Inc.
Patrick Downey
President and Chief Executive Officer
(604) 682-3366
(604) 682-3363 (FAX)
[email protected]
www.elginmining.com

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
With more than 30 Kubernetes solutions in the marketplace, it's tempting to think Kubernetes and the vendor ecosystem has solved the problem of operationalizing containers at scale or of automatically managing the elasticity of the underlying infrastructure that these solutions need to be truly scalable. Far from it. There are at least six major pain points that companies experience when they try to deploy and run Kubernetes in their complex environments. In this presentation, the speaker will d...
Dhiraj Sehgal works in Delphix's product and solution organization. His focus has been DevOps, DataOps, private cloud and datacenters customers, technologies and products. He has wealth of experience in cloud focused and virtualized technologies ranging from compute, networking to storage. He has spoken at Cloud Expo for last 3 years now in New York and Santa Clara.
Enterprises are striving to become digital businesses for differentiated innovation and customer-centricity. Traditionally, they focused on digitizing processes and paper workflow. To be a disruptor and compete against new players, they need to gain insight into business data and innovate at scale. Cloud and cognitive technologies can help them leverage hidden data in SAP/ERP systems to fuel their businesses to accelerate digital transformation success.
Daniel Jones is CTO of EngineerBetter, helping enterprises deliver value faster. Previously he was an IT consultant, indie video games developer, head of web development in the finance sector, and an award-winning martial artist. Continuous Delivery makes it possible to exploit findings of cognitive psychology and neuroscience to increase the productivity and happiness of our teams.
When building large, cloud-based applications that operate at a high scale, it's important to maintain a high availability and resilience to failures. In order to do that, you must be tolerant of failures, even in light of failures in other areas of your application. "Fly two mistakes high" is an old adage in the radio control airplane hobby. It means, fly high enough so that if you make a mistake, you can continue flying with room to still make mistakes. In his session at 18th Cloud Expo, Le...
Machine learning has taken residence at our cities' cores and now we can finally have "smart cities." Cities are a collection of buildings made to provide the structure and safety necessary for people to function, create and survive. Buildings are a pool of ever-changing performance data from large automated systems such as heating and cooling to the people that live and work within them. Through machine learning, buildings can optimize performance, reduce costs, and improve occupant comfort by ...
DevOps tends to focus on the relationship between Dev and Ops, putting an emphasis on the ops and application infrastructure. But that’s changing with microservices architectures. In her session at DevOps Summit, Lori MacVittie, Evangelist for F5 Networks, will focus on how microservices are changing the underlying architectures needed to scale, secure and deliver applications based on highly distributed (micro) services and why that means an expansion into “the network” for DevOps.
Sanjeev Sharma Joins November 11-13, 2018 @DevOpsSummit at @CloudEXPO New York Faculty. Sanjeev Sharma is an internationally known DevOps and Cloud Transformation thought leader, technology executive, and author. Sanjeev's industry experience includes tenures as CTO, Technical Sales leader, and Cloud Architect leader. As an IBM Distinguished Engineer, Sanjeev is recognized at the highest levels of IBM's core of technical leaders.
René Bostic is the Technical VP of the IBM Cloud Unit in North America. Enjoying her career with IBM during the modern millennial technological era, she is an expert in cloud computing, DevOps and emerging cloud technologies such as Blockchain. Her strengths and core competencies include a proven record of accomplishments in consensus building at all levels to assess, plan, and implement enterprise and cloud computing solutions. René is a member of the Society of Women Engineers (SWE) and a m...
Containers and Kubernetes allow for code portability across on-premise VMs, bare metal, or multiple cloud provider environments. Yet, despite this portability promise, developers may include configuration and application definitions that constrain or even eliminate application portability. In this session we'll describe best practices for "configuration as code" in a Kubernetes environment. We will demonstrate how a properly constructed containerized app can be deployed to both Amazon and Azure ...
Bill Schmarzo, author of "Big Data: Understanding How Data Powers Big Business" and "Big Data MBA: Driving Business Strategies with Data Science" is responsible for guiding the technology strategy within Hitachi Vantara for IoT and Analytics. Bill brings a balanced business-technology approach that focuses on business outcomes to drive data, analytics and technology decisions that underpin an organization's digital transformation strategy.
Poor data quality and analytics drive down business value. In fact, Gartner estimated that the average financial impact of poor data quality on organizations is $9.7 million per year. But bad data is much more than a cost center. By eroding trust in information, analytics and the business decisions based on these, it is a serious impediment to digital transformation.
DXWorldEXPO LLC announced today that Ed Featherston has been named the "Tech Chair" of "FinTechEXPO - New York Blockchain Event" of CloudEXPO's 10-Year Anniversary Event which will take place on November 12-13, 2018 in New York City. CloudEXPO | DXWorldEXPO New York will present keynotes, general sessions, and more than 20 blockchain sessions by leading FinTech experts.
Apps and devices shouldn't stop working when there's limited or no network connectivity. Learn how to bring data stored in a cloud database to the edge of the network (and back again) whenever an Internet connection is available. In his session at 17th Cloud Expo, Ben Perlmutter, a Sales Engineer with IBM Cloudant, demonstrated techniques for replicating cloud databases with devices in order to build offline-first mobile or Internet of Things (IoT) apps that can provide a better, faster user e...
In this presentation, you will learn first hand what works and what doesn't while architecting and deploying OpenStack. Some of the topics will include:- best practices for creating repeatable deployments of OpenStack- multi-site considerations- how to customize OpenStack to integrate with your existing systems and security best practices.