Detour Gold Reports Second Quarter 2014 Results

TORONTO, ONTARIO -- (Marketwired) -- 07/29/14 -- Detour Gold Corporation (TSX:DGC) ("Detour Gold" or the "Company") reports its operational and financial results for the second quarter of 2014. This release should be read in conjunction with the Company's second quarter 2014 financial statements and MD&A report on the Company's website or on SEDAR. All amounts are in U.S. dollars unless otherwise indicated.

Q2 2014 Highlights


--  Gold production of 117,366 ounces 
--  Revenues of $139 million on gold sales of 107,206 ounces 
--  Total cash costs of $941 per gold ounce sold(1) 
--  Net loss of $35.0 million or $0.23 per share; Adjusted net loss of $17.4
    million or $0.12 per share(1) 
--  Cash and short-term investments balance of $138.2 million at June 30,
    2014 
--  High grade gold intersections reported from Lower Detour area 

"Operationally, we made good progress in the second quarter and attained the upper end of our production guidance for the first half of the year at 224,520 ounces of gold," said Paul Martin, President and CEO. "We realized higher grades than planned which compensated for the slightly slower ramp-up progress during the first half of the year. For the remainder of 2014, we project a similar rate of progress and have consequently trimmed the high end of our 2014 production guidance by 20,000 ounces to 480,000 ounces while maintaining the lower end at 450,000 ounces. We have also revised our 2014 total cash cost guidance range to be between $900 and $975 per ounce sold(1). We remain focused on execution and continue to expect reaching mill design capacity of 55,000 tonnes per day by year-end."

Summary Operational Results

In the second quarter of 2014, gold production totaled 117,366 ounces, driven primarily by higher gold grades due to improved dilution control. The mill processed 4.4 million tonnes (Mt) of ore from a combination of direct feed (65%) and run-of-mine stockpiles (35%) at an average grade of 0.91 g/t with recoveries of 91%. At quarter-end, the run-of-mine ore stockpiles were 1.3 Mt grading 0.76 grams per tonne (g/t).

The mill facility processed an average of 48,569 tonnes of ore per day (tpd) in the second quarter with 83% availability, approximately 4% higher than the first quarter but at the low end of expectations for the quarter.

A total of 19.0 Mt was mined during the second quarter with mining rates averaging 209,000 tpd, below projected rates of 230,000 tpd. Mining activities were heavily weighted on overburden and waste stripping, mainly for the development of the southwall pushback and Campbell pit breakthrough (western end of former open pit). Due to the reduced productivity in mining overburden and till and removing old infrastructure around the former Campbell pit, mining rates were lower than initially planned. With the overburden and till stripping decreasing significantly in the second half of 2014 (from 12.1 Mt to approximately 4.6 Mt), mining rates are expected to increase to 250,000 tpd by year-end.

(1) Refer to the section on Non-IFRS Financial Performance Measures at end of the press release. Reconciliation of these measures is described at end of the press release and in the MD&A for the second quarter ended June 30, 2014.

The development of the southwall pushback is expected to be completed in the third quarter and tailings construction activities remain on schedule.

Although the operation is making positive progress quarter over quarter, the ramp-up is slightly behind schedule as of the end of June. For the second half of 2014, the forecasted mining and mill throughput rates have been adjusted downwards thereby lowering the high-end of production guidance by approximately 20,000 ounces of gold for the year (see page 4 - section entitled '2014 Outlook and Updated Guidance').

Total cash costs for the second quarter of 2014 were $941 per ounce sold(2), 4% lower than Q1 but above plan, mainly due to (1) fewer tonnes mined resulting in less ore stockpiled which would have reduced reportable costs and (2) higher unit costs during the ramp-up period.


                                                                            
Detour Lake Mine Operation Statistics                                       
                                                                            
                                 Q2 2013  Q3 2013  Q4 2013  Q1 2014  Q2 2014
----------------------------------------------------------------------------
Ore mined (Mt)                      2.70     4.16     4.09     4.88     2.89
Waste mined (Mt)                    9.96    12.42    16.80    14.29    16.11
Total mined (Mt)                   12.66    16.58    20.89    19.17    19.00
Strip ratio (waste:ore)              3.7      3.0      4.1      2.9      5.6
Mining rate (tpd)                160,000  180,000  203,000  213,000  209,000
                                                                            
Ore milled (Mt)                     2.87     3.88     3.41     4.08     4.42
Head grade (g/t Au)                 0.76     0.72     0.81     0.90     0.91
Recovery (%)                          82       85       92       91       91
Mill throughput (tpd)             31,513   42,141   37,090   45,282   48,569
Mill availability (%)                 68       78       66       80       83
Ounces produced(1) (oz)           57,897   75,672   81,877  107,154  117,366
Ounces sold (oz)                  37,870   75,600   95,000   84,560  107,206
                                                                            
Average realized price(2)                                                   
 ($/oz)                                -   $1,340   $1,269   $1,301   $1,293
Total cash cost per oz sold(2)                                              
 ($/oz)                                -   $1,214   $1,174     $976     $941
                                                                            
Mining (Cdn$/t mined)                  -        -    $2.60    $2.87    $2.87
Milling (Cdn$/t milled)                -        -   $11.75   $11.13   $11.25
G&A (Cdn$/t milled)(3)                 -        -    $4.13    $3.68    $3.46
----------------------------------------------------------------------------
                                                                            

Unit mining costs were higher than plan due to the shortfall in total tonnes mined and higher equipment maintenance costs. Unit milling costs were also slightly higher than plan mainly due to higher maintenance costs and lower mill throughput partially offset by lower consumables and reagent consumption. With further improvements expected in mine and mill throughput rates, unit operating costs are projected to trend downward.

(1) Includes pre-production ounces prior to the declaration of commercial production on September 1, 2013.

(2) Refer to the section on Non-IFRS Financial Performance Measures at end of the press release. Reconciliation of these measures is described at end of the press release and in the MD&A for the relevant periods.

(3) G&A costs include site G&A, infrastructure, environmental and Aboriginal costs.


                                                                            
2014 Selected Financial Information                                         
                                                                            
Summary Financial Data                                                      
(in millions unless specified)   Q2 2013  Q3 2013  Q4 2013  Q1 2014  Q2 2014
----------------------------------------------------------------------------
Metal sales(1)                         -     33.1    120.8    110.0    139.0
 Production costs                      -     30.4     98.0     83.1     98.1
 Depreciation and depletion            -      2.9     34.0     30.6     38.3
 Mine standby costs                    -        -      4.2        -        -
 Inventory write-down                  -        -     14.6        -        -
Cost of sales                          -     33.3    150.8    113.7    136.4
Earnings (loss) from mine                                                   
 operations                            -    (0.2)   (30.0)    (3.7)    (2.6)
                                                                            
Net earnings (loss)                 23.1   (11.8)   (47.0)   (54.9)   (35.0)
Net earnings (loss) per share       0.19   (0.09)   (0.34)   (0.38)   (0.23)
Adjusted net loss(2)              (11.8)   (10.6)   (36.0)   (28.1)   (17.4)
Adjusted net loss per share(2)    (0.10)   (0.08)   (0.26)   (0.20)   (0.12)
----------------------------------------------------------------------------
                                                                            
Note: Totals may not add up due to rounding.                                
                                                                            

Summary Financial Results

Revenues for the second quarter were $139.0 million from the sales of 107,206 ounces of gold at an average realized price of $1,293 per ounce(2) versus the average London PM fix gold price of $1,288 per ounce.

Cost of sales excluding depreciation and depletion for the second quarter amounted to $98.1 million and is net of a $3.9 million rebate relating to 2013 electricity costs. Depreciation and depletion expense for the quarter was $38.3 million, or $357 per ounce of gold sold.

The Company recorded a net loss of $35.0 million, or $0.23 per share, in the second quarter of 2014. The net loss includes $63.5 million of non-cash items, including depreciation and depletion of $38.3 million, a fair value loss on the convertible notes of $15.1 million as a result of share price appreciation, accretion charges related to the convertible notes of $6.2 million, an unrealized loss on derivative instruments of $1.2 million and non-cash share-based compensation expense of $2.7 million. Adjusted net loss(2) in the second quarter amounted to $17.4 million, or $0.12 per share, attributable to higher cost of sales during the mine ramp-up to full production levels.

Operating cash flow before changes in working capital for the three months ended June 30, 2014 was $38.8 million. During the quarter, sustaining capital expenditures totaled $27.1 million of which $6.2 million was on the tailings dam construction raise, $2.4 million on the processing plant, $16.0 million on mine equipment, and $2.5 million for other. Cash deferred stripping totaled $15.1 million.

Cash and short term investments were $138.2 million at June 30, 2014, approximately $7.0 million lower than the previous quarter.

In early 2014, the Company signed a 6-year fixed rate electricity contract with the Ontario Power Authority. At June 30, 2014, the Company had accrued $26.4 million as electricity rebate receivable for charges paid in 2013 and the first half of 2014. In July 2014, the Company received $16.0 million and expects to receive the remainder over the course of 2014.

(1) Sales prior to commercial production (September 1, 2013) were credited against capitalized project costs. Includes silver sales.

(2) Refer to the section on Non-IFRS Financial Performance Measures at end of the press release. Reconciliation of these measures is described at end of the press release and in the MD&A for the relevant periods.

In July 2014, the Company amended its existing credit facility to extend the date by which the Completion Test (as set out section "Liquidity and Capital Resources" in Second Quarter 2014 MD&A) must be achieved from September 30, 2014 to May 31, 2015.

During the second quarter, the Company realized a net gain of $1.8 million on its gold sales and foreign exchange risk management programs. The Company has a total of 100,000 ounces of gold hedged at an average price of $1,287 per ounce for its gold sales from August to December 2014.

2014 Outlook and Updated Guidance

In the first half of 2014, the Company continued to make progress towards completing the ramp-up of the Detour Lake mine. Detour Gold met the high end of its gold production guidance for the first half of the year, despite the mine ramp-up proceeding slightly below plan.

Based on both the throughput and mining rates being below target levels at the end of the quarter, the Company has revised its mine output from 92 Mt to 82 Mt and mill output from 19 Mt to 17.7 Mt for 2014. As a result, the Company does not expect to reach the upper end of its production guidance of 500,000 ounces for 2014 and has revised it downward to 480,000 ounces with the low end remaining at 450,000 ounces. With this updated production range, combined with an increase in forecasted operating costs, total cash costs for 2014 have been revised from $800 to $900 per ounce sold(1)to $900 to $975 per ounce sold(1). The Company continues to expect that mill design capacity (55,000 tpd) will be attained by year-end.

Sustaining capital expenditures for the year are expected to range between $125 and $135 million, including no change to deferred stripping of $35 million.


                                                  2014                  2014
                                        Prior Guidance      Updated Guidance
============================================================================
Total gold production (oz)             450,000-500,000       450,000-480,000
----------------------------------------------------------------------------
Total cash costs ($/oz sold)(1)               $800-900              $900-975
----------------------------------------------------------------------------
Sustaining capital expenditures                                             
 ($ millions)(2)                                  $131              $125-135
----------------------------------------------------------------------------

For 2014, the Company targets to maintain a minimum of $100 million in cash and short term investments. As a result, our discretionary debt reduction program will be based on gold price and mine performance. With the high-end of the production guidance lowered, the Company is targeting debt repayment of up to $80 million in 2014.

Although the Company remains focused on the mine ramp-up, it is continuing to advance its organic growth and optimization initiatives:


--  Mineral reserve estimation of Block A for 2014 year-end reserve update 
--  Amenability to heap leaching underway to evaluate potential to process
    low-grade material 
--  Assessment to potentially remove the pebble crushing circuit 
--  Further evaluation of Lower Detour area (high-grade intersections in
    Zone 58) 
--  Exploration plan for 2015 winter drilling program in progress 

(1) Refer to the section on Non-IFRS Financial Performance Measures at end of the press release.

(2) Include deferred stripping costs of approximately $35 million.

Technical Information

The scientific and technical content of this news release has been reviewed, verified and approved by Drew Anwyll, P.Eng., Vice President of Operations, a Qualified Person as defined by Canadian Securities Administrators National Instrument 43-101 "Standards of Disclosure for Mineral Projects".

Conference Call

The Company will host a conference call on Wednesday, July 30, 2014 at 10:00 AM E.T. where senior management will discuss the second quarter operational and financial results. The details of the conference call are as follows:


--  Via webcast, go to www.detourgold.com and click on the "Q2 Results
    Conference Call and Webcast" link on home page 
--  By phone toll free in Canada and the United states 1-800-319-4610 
--  By phone International 416-915-3239 

The conference call will be recorded and playback of the call will be available after the event by dialing toll free in Canada and the United States 1-800-319-6413, or internationally 604-638-9010, pass code 1532 (available up to August 31, 2014).

About Detour Gold

Detour Gold is an emerging mid-tier gold producer in Canada. The Company is currently completing the ramp-up of its 100% owned Detour Lake mine to a long life, large scale open pit operation.

Detour Gold Corporation, Royal Bank Plaza, South Tower, 200 Bay Street, Suite 2200, Toronto, Ontario M5J 2J1

Non-IFRS Financial Performance Measures

The Company has included certain non-IFRS measures in this press release. The Company believes that these measures, in addition to conventional measures prepared in accordance with IFRS, provide investors an improved ability to evaluate the underlying performance of the Company. The non-IFRS measures are intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. These measures do not have any standardized meaning prescribed under IFRS, and therefore may not be comparable to other issuers.

The non-IFRS measures are defined below and are reconciled with the reported IFRS measures. Refer to the Company's MD&A for the three and six months ended June 30, 2014 for full details.

Total cash costs per gold ounce sold

Detour Gold reports total cash costs on a sales basis. Total cash costs per gold ounce sold include production costs such as mining, processing, refining and site administration, agreements with Aboriginal communities, less non-cash share-based compensation and net of silver sales divided by gold ounces sold to arrive at total cash costs per gold ounce sold. The measure also includes other mine related costs incurred such as mine standby costs and current inventory write downs. Production costs are exclusive of depreciation and depletion. Production costs include the costs associated with providing the royalty in kind ounces. The Company did not include the positive impact of the electricity rebate in calculating total cash costs per ounce sold.


                                                                            
                                  Three months ended        Six months ended
                                             June 30                 June 30
                            ------------------------------------------------
                                    2014        2013        2014        2013
----------------------------------------------------------------------------
                                                                            
Production costs             $    98,141 $         - $   181,273 $         -
Share-based compensation           (862)           -     (1,489)           -
Silver sales                       (370)           -       (376)           -
Electricity rebate                 3,930                   3,930            
                            ------------------------------------------------
Total cash costs             $   100,839 $         - $   183,338 $         -
Gold ounces sold                 107,206           -     191,766           -
                            ------------------------------------------------
Total cash costs per gold                                                   
 ounce sold                  $       941 $         - $       956 $         -
----------------------------------------------------------------------------
                                                                            

Average realized price and Average realized margin

Management and investors use these measures to better understand the gold price and margin realized throughout a period. Average realized margin represents average realized price per gold ounce sold less total cash costs per gold ounce sold.


                                                                            
                                        Three months                        
                                               ended        Six months ended
                                             June 30                 June 30
                            ------------------------------------------------
                                    2014        2013        2014        2013
----------------------------------------------------------------------------
                                                                            
Metal sales                  $   139,009 $         - $   249,024 $         -
Silver sales                       (370)           -       (376)           -
                            ------------------------------------------------
Revenues from gold sales     $   138,639 $         - $   248,648 $         -
Gold ounces sold                 107,206           -     191,766           -
                            ------------------------------------------------
Average realized price       $     1,293 $         - $     1,297 $         -
Less: Total cash costs per                                                  
 gold ounce sold                   (941)           -       (956)           -
                            ------------------------------------------------
Average realized margin per                                                 
 gold ounce sold             $       352 $         - $       341 $         -
----------------------------------------------------------------------------
                                                                            

Adjusted net earnings (loss) and Adjusted basic net earnings (loss) per share

Adjusted net earnings (loss) and adjusted basic earnings (loss) per share are used by management and investors to measure the underlying operating performance of the Company. Presenting these measures from period to period helps management and investors evaluate earnings trends more readily in comparison with results from prior periods.

Adjusted net earnings (loss) are defined as net earnings (loss) adjusted to exclude specific items that are significant, but not reflective of the underlying operations of the Company, including: fair value change of the convertible notes; the impact of foreign exchange gains and losses, non-cash unrealized gains and losses on derivative instruments including hedges, accretion on convertible notes, unwinding of discount on decommissioning and restoration provisions, impairment provisions and reversals thereof; and other non-recurring items. Adjusted net earnings (loss) excludes the positive impact of the electricity rebate related to the Company's 2013 electricity usage

Adjusted net earnings (loss) per share is calculated using the weighted average number of share outstanding under the basic method of earnings (loss) per share as determined under IFRS.


                                                                            
                                  Three months ended        Six months ended
                                             June 30                 June 30
                            ------------------------------------------------
                                    2014        2013        2014        2013
----------------------------------------------------------------------------
                                                                            
Net earnings (loss)          $  (35,037) $    23,097 $  (89,980) $    46,510
Adjusted for:                                                               
 Fair value (gain) loss of                                                  
  the convertible notes           15,103    (40,695)      31,582    (79,330)
 Foreign exchange (gain)                                                    
  loss                             (989)       5,791       (916)       8,074
 Non-cash unrealized (gain)                                                 
  loss on derivative                                                        
 instruments                       1,228           -       5,480           -
 Accretion on convertible                                                   
  notes                            6,181           -      12,134           -
 Unwinding of discount on                                                   
  decommissioning and                                                       
 restoration provisions               74          38         168          69
 Electricity rebate              (3,930)           -     (3,930)           -
                            ------------------------------------------------
Adjusted net earnings (loss) $  (17,370) $  (11,769) $  (45,462) $  (24,677)
                                                                            
Adjusted basic earnings                                                     
 (loss) per share            $    (0.12) $    (0.10) $    (0.29) $    (0.20)
----------------------------------------------------------------------------
                                                                            

The Company has included the additional IFRS measure "Earnings (loss) from mine operations" in this press release. Management noted that "Earnings (loss) from mine operations" provides useful information to investors as an indication of the Company's principal business activities before consideration of how those activities are financed, sustaining capital expenditures, corporate and exploration and evaluation expenses, finance income and costs, and taxation.

Forward-Looking Information

This press release contains certain forward-looking information as defined in applicable securities laws (referred to herein as "forward-looking statements"). Specifically, this press release contains forward-looking statements regarding 2014 production of between 450,000 and 480,000 ounces; 2014 total cash costs of between $900 and $975 per ounce sold; reaching mill design capacity of 55,000 tonnes per day by year-end; an increase in mining rates to 250,000 tpd by year-end; completion of the development of the southwall pushback in the third quarter of 2014; a continuing downward trend in unit operating costs; mine output of 82 Mt and mill output of 17.7 Mt in 2014; sustaining capital expenditures for 2014 of between $125 and $135 million for 2014; maintaining a minimum of $100 million in cash and short term investments; repaying up to $80 million of debt in 2014; and continuing to advance certain organic growth and optimization initiatives in 2014.

Forward-looking statements involve known and unknown risks, uncertainties and other factors which are beyond Detour Gold's ability to predict or control and may cause Detour Gold's actual results, performance or achievements to be materially different from any of its future results, performance or achievements expressed or implied by forward-looking statements. These risks, uncertainties and other factors include, but are not limited to, gold price volatility, changes in debt and equity markets, the uncertainties involved in interpreting geological data, increases in costs, environmental compliance and changes in environmental legislation and regulation, interest rate and exchange rate fluctuations, general economic conditions and other risks involved in the gold exploration and development industry, as well as those risk factors discussed in the section entitled "Description of Business - Risk Factors" in Detour Gold's 2013 AIF and in the continuous disclosure documents filed by Detour Gold on and available on SEDAR at www.sedar.com. Such forward-looking statements are also based on a number of assumptions which may prove to be incorrect, including, but not limited to, assumptions about the following: the availability of financing for exploration and development activities; operating and capital costs; the Company's ability to attract and retain skilled staff; the mine development schedule; sensitivity to metal prices and other sensitivities; the supply and demand for, and the level and volatility of the price of, gold; timing of the receipt of regulatory and governmental approvals for development projects and other operations; the supply and availability of consumables and services; the exchange rates of the Canadian dollar to the U.S. dollar; energy and fuel costs; the accuracy of reserve and resource estimates and the assumptions on which the reserve and resource estimates are based; market competition; ongoing relations with employees and impacted communities and general business and economic conditions. Accordingly, readers should not place undue reliance on forward-looking statements. The forward-looking statements contained herein are made as of the date hereof, or such other date or dates specified in such statements. Detour Gold undertakes no obligation to update publicly or otherwise revise any forward-looking statements contained herein whether as a result of new information or future events or otherwise, except as may be required by law. If the Company does update one or more forward-looking statements, no inference should be drawn that it will make additional updates with respect to those or other forward-looking statements.

Contacts:
Detour Gold Corporation
Paul Martin
President and CEO
(416) 304.0800

Detour Gold Corporation
Laurie Gaborit
Director Investor Relations
(416) 304.0581

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
As ridesharing competitors and enhanced services increase, notable changes are occurring in the transportation model. Despite the cost-effective means and flexibility of ridesharing, both drivers and users will need to be aware of the connected environment and how it will impact the ridesharing experience. In his session at @ThingsExpo, Timothy Evavold, Executive Director Automotive at Covisint, will discuss key challenges and solutions to powering a ride sharing and/or multimodal model in the a...
SYS-CON Events announced today that Commvault, a global leader in enterprise data protection and information management, has been named “Bronze Sponsor” of SYS-CON's 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. Commvault is a leading provider of data protection and information management solutions, helping companies worldwide activate their data to drive more value and business insight and to transform moder...
Creating replica copies to tolerate a certain number of failures is easy, but very expensive at cloud-scale. Conventional RAID has lower overhead, but it is limited in the number of failures it can tolerate. And the management is like herding cats (overseeing capacity, rebuilds, migrations, and degraded performance). Download Slide Deck: ▸ Here In his general session at 18th Cloud Expo, Scott Cleland, Senior Director of Product Marketing for the HGST Cloud Infrastructure Business Unit, discusse...
Whether they’re located in a public, private, or hybrid cloud environment, cloud technologies are constantly evolving. While the innovation is exciting, the end mission of delivering business value and rapidly producing incremental product features is paramount. In his session at @DevOpsSummit at 19th Cloud Expo, Kiran Chitturi, CTO Architect at Sungard AS, will discuss DevOps culture, its evolution of frameworks and technologies, and how it is achieving maturity. He will also cover various st...
SYS-CON Events announced today that eCube Systems, a leading provider of middleware modernization, integration, and management solutions, will exhibit at @DevOpsSummit at 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. eCube Systems offers a family of middleware evolution products and services that maximize return on technology investment by leveraging existing technical equity to meet evolving business needs. ...
All clouds are not equal. To succeed in a DevOps context, organizations should plan to develop/deploy apps across a choice of on-premise and public clouds simultaneously depending on the business needs. This is where the concept of the Lean Cloud comes in - resting on the idea that you often need to relocate your app modules over their life cycles for both innovation and operational efficiency in the cloud. In his session at @DevOpsSummit at19th Cloud Expo, Valentin (Val) Bercovici, CTO of So...
What are the new priorities for the connected business? First: businesses need to think differently about the types of connections they will need to make – these span well beyond the traditional app to app into more modern forms of integration including SaaS integrations, mobile integrations, APIs, device integration and Big Data integration. It’s important these are unified together vs. doing them all piecemeal. Second, these types of connections need to be simple to design, adapt and configure...
Digital innovation is the next big wave of business transformation based on digital technologies of which IoT and Big Data are key components, For example: Business boundary innovation is a challenge to excavate third-party business value using IoT and BigData, like Nest Business structure innovation may propose re-building business structure from scratch, as Uber does in the taxicab industry The social model innovation is also a big challenge to the new social architecture with the design fr...
Cloud computing is being adopted in one form or another by 94% of enterprises today. Tens of billions of new devices are being connected to The Internet of Things. And Big Data is driving this bus. An exponential increase is expected in the amount of information being processed, managed, analyzed, and acted upon by enterprise IT. This amazing is not part of some distant future - it is happening today. One report shows a 650% increase in enterprise data by 2020. Other estimates are even higher....
A strange thing is happening along the way to the Internet of Things, namely far too many devices to work with and manage. It has become clear that we'll need much higher efficiency user experiences that can allow us to more easily and scalably work with the thousands of devices that will soon be in each of our lives. Enter the conversational interface revolution, combining bots we can literally talk with, gesture to, and even direct with our thoughts, with embedded artificial intelligence, wh...
Data is an unusual currency; it is not restricted by the same transactional limitations as money or people. In fact, the more that you leverage your data across multiple business use cases, the more valuable it becomes to the organization. And the same can be said about the organization’s analytics. In his session at 19th Cloud Expo, Bill Schmarzo, CTO for the Big Data Practice at EMC, will introduce a methodology for capturing, enriching and sharing data (and analytics) across the organizati...
SYS-CON Events has announced today that Roger Strukhoff has been named conference chair of Cloud Expo and @ThingsExpo 2016 Silicon Valley. The 19th Cloud Expo and 6th @ThingsExpo will take place on November 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. "The Internet of Things brings trillions of dollars of opportunity to developers and enterprise IT, no matter how you measure it," stated Roger Strukhoff. "More importantly, it leverages the power of devices and the Interne...
SYS-CON Events announced today that Bsquare has been named “Silver Sponsor” of SYS-CON's @ThingsExpo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. For more than two decades, Bsquare has helped its customers extract business value from a broad array of physical assets by making them intelligent, connecting them, and using the data they generate to optimize business processes.
We’ve been doing it for years, decades for some. How many websites have you created accounts on? Your bank, your credit card companies, social media sites, hotels and travel sites, online shopping sites, and that’s just the start. We do it often without even thinking about it, quickly entering our personal information, our data, in a plethora of systems. Sometimes we’re not even aware of the information we are providing. It could be very personal information (think of the security questions you ...
19th Cloud Expo, taking place November 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA, will feature technical sessions from a rock star conference faculty and the leading industry players in the world. Cloud computing is now being embraced by a majority of enterprises of all sizes. Yesterday's debate about public vs. private has transformed into the reality of hybrid cloud: a recent survey shows that 74% of enterprises have a hybrid cloud strategy. Meanwhile, 94% of enterpri...