Focus Graphite Files Lac Knife Graphite Project Feasibility Study Technical Report

Weighs lower-cost options for tandem financing of mine/plant and purification facilities for high value "battery grade" graphite production

OTTAWA, ONTARIO -- (Marketwired) -- 08/08/14 -- Focus Graphite Inc. ("Focus" or the "Company") (TSX VENTURE:FMS)(OTCQX:FCSMF)(FRANKFURT:FKC) sole owner of the Lac Knife, Quebec high purity graphite deposit announced today that the Feasibility Report prepared in accordance with National Instrument 43-101and with form 43-101F1 will be filed under the Company's SEDAR profile on Friday August 8th, 2014 at www.sedar.com and on Focus' website (www.focusgraphite.com).

The Feasibility Study was prepared by Met-Chem Canada Inc. with contributions from AGP Mining Consultants, Journeaux Associates and Golder Associates.

Don Baxter, Focus' President and Chief Operating Officer said: "With the Feasibility Study now completed, we continue to de-risk the project by focusing on key, near to mid-term milestones, including: detailed engineering, project financing, and the permitting process.

"In particular," he added, "the Feasibility Study opens the door to another level of available financing.

"We are evaluating options to secure project financing that will enable us to advance the Lac Knife mine and plant construction."

Mr. Baxter said discussions with potential offtake partners are ongoing and will complement the existing 10-year offtake signed in December, 2013.

The highlights of the Feasibility Study, as reported June 25, 2014:


---------------------------------------------------------------------------
Table 1                                                                    
---------------------------------------------------------------------------
Lac Knife Feasibility Results                                              
 (Pre-Tax)                           Base Case    2016 Forecast   Units    
---------------------------------------------------------------------------
Average Price / Tonne of             $1,713       $2,256          US$      
 Concentrate:                                                              
---------------------------------------------------------------------------
Internal Rate of Return (IRR)        30.1         41.8            %        
---------------------------------------------------------------------------
Net Present Value @ 6% Discounted    510          809             $ million
 Cash Flow                                                                 
---------------------------------------------------------------------------
Net Present Value @ 8% Discounted    383          624             $ million
 Cash Flow                                                                 
---------------------------------------------------------------------------
Net Present Value @ 10% Discounted   291          488             $ million
 Cash Flow                                                                 
---------------------------------------------------------------------------
Payback Period                       3.0          2.1             Years    
---------------------------------------------------------------------------
Lac Knife Feasibility Results        Base Case    2016 Forecast   Units    
 (After-Tax)                                                               
---------------------------------------------------------------------------
Internal Rate of Return (IRR)        24.1         32.8            %        
---------------------------------------------------------------------------
Net Present Value @ 6% Discounted    304          476             $ million
 Cash Flow                                                                 
---------------------------------------------------------------------------
Net Present Value @ 8% Discounted    224          364             $ million
 Cash Flow                                                                 
---------------------------------------------------------------------------
Net Present Value @ 10% Discounted   165          280             $ million
 Cash Flow                                                                 
---------------------------------------------------------------------------
Payback Period                       3.2          2.4             Years    
---------------------------------------------------------------------------
All monetary values are in Canadian Dollars ("CDN") except where specified 
 otherwise                                                                 
---------------------------------------------------------------------------

Of note is that average prices used in the financial model do not include value added products produced using the typically lower valued finer natural flake graphite.

Background:

The Feasibility Study was conducted with engineering and estimation methods appropriate to target an accuracy of 15% that is standard and realistic for capital and operating cost estimates for this level of study, that is required prior to detailed engineering, and well beyond the +/- 30% accuracy of a Preliminary Economic Assessment (PEA). Based on an extensive risk review exercise the contingency is 11.5%. Capital Expenditures in Table 2 itemize cost requirements for mine construction, processing plant, power line and all associated infrastructure estimated at $165.55 million.


---------------------------------------------------------------------
Table 2                                                              
---------------------------------------------------------------------
Lac Knife Capital Expenditure - Cost Centers            CDN$ millions
---------------------------------------------------------------------
Mine equipment, infrastructure, and pre-stripping       4.21         
---------------------------------------------------------------------
Infrastructure                                          11.62        
---------------------------------------------------------------------
Primary Crushing                                        7.02         
---------------------------------------------------------------------
Concentrator                                            62.24        
---------------------------------------------------------------------
Environmental and Tailings Management                   8.22         
---------------------------------------------------------------------
Additional Infrastructure                               15.4         
---------------------------------------------------------------------
Indirect Costs                                          39.77        
---------------------------------------------------------------------
Contingency (11.5%)                                     17.07        
---------------------------------------------------------------------
Sub Total                                               165.55       
---------------------------------------------------------------------

The company is continuing discussions with vendors to define financing packages for equipment. The company's aim is to reduce up front capital and add to the basket of financing options currently being investigated. Discussions and due diligence continue regarding Supply Chain Financing ("SCF") based on the offtake agreement signed in December, 2013 for a minimum of 50% of Lac Knife's production over the life of a 10-year agreement. SCF is a non-dilutive alternative to equity financing and is less encumbering than traditional debt, or royalty financing.

Future off-take agreements will contain a financial component. This project-financing alternative could include equity and low interest debt as well as a signing bonus to execute an offtake agreement. The various options discussed above have the potential to enhance future project economic evaluation metrics, and the company continues these discussions with several interested parties.

Qualified Persons

The technical information within this news release was approved by Project Leader Mary-Jean Buchanan Eng., and Jeffrey Cassoff Eng., Lead Mining Engineer, and Ewald Pengel P. Eng., Senior Metallurgist, who was responsible for concentrator design, of Met-Chem Canada Inc. all Qualified Persons under NI 43-101 guidelines and independent of the issuer. Pierre Desautels, P.Geo., of AGP Inc. completed the NI- 43-101 Mineral Resource Estimate and is independent of the issuer.

The technical information in this news release was prepared by Mr. Don Baxter, P. Eng., Focus President & Chief Operating Officer, a Qualified Person as defined by NI 43-101 guidelines, who has reviewed and approved the technical content of this news release.

About Focus Graphite

Focus Graphite Inc. is an emerging mining development company with an objective to produce value added products initially for the lithium ion battery market from the Lac Knife graphite deposit located south west of Fermont, Quebec. The Lac Knife project hosts a NI 43-101 compliant Measured and Indicated Mineral Resource Estimate(i) of 9.6 million tonnes grading 14.77% graphitic carbon (Cg) as natural flake graphite with an additional Inferred Mineral Resource Estimate(i) of 3.1 million tonnes grading 13.25% Cg. Focus' goal is to assume an industry leadership position by becoming a low-cost producer of technology-grade graphite. The Feasibility Study filed with SEDAR on August 8, 2014 for the Lac Knife Project indicates the project is economically viable and has the potential to become a low cost graphite producer based on 7.86 million tonnes (429,000 tonnes Proven and 7,428,000 tonnes Probable) of Proven and Probable Reserves grading 15.13 Cg. On May 27, 2014 the Company announced the Potential for High Value Added Sales in the Li-Ion Battery Sector following battery coin cell tests performed on Lac Knife Spherical Graphite ("SPG"). Testing measured the performance metrics and confirmed Focus' capability to tailor lithium ion battery anode grade graphite and value added products to meet the most stringent customer specifications. Focus Graphite is a technology-oriented enterprise with a vision for building long-term, sustainable shareholder value. Focus also holds a significant equity position in graphene applications developer Grafoid Inc.

(i) Mineral resources are not mineral reserves and do not have demonstrated economic viability

Forward Looking Statement

This news release contains "forward-looking information" within the meaning of Canadian securities legislation. All information contained herein that is not clearly historical in nature may constitute forward-looking information. Generally, such forward-looking information can be identified by the use of forward-looking terminology such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate", or "believes", or variations of such words and phrases or state that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved". Forward-looking information is subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of the Company to be materially different from those expressed or implied by such forward-looking information, including but not limited to: (i) volatile stock price; (ii) the general global markets and economic conditions; (iii) the possibility of write-downs and impairments; (iv) the risk associated with exploration, development and operation of mineral deposits; (v) the risk associated with establishing title to mineral properties and assets; (vi) the risks associated with entering into joint ventures; (vii) fluctuations in commodity prices; (viii) the risks associated with uninsurable risks arising during the course of exploration, development and production; (ix) competition faced by the resulting issuer in securing experienced personnel and financing; (x) access to adequate infrastructure to support mining, processing, development and exploration activities;

(xi) the risks associated with changes in the mining regulatory regime governing the resulting issuer; (xii) the risks associated with the various environmental regulations the resulting issuer is subject to; (xiii) risks related to regulatory and permitting delays; (xiv) risks related to potential conflicts of interest; (xv) the reliance on key personnel; (xvi) liquidity risks; (xvii) the risk of potential dilution through the issue of common shares; (xviii) the Company does not anticipate declaring dividends in the near term; (xix) the risk of litigation; and (xx) risk management. Forward-looking information is based on assumptions management believes to be reasonable at the time such statements are made, including but not limited to, continued exploration activities, no material adverse change in metal prices, exploration and development plans proceeding in accordance with plans and such plans achieving their stated expected outcomes, receipt of required regulatory approvals, and such other assumptions and factors as set out herein. Although the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in the forward-looking information, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such forward-looking information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such forward-looking information. Such forward-looking information has been provided for the purpose of assisting investors in understanding the Company's business, operations and exploration plans and may not be appropriate for other purposes. Accordingly, readers should not place undue reliance on forward-looking information. Forward-looking information is made as of the date of this news release, and the Company does not undertake to update such forward-looking information except in accordance with applicable securities laws.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
New Relic, Inc. has announced a set of new features across the New Relic Software Analytics Cloud that offer IT operations teams increased visibility, and the ability to diagnose and resolve performance problems quickly. The new features further IT operations teams’ ability to leverage data and analytics, as well as drive collaboration and a common, shared understanding between teams. Software teams are under pressure to resolve performance issues quickly and improve availability, as the comple...
The proper isolation of resources is essential for multi-tenant environments. The traditional approach to isolate resources is, however, rather heavyweight. In his session at 18th Cloud Expo, Igor Drobiazko, co-founder of elastic.io, will draw upon their own experience with operating a Docker container-based infrastructure on a large scale and present a lightweight solution for resource isolation using microservices. He will also discuss the implementation of microservices in data and applicat...
Join IBM June 8 at 18th Cloud Expo at the Javits Center in New York City, NY, and learn how to innovate like a startup and scale for the enterprise. You need to deliver quality applications faster and cheaper, attract and retain customers with an engaging experience across devices, and seamlessly integrate your enterprise systems. And you can't take 12 months to do it.
See storage differently! Storage performance problems have only gotten worse and harder to solve as applications have become largely virtualized and moved to a cloud-based infrastructure. Storage performance in a virtualized environment is not just about IOPS, it is about how well that potential performance is guaranteed to individual VMs for these apps as the number of VMs keep going up real time. In his session at 18th Cloud Expo, Dhiraj Sehgal, in product and marketing at Tintri, will discu...
Machine Learning helps make complex systems more efficient. By applying advanced Machine Learning techniques such as Cognitive Fingerprinting, wind project operators can utilize these tools to learn from collected data, detect regular patterns, and optimize their own operations. In his session at 18th Cloud Expo, Stuart Gillen, Director of Business Development at SparkCognition, will discuss how research has demonstrated the value of Machine Learning in delivering next generation analytics to im...
This is not a small hotel event. It is also not a big vendor party where politicians and entertainers are more important than real content. This is Cloud Expo, the world's longest-running conference and exhibition focused on Cloud Computing and all that it entails. If you want serious presentations and valuable insight about Cloud Computing for three straight days, then register now for Cloud Expo.
As you respond to increasing requests for new analytics, you need fast and flexible technology in your arsenal so that you can deploy the right workload to the right platform for the need at hand. Do you need self-service and fast time to value? Do you have data and application control and privacy needs, along with strict SLAs to meet? IBM dashDB™ is data warehouse technology powered by in-memory computing and in-database analytics that are designed for fast results, scalability and more.
You think you know what’s in your data. But do you? Most organizations are now aware of the business intelligence represented by their data. Data science stands to take this to a level you never thought of – literally. The techniques of data science, when used with the capabilities of Big Data technologies, can make connections you had not yet imagined, helping you discover new insights and ask new questions of your data. In his session at @ThingsExpo, Sarbjit Sarkaria, data science team lead ...
SYS-CON Events announced today that SoftLayer, an IBM Company, has been named “Gold Sponsor” of SYS-CON's 18th Cloud Expo, which will take place on June 7-9, 2016, at the Javits Center in New York, New York. SoftLayer, an IBM Company, provides cloud infrastructure as a service from a growing number of data centers and network points of presence around the world. SoftLayer’s customers range from Web startups to global enterprises.
So, you bought into the current machine learning craze and went on to collect millions/billions of records from this promising new data source. Now, what do you do with them? Too often, the abundance of data quickly turns into an abundance of problems. How do you extract that "magic essence" from your data without falling into the common pitfalls? In her session at @ThingsExpo, Natalia Ponomareva, Software Engineer at Google, will provide tips on how to be successful in large scale machine lear...
Up until last year, enterprises that were looking into cloud services usually undertook a long-term pilot with one of the large cloud providers, running test and dev workloads in the cloud. With cloud’s transition to mainstream adoption in 2015, and with enterprises migrating more and more workloads into the cloud and in between public and private environments, the single-provider approach must be revisited. In his session at 18th Cloud Expo, Yoav Mor, multi-cloud solution evangelist at Cloudy...
IoT device adoption is growing at staggering rates, and with it comes opportunity for developers to meet consumer demand for an ever more connected world. Wireless communication is the key part of the encompassing components of any IoT device. Wireless connectivity enhances the device utility at the expense of ease of use and deployment challenges. Since connectivity is fundamental for IoT device development, engineers must understand how to overcome the hurdles inherent in incorporating multipl...
We’ve worked with dozens of early adopters across numerous industries and will debunk common misperceptions, which starts with understanding that many of the connected products we’ll use over the next 5 years are already products, they’re just not yet connected. With an IoT product, time-in-market provides much more essential feedback than ever before. Innovation comes from what you do with the data that the connected product provides in order to enhance the customer experience and optimize busi...
The IETF draft standard for M2M certificates is a security solution specifically designed for the demanding needs of IoT/M2M applications. In his session at @ThingsExpo, Brian Romansky, VP of Strategic Technology at TrustPoint Innovation, will explain how M2M certificates can efficiently enable confidentiality, integrity, and authenticity on highly constrained devices.
The paradigm has shifted. A Gartner survey shows that 43% of organizations are using or plan to implement the Internet of Things in 2016. However, not just a handful of companies are still using the old-style ad-hoc trial-and-error ways, unaware of the critical barriers, paint points, traps, and hidden roadblocks. How can you become a winner? In his session at @ThingsExpo, Tony Shan will present a methodical approach to guide the holistic adoption and enablement of IoT implementations. This ov...