Focus Graphite Files Lac Knife Graphite Project Feasibility Study Technical Report

Weighs lower-cost options for tandem financing of mine/plant and purification facilities for high value "battery grade" graphite production

OTTAWA, ONTARIO -- (Marketwired) -- 08/08/14 -- Focus Graphite Inc. ("Focus" or the "Company") (TSX VENTURE:FMS)(OTCQX:FCSMF)(FRANKFURT:FKC) sole owner of the Lac Knife, Quebec high purity graphite deposit announced today that the Feasibility Report prepared in accordance with National Instrument 43-101and with form 43-101F1 will be filed under the Company's SEDAR profile on Friday August 8th, 2014 at www.sedar.com and on Focus' website (www.focusgraphite.com).

The Feasibility Study was prepared by Met-Chem Canada Inc. with contributions from AGP Mining Consultants, Journeaux Associates and Golder Associates.

Don Baxter, Focus' President and Chief Operating Officer said: "With the Feasibility Study now completed, we continue to de-risk the project by focusing on key, near to mid-term milestones, including: detailed engineering, project financing, and the permitting process.

"In particular," he added, "the Feasibility Study opens the door to another level of available financing.

"We are evaluating options to secure project financing that will enable us to advance the Lac Knife mine and plant construction."

Mr. Baxter said discussions with potential offtake partners are ongoing and will complement the existing 10-year offtake signed in December, 2013.

The highlights of the Feasibility Study, as reported June 25, 2014:


---------------------------------------------------------------------------
Table 1                                                                    
---------------------------------------------------------------------------
Lac Knife Feasibility Results                                              
 (Pre-Tax)                           Base Case    2016 Forecast   Units    
---------------------------------------------------------------------------
Average Price / Tonne of             $1,713       $2,256          US$      
 Concentrate:                                                              
---------------------------------------------------------------------------
Internal Rate of Return (IRR)        30.1         41.8            %        
---------------------------------------------------------------------------
Net Present Value @ 6% Discounted    510          809             $ million
 Cash Flow                                                                 
---------------------------------------------------------------------------
Net Present Value @ 8% Discounted    383          624             $ million
 Cash Flow                                                                 
---------------------------------------------------------------------------
Net Present Value @ 10% Discounted   291          488             $ million
 Cash Flow                                                                 
---------------------------------------------------------------------------
Payback Period                       3.0          2.1             Years    
---------------------------------------------------------------------------
Lac Knife Feasibility Results        Base Case    2016 Forecast   Units    
 (After-Tax)                                                               
---------------------------------------------------------------------------
Internal Rate of Return (IRR)        24.1         32.8            %        
---------------------------------------------------------------------------
Net Present Value @ 6% Discounted    304          476             $ million
 Cash Flow                                                                 
---------------------------------------------------------------------------
Net Present Value @ 8% Discounted    224          364             $ million
 Cash Flow                                                                 
---------------------------------------------------------------------------
Net Present Value @ 10% Discounted   165          280             $ million
 Cash Flow                                                                 
---------------------------------------------------------------------------
Payback Period                       3.2          2.4             Years    
---------------------------------------------------------------------------
All monetary values are in Canadian Dollars ("CDN") except where specified 
 otherwise                                                                 
---------------------------------------------------------------------------

Of note is that average prices used in the financial model do not include value added products produced using the typically lower valued finer natural flake graphite.

Background:

The Feasibility Study was conducted with engineering and estimation methods appropriate to target an accuracy of 15% that is standard and realistic for capital and operating cost estimates for this level of study, that is required prior to detailed engineering, and well beyond the +/- 30% accuracy of a Preliminary Economic Assessment (PEA). Based on an extensive risk review exercise the contingency is 11.5%. Capital Expenditures in Table 2 itemize cost requirements for mine construction, processing plant, power line and all associated infrastructure estimated at $165.55 million.


---------------------------------------------------------------------
Table 2                                                              
---------------------------------------------------------------------
Lac Knife Capital Expenditure - Cost Centers            CDN$ millions
---------------------------------------------------------------------
Mine equipment, infrastructure, and pre-stripping       4.21         
---------------------------------------------------------------------
Infrastructure                                          11.62        
---------------------------------------------------------------------
Primary Crushing                                        7.02         
---------------------------------------------------------------------
Concentrator                                            62.24        
---------------------------------------------------------------------
Environmental and Tailings Management                   8.22         
---------------------------------------------------------------------
Additional Infrastructure                               15.4         
---------------------------------------------------------------------
Indirect Costs                                          39.77        
---------------------------------------------------------------------
Contingency (11.5%)                                     17.07        
---------------------------------------------------------------------
Sub Total                                               165.55       
---------------------------------------------------------------------

The company is continuing discussions with vendors to define financing packages for equipment. The company's aim is to reduce up front capital and add to the basket of financing options currently being investigated. Discussions and due diligence continue regarding Supply Chain Financing ("SCF") based on the offtake agreement signed in December, 2013 for a minimum of 50% of Lac Knife's production over the life of a 10-year agreement. SCF is a non-dilutive alternative to equity financing and is less encumbering than traditional debt, or royalty financing.

Future off-take agreements will contain a financial component. This project-financing alternative could include equity and low interest debt as well as a signing bonus to execute an offtake agreement. The various options discussed above have the potential to enhance future project economic evaluation metrics, and the company continues these discussions with several interested parties.

Qualified Persons

The technical information within this news release was approved by Project Leader Mary-Jean Buchanan Eng., and Jeffrey Cassoff Eng., Lead Mining Engineer, and Ewald Pengel P. Eng., Senior Metallurgist, who was responsible for concentrator design, of Met-Chem Canada Inc. all Qualified Persons under NI 43-101 guidelines and independent of the issuer. Pierre Desautels, P.Geo., of AGP Inc. completed the NI- 43-101 Mineral Resource Estimate and is independent of the issuer.

The technical information in this news release was prepared by Mr. Don Baxter, P. Eng., Focus President & Chief Operating Officer, a Qualified Person as defined by NI 43-101 guidelines, who has reviewed and approved the technical content of this news release.

About Focus Graphite

Focus Graphite Inc. is an emerging mining development company with an objective to produce value added products initially for the lithium ion battery market from the Lac Knife graphite deposit located south west of Fermont, Quebec. The Lac Knife project hosts a NI 43-101 compliant Measured and Indicated Mineral Resource Estimate(i) of 9.6 million tonnes grading 14.77% graphitic carbon (Cg) as natural flake graphite with an additional Inferred Mineral Resource Estimate(i) of 3.1 million tonnes grading 13.25% Cg. Focus' goal is to assume an industry leadership position by becoming a low-cost producer of technology-grade graphite. The Feasibility Study filed with SEDAR on August 8, 2014 for the Lac Knife Project indicates the project is economically viable and has the potential to become a low cost graphite producer based on 7.86 million tonnes (429,000 tonnes Proven and 7,428,000 tonnes Probable) of Proven and Probable Reserves grading 15.13 Cg. On May 27, 2014 the Company announced the Potential for High Value Added Sales in the Li-Ion Battery Sector following battery coin cell tests performed on Lac Knife Spherical Graphite ("SPG"). Testing measured the performance metrics and confirmed Focus' capability to tailor lithium ion battery anode grade graphite and value added products to meet the most stringent customer specifications. Focus Graphite is a technology-oriented enterprise with a vision for building long-term, sustainable shareholder value. Focus also holds a significant equity position in graphene applications developer Grafoid Inc.

(i) Mineral resources are not mineral reserves and do not have demonstrated economic viability

Forward Looking Statement

This news release contains "forward-looking information" within the meaning of Canadian securities legislation. All information contained herein that is not clearly historical in nature may constitute forward-looking information. Generally, such forward-looking information can be identified by the use of forward-looking terminology such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate", or "believes", or variations of such words and phrases or state that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved". Forward-looking information is subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of the Company to be materially different from those expressed or implied by such forward-looking information, including but not limited to: (i) volatile stock price; (ii) the general global markets and economic conditions; (iii) the possibility of write-downs and impairments; (iv) the risk associated with exploration, development and operation of mineral deposits; (v) the risk associated with establishing title to mineral properties and assets; (vi) the risks associated with entering into joint ventures; (vii) fluctuations in commodity prices; (viii) the risks associated with uninsurable risks arising during the course of exploration, development and production; (ix) competition faced by the resulting issuer in securing experienced personnel and financing; (x) access to adequate infrastructure to support mining, processing, development and exploration activities;

(xi) the risks associated with changes in the mining regulatory regime governing the resulting issuer; (xii) the risks associated with the various environmental regulations the resulting issuer is subject to; (xiii) risks related to regulatory and permitting delays; (xiv) risks related to potential conflicts of interest; (xv) the reliance on key personnel; (xvi) liquidity risks; (xvii) the risk of potential dilution through the issue of common shares; (xviii) the Company does not anticipate declaring dividends in the near term; (xix) the risk of litigation; and (xx) risk management. Forward-looking information is based on assumptions management believes to be reasonable at the time such statements are made, including but not limited to, continued exploration activities, no material adverse change in metal prices, exploration and development plans proceeding in accordance with plans and such plans achieving their stated expected outcomes, receipt of required regulatory approvals, and such other assumptions and factors as set out herein. Although the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in the forward-looking information, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such forward-looking information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such forward-looking information. Such forward-looking information has been provided for the purpose of assisting investors in understanding the Company's business, operations and exploration plans and may not be appropriate for other purposes. Accordingly, readers should not place undue reliance on forward-looking information. Forward-looking information is made as of the date of this news release, and the Company does not undertake to update such forward-looking information except in accordance with applicable securities laws.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
All clouds are not equal. To succeed in a DevOps context, organizations should plan to develop/deploy apps across a choice of on-premise and public clouds simultaneously depending on the business needs. This is where the concept of the Lean Cloud comes in - resting on the idea that you often need to relocate your app modules over their life cycles for both innovation and operational efficiency in the cloud. In his session at @DevOpsSummit at19th Cloud Expo, Valentin (Val) Bercovici, CTO of Soli...
Without a clear strategy for cost control and an architecture designed with cloud services in mind, costs and operational performance can quickly get out of control. To avoid multiple architectural redesigns requires extensive thought and planning. Boundary (now part of BMC) launched a new public-facing multi-tenant high resolution monitoring service on Amazon AWS two years ago, facing challenges and learning best practices in the early days of the new service. In his session at 19th Cloud Exp...
Predictive analytics tools monitor, report, and troubleshoot in order to make proactive decisions about the health, performance, and utilization of storage. Most enterprises combine cloud and on-premise storage, resulting in blended environments of physical, virtual, cloud, and other platforms, which justifies more sophisticated storage analytics. In his session at 18th Cloud Expo, Peter McCallum, Vice President of Datacenter Solutions at FalconStor, discussed using predictive analytics to mon...
Keeping pace with advancements in software delivery processes and tooling is taxing even for the most proficient organizations. Point tools, platforms, open source and the increasing adoption of private and public cloud services requires strong engineering rigor – all in the face of developer demands to use the tools of choice. As Agile has settled in as a mainstream practice, now DevOps has emerged as the next wave to improve software delivery speed and output. To make DevOps work, organization...
With major technology companies and startups seriously embracing IoT strategies, now is the perfect time to attend @ThingsExpo 2016 in New York. Learn what is going on, contribute to the discussions, and ensure that your enterprise is as "IoT-Ready" as it can be! Internet of @ThingsExpo, taking place June 6-8, 2017, at the Javits Center in New York City, New York, is co-located with 20th Cloud Expo and will feature technical sessions from a rock star conference faculty and the leading industry p...
20th Cloud Expo, taking place June 6-8, 2017, at the Javits Center in New York City, NY, will feature technical sessions from a rock star conference faculty and the leading industry players in the world. Cloud computing is now being embraced by a majority of enterprises of all sizes. Yesterday's debate about public vs. private has transformed into the reality of hybrid cloud: a recent survey shows that 74% of enterprises have a hybrid cloud strategy.
Traditional on-premises data centers have long been the domain of modern data platforms like Apache Hadoop, meaning companies who build their business on public cloud were challenged to run Big Data processing and analytics at scale. But recent advancements in Hadoop performance, security, and most importantly cloud-native integrations, are giving organizations the ability to truly gain value from all their data. In his session at 19th Cloud Expo, David Tishgart, Director of Product Marketing ...
Join Impiger for their featured webinar: ‘Cloud Computing: A Roadmap to Modern Software Delivery’ on November 10, 2016, at 12:00 pm CST. Very few companies have not experienced some impact to their IT delivery due to the evolution of cloud computing. This webinar is not about deciding whether you should entertain moving some or all of your IT to the cloud, but rather, a detailed look under the hood to help IT professionals understand how cloud adoption has evolved and what trends will impact th...
More and more brands have jumped on the IoT bandwagon. We have an excess of wearables – activity trackers, smartwatches, smart glasses and sneakers, and more that track seemingly endless datapoints. However, most consumers have no idea what “IoT” means. Creating more wearables that track data shouldn't be the aim of brands; delivering meaningful, tangible relevance to their users should be. We're in a period in which the IoT pendulum is still swinging. Initially, it swung toward "smart for smar...
Internet of @ThingsExpo, taking place June 6-8, 2017 at the Javits Center in New York City, New York, is co-located with the 20th International Cloud Expo and will feature technical sessions from a rock star conference faculty and the leading industry players in the world. @ThingsExpo New York Call for Papers is now open.
"ReadyTalk is an audio and web video conferencing provider. We've really come to embrace WebRTC as the platform for our future of technology," explained Dan Cunningham, CTO of ReadyTalk, in this SYS-CON.tv interview at WebRTC Summit at 19th Cloud Expo, held November 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA.
Everyone knows that truly innovative companies learn as they go along, pushing boundaries in response to market changes and demands. What's more of a mystery is how to balance innovation on a fresh platform built from scratch with the legacy tech stack, product suite and customers that continue to serve as the business' foundation. In his General Session at 19th Cloud Expo, Michael Chambliss, Head of Engineering at ReadyTalk, discussed why and how ReadyTalk diverted from healthy revenue and mor...
In an era of historic innovation fueled by unprecedented access to data and technology, the low cost and risk of entering new markets has leveled the playing field for business. Today, any ambitious innovator can easily introduce a new application or product that can reinvent business models and transform the client experience. In their Day 2 Keynote at 19th Cloud Expo, Mercer Rowe, IBM Vice President of Strategic Alliances, and Raejeanne Skillern, Intel Vice President of Data Center Group and G...
When it comes to cloud computing, the ability to turn massive amounts of compute cores on and off on demand sounds attractive to IT staff, who need to manage peaks and valleys in user activity. With cloud bursting, the majority of the data can stay on premises while tapping into compute from public cloud providers, reducing risk and minimizing need to move large files. In his session at 18th Cloud Expo, Scott Jeschonek, Director of Product Management at Avere Systems, discussed the IT and busin...
Extracting business value from Internet of Things (IoT) data doesn’t happen overnight. There are several requirements that must be satisfied, including IoT device enablement, data analysis, real-time detection of complex events and automated orchestration of actions. Unfortunately, too many companies fall short in achieving their business goals by implementing incomplete solutions or not focusing on tangible use cases. In his general session at @ThingsExpo, Dave McCarthy, Director of Products...