NioCorp Receives Highest Grade Niobium Assays to Date

VANCOUVER, BRITISH COLUMBIA -- (Marketwired) -- 08/11/14 -- NioCorp Developments Ltd. ("NioCorp" or the "Company") (TSX VENTURE: NB)(OTCQX: NIOBF)(FRANKFURT: BR3) is pleased to announce receipt of the following assays from the ongoing drilling and development operations at Elk Creek, Nebraska.

Drillholes NEC14-006, NEC14-007 and NEC14-008, were drilled along a North-East to South-West section line that was designed to drill across the previously defined Niobium Resource. These holes were drilled at approximately 50 m (165 ft.) intervals along the drill section line. Drillholes NEC14-009 and NEC14-010 were recently completed along a parallel section line to the east of the first three holes. Together, these five holes make up Phase I of NioCorp's 2014 drilling program. Phase II drilling at the project has commenced, which will consists of an additional 6 holes.

The collected core samples have been systematically processed and shipped for analytical and physical rock property test work to support NioCorp's corporate objectives for the project. Assay results have now been received and reviewed for the final 120 m of NEC14-008 (total depth drilled and sampled 886 m), along with the top 402 meters of NEC14-009

Analytical highlights for NEC14-008 and NEC14-009 appear below. Note that due to the angle of the drilling and other factors, these do not represent the true thickness of the Niobium Resource:

--  NEC14-008 - newly received results (with previously released results
    from August 5, 2014 noted immediately below)
    --  448 m interval between 438 - 886 m at 0.69 % Nb2O5
    --  32 m (466 - 498 m) at 1.09 % Nb2O5
        --  5 m (493 - 498 m) at 1.68 % Nb2O5
    --  9 m (553 - 563 m) at 1.00 % Nb2O5
    --  13 m (610 - 623 m) at 1.02 % Nb2O5
    --  12 m (760 - 772 m) at 2.12 % Nb2O5
        --  3 m (768-771 m) at 3.23% Nb2O5
    --  16 m (772 - 788 m) at 1.01 % Nb2O5
    --  10 m (835 - 845 m) at 1.15 % Nb2O5
--  NEC14-008 - previously released results - (see news release dated August
    5, 2014)
    --  326 m interval between 438 - 765 m (open) at 0.67 % Nb2O5
        --  32 m (466 - 498 m) at 1.09 % Nb2O5
            --  5 m (493 - 498 m) at 1.68 % Nb2O5
        --  9 m (553 - 563 m) at 1.00 % Nb2O5
        --  13 m (610 - 623 m) at 1.02 % Nb2O5
        --  25 m (740 - 765 m) at 0.85 % Nb2O5
--  NEC14-009 - newly received results for the first 402 m
    --  o 183 m interval between 218 - 402 m (open) at 0.55 % Nb2O5,
        including
        --  29 m (218 - 247 m) at 0.76 % Nb2O5
            --  7 m (240 - 247 m) at 1.76 % Nb2O5
        --  11 m (271 - 282 m) at 1.06 % Nb2O5
        --  11 m (302 - 313 m) at 1.01 % Nb2O5
        --  31 m (370 - 402 m) at 0.65 % Nb2O5

Note that drillhole NEC14-009 was drilled to a final depth of 897.03 meters, and analytical results for the balance of this hole are pending.

"Our drilling program at Elk Creek continues to deliver impressive Niobium assays" said Mark Smith, CEO of Niocorp. "The third drill rig that has been added to the program has accelerated the overall drilling schedule, and I look forward to seeing the balance of the Phase I analytical results in the near future".

Quality Control: Sampling for NEC14-008 was continuously collected from the base of the limestone-carbonatite contact to the end of the drillhole (230 m to 772.67 m). A total of 830 samples from drill hole NEC14-008 were delivered to Activation Laboratories Ltd. (ActLabs), Ancaster, Ontario. Of the 830 samples submitted, 673 samples are core sections while the remainder are control samples. The Carbonatite continued at depth and remains open in that direction. HQ diameter core was sawn into half-core samples, and control samples were inserted into each batch.

Sampling for NEC14-009 was continuously collected from the base of the limestone-carbonatite contact to the end of the drillhole (209 m to 897.03 m). A total of 843 samples from drill hole NEC14-009 were delivered to Activation Laboratories Ltd. (ActLabs), Ancaster, Ontario. Of the 843 samples submitted, 686 samples are core sections while the remainder are control samples. The Carbonatite continued at depth and remains open in that direction. HQ diameter core was sawn into half-core samples, and control samples were inserted into each batch.

Qualified Persons: Brad Ulry, B.Sc., P.Geo., Dahrouge Geological Consulting Ltd., a Qualified Person as defined by National Instrument 43-101, is responsible for the Elk Creek drilling operations and has read and approved the technical information contained in this news release.

About the Company: NioCorp are developing the only primary niobium deposit known to be under development in the U.S., and the highest grade undeveloped niobium deposit in North America, located near Elk Creek, Nebraska. The Company has published an NI 43-101 resource of 19.3 Million tonnes grading 0.67% Indicated, containing over 129,182 tonnes of Nb2O5, and 83.3 Mt grading 0.63% Inferred, containing over 523,844 tonnes of Nb2O5). Niobium is mainly used in the form of Ferro-Niobium to produce HSLA (High Strength, Low Alloy) steel, to produce lighter, stronger steel for use in automotive, structural and pipeline industries. The U.S. imports 100% of its niobium needs.

ON BEHALF OF THE BOARD

Peter Dickie, Director, President and Corporate Secretary

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Certain statements contained in this press release may constitute forward-looking statements. Such forward-looking statements are based upon NioCorp's reasonable expectations and business plan at the date hereof, which are subject to change depending on economic, political and competitive circumstances and contingencies. Readers are cautioned that such forward-looking statements involve known and unknown risks, uncertainties and other factors that may cause a change in such assumptions and the actual outcomes and estimates to be materially different from those estimated or anticipated future results, achievements or position expressed or implied by those forward-looking statements. Risks, uncertainties and other factors that could cause NioCorp's plans or prospects to change include changes in demand for and price of commodities (such as fuel and electricity) and currencies; changes or disruptions in the securities markets; legislative, political or economic developments; the need to obtain permits and comply with laws and regulations and other regulatory requirements; the possibility that actual results of work may differ from projections/expectations or may not realize the perceived potential of NioCorp's projects; risks of accidents, equipment breakdowns and labour disputes or other unanticipated difficulties or interruptions; the possibility of cost overruns or unanticipated expenses in development programs; operating or technical difficulties in connection with exploration, mining or development activities; the speculative nature of mineral exploration and development, including the risks of diminishing quantities of grades of reserves and resources; and the risks involved in the exploration, development and mining business. NioCorp disclaims any intention or obligation to update or revise any forward-looking statements whether as a result of new information, future events or otherwise.

Contacts:
NioCorp Developments Ltd.
Head Office - Suite 525, 999 West Hastings St.
Vancouver, B.C., Canada V6C 2W2
(604) 568-7365
(604) 568-8270 (FAX)
www.NioCorp.com

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
SYS-CON Events announced today that Avere Systems, a leading provider of hybrid cloud enablement solutions, will exhibit at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. Avere Systems was created by file systems experts determined to reinvent storage by changing the way enterprises thought about and bought storage resources. With decades of experience behind the company’s founders, Avere got its ...
Microsoft Azure Container Services can be used for container deployment in a variety of ways including support for Orchestrators like Kubernetes, Docker Swarm and Mesos. However, the abstraction for app development that support application self-healing, scaling and so on may not be at the right level. Helm and Draft makes this a lot easier. In this primarily demo-driven session at @DevOpsSummit at 21st Cloud Expo, Raghavan "Rags" Srinivas, a Cloud Solutions Architect/Evangelist at Microsoft, wi...
As you move to the cloud, your network should be efficient, secure, and easy to manage. An enterprise adopting a hybrid or public cloud needs systems and tools that provide: Agility: ability to deliver applications and services faster, even in complex hybrid environments Easier manageability: enable reliable connectivity with complete oversight as the data center network evolves Greater efficiency: eliminate wasted effort while reducing errors and optimize asset utilization Security: imple...
Containers are rapidly finding their way into enterprise data centers, but change is difficult. How do enterprises transform their architecture with technologies like containers without losing the reliable components of their current solutions? In his session at @DevOpsSummit at 21st Cloud Expo, Tony Campbell, Director, Educational Services at CoreOS, will explore the challenges organizations are facing today as they move to containers and go over how Kubernetes applications can deploy with lega...
High-velocity engineering teams are applying not only continuous delivery processes, but also lessons in experimentation from established leaders like Amazon, Netflix, and Facebook. These companies have made experimentation a foundation for their release processes, allowing them to try out major feature releases and redesigns within smaller groups before making them broadly available. In his session at 21st Cloud Expo, Brian Lucas, Senior Staff Engineer at Optimizely, will discuss how by using...
Today most companies are adopting or evaluating container technology - Docker in particular - to speed up application deployment, drive down cost, ease management and make application delivery more flexible overall. As with most new architectures, this dream takes significant work to become a reality. Even when you do get your application componentized enough and packaged properly, there are still challenges for DevOps teams to making the shift to continuous delivery and achieving that reducti...
In this strange new world where more and more power is drawn from business technology, companies are effectively straddling two paths on the road to innovation and transformation into digital enterprises. The first path is the heritage trail – with “legacy” technology forming the background. Here, extant technologies are transformed by core IT teams to provide more API-driven approaches. Legacy systems can restrict companies that are transitioning into digital enterprises. To truly become a lead...
Is advanced scheduling in Kubernetes achievable? Yes, however, how do you properly accommodate every real-life scenario that a Kubernetes user might encounter? How do you leverage advanced scheduling techniques to shape and describe each scenario in easy-to-use rules and configurations? In his session at @DevOpsSummit at 21st Cloud Expo, Oleg Chunikhin, CTO at Kublr, will answer these questions and demonstrate techniques for implementing advanced scheduling. For example, using spot instances ...
With major technology companies and startups seriously embracing Cloud strategies, now is the perfect time to attend 21st Cloud Expo October 31 - November 2, 2017, at the Santa Clara Convention Center, CA, and June 12-14, 2018, at the Javits Center in New York City, NY, and learn what is going on, contribute to the discussions, and ensure that your enterprise is on the right path to Digital Transformation.
SYS-CON Events announced today that Yuasa System will exhibit at the Japan External Trade Organization (JETRO) Pavilion at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. Yuasa System is introducing a multi-purpose endurance testing system for flexible displays, OLED devices, flexible substrates, flat cables, and films in smartphones, wearables, automobiles, and healthcare.
SYS-CON Events announced today that CAST Software will exhibit at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 - Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. CAST was founded more than 25 years ago to make the invisible visible. Built around the idea that even the best analytics on the market still leave blind spots for technical teams looking to deliver better software and prevent outages, CAST provides the software intelligence that matter ...
SYS-CON Events announced today that Daiya Industry will exhibit at the Japanese Pavilion at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. Ruby Development Inc. builds new services in short period of time and provides a continuous support of those services based on Ruby on Rails. For more information, please visit https://github.com/RubyDevInc.
When it comes to cloud computing, the ability to turn massive amounts of compute cores on and off on demand sounds attractive to IT staff, who need to manage peaks and valleys in user activity. With cloud bursting, the majority of the data can stay on premises while tapping into compute from public cloud providers, reducing risk and minimizing need to move large files. In his session at 18th Cloud Expo, Scott Jeschonek, Director of Product Management at Avere Systems, discussed the IT and busine...
SYS-CON Events announced today that Evatronix will exhibit at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. Evatronix SA offers comprehensive solutions in the design and implementation of electronic systems, in CAD / CAM deployment, and also is a designer and manufacturer of advanced 3D scanners for professional applications.
As businesses evolve, they need technology that is simple to help them succeed today and flexible enough to help them build for tomorrow. Chrome is fit for the workplace of the future — providing a secure, consistent user experience across a range of devices that can be used anywhere. In her session at 21st Cloud Expo, Vidya Nagarajan, a Senior Product Manager at Google, will take a look at various options as to how ChromeOS can be leveraged to interact with people on the devices, and formats th...