Orvana Announces Decrease in Resources and Reserves at EVBC and Updates Life-of-Mine Plan

-- EVBC estimated mine life approximately four years with AISC of $1,100

TORONTO, ONTARIO -- (Marketwired) -- 08/13/14 -- Orvana Minerals Corp. ("Orvana" or the "Company") (TSX:ORV) announces that it has received updated mineral resources and reserves estimates (the "MRMR Update") for El Valle-Boinas/Carles ("EVBC") gold-copper mines in northern Spain, showing a year-over-year decrease in reserves and resources. The Company also received an updated life-of-mine plan (the "LOMP Update") using proven and probable mineral reserves reflecting a shortened mine life based on these updated reserves. The Company also announces that it expects to place the Carles Mine on care and maintenance by the end of 2014.

EVBC has had a record of under-performance against plan with respect to gold output. In 2014, Orvana initiated a review of past performance, including measures taken by previous and current management teams to enhance mine performance. As a result of this review, management deemed it appropriate to further assess the assumptions of previous mine plans, particularly in regard to reserves and resources, and engaged Roscoe Postle Associates Inc. ("RPA") to complete the MRMR Update and LOMP Update.

The MRMR Update and the LOMP Update revise certain assumptions used previously and present a different methodology with respect to the application of cut-off grades in certain zones of EVBC. Various other factors resulting in the changes include removal of uneconomic zones and depletion from mining activities since June 1, 2013.

"The reserve and resource reductions are disappointing. Orvana's decisions in response to these decreases and associated life-of-mine adjustments are difficult but necessary steps," said Michael Winship, President and CEO of Orvana. "Orvana will optimize production at Boinas Mine and will focus on producing only profitable ounces. Production will increase at Boinas, while the Carles Mine will be placed on care and maintenance by the end of 2014. We believe that these measures, coupled with the significant repayment of debt, will enable us to achieve improvements in free cash flow."

MRMR Update

The MRMR Update and the LOMP Update were prepared in accordance with National Instrument 43-101 - Standards of Disclosure for Mineral Projects ("NI 43-101") by RPA, an independent mining consulting firm. RPA will be completing a NI 43-101 technical report with respect to the MRMR Update and the LOMP Update, which will be filed on SEDAR within 45 days.

The Company has most recently published mineral resources and reserves estimates for EVBC as at June 1, 2013 in its annual information form dated December 19, 2013 (the "2013 AIF").

The following is a summary of the MRMR Update with more detailed information set forth in Table 1 and Table 2 in the appendix to this press release:

--  Proven and Probable Reserves - approximately 2.2 million tonnes grading
    4.3 g/t gold and 0.7% copper, containing 302,000 ounces of gold and
    14,680 tonnes of copper, a decrease of approximately 66% and 59%,
    respectively; 
    
--  Measured and Indicated Resources - approximately 6.0 million tonnes
    grading 4.4 g/t gold and 0.7% copper, containing 850,900 ounces of gold
    and 41,500 tonnes of copper, a decrease of approximately 32% and 22%,
    respectively; and 
    
--  Inferred Resources - approximately 6.0 million tonnes grading 5.0 g/t
    gold and 0.5% copper, containing 979,500 ounces of gold and 26,900
    tonnes of copper, a decrease of approximately 22% and 5%, respectively. 

LOMP Update

RPA completed the LOMP Update based on proven and probable reserves estimated as part of the MRMR Update which estimates mine life for EVBC at approximately four years compared with approximately nine years as previously disclosed. Total gold production is expected to be approximately 282,200 ounces at an average all-in-sustaining cost per ounce of gold sold of approximately $1,100 over the currently estimated mine life.

In addition, the inferred mineral resources are estimated to contain 979,500 gold ounces, providing opportunities to extend the mine life.

"Management will continue to focus on delineation drilling at EVBC, which historically has enabled us to convert mineral resources into reserves. We believe there is upside potential to extend EVBC's mine life beyond this current estimate," said Mr. Winship.

Carles Mine Suspension

Orvana plans to ramp down and put Carles on care and maintenance pending an improved economic mining plan or higher metal prices. In addition to executing on the new optimization plan, which has yielded improved results in recent months, the Company is also undertaking a review of alternatives. This includes evaluating narrow high-grade areas in Carles for more suitable mining methods and further exploration targeting certain zones and satellite deposits in the region.

EVBC Impairment

As a result of the MRMR Update and the Carles suspension and in accordance with its usual policy, Orvana conducted a carrying value assessment of EVBC as at June 30, 2014 and determined that EVBC's net recoverable amount was lower than its carrying amount. As a result, Orvana recognized a non-cash impairment loss in respect of EVBC of $25.5 million in the third quarter of fiscal 2014.

In a separate news release issued today, Orvana announced its operating and financial results as at and for the three and nine months ended June 30, 2014.

Orvana Strategy

In the context of the MRMR Update and the LOMP Update, Orvana is initiating a comprehensive strategic review of the Company and its asset base. This review will encompass the consideration of a number of possible outcomes for Orvana and its shareholders and may include exploration, asset transactions or a corporate transaction. Orvana will report on its progress in due course.

"We continue to build on the progress we have made in recent months," said Mr. Winship. "At the same time, and taking into account the updates to our mine operations, the Board together with management will thoughtfully and deliberately review our strategy for future growth and value creation."

Qualified Persons

The scientific and technical information contained in this press release has been reviewed and approved (i) in respect of the estimated mineral reserves and the LOMP Update by Jason Cox, P.Eng., of RPA, and (ii) in respect of the estimated mineral resources by Sean Horan, P.Geo., of RPA. RPA is an independent mining consultant and each of Messrs. Cox and Horan is a Qualified Person within the meaning of NI 43-101.

About Orvana

Orvana Minerals is a multi-mine gold and copper producer. Orvana's operating assets consist of the EVBC gold-copper mines in northern Spain and copper-gold-silver Don Mario Mine in Bolivia. Additional information is available at Orvana's website (www.orvana.com).

Forward Looking Disclaimer

Certain statements in this press release constitute forward-looking statements or forward-looking information within the meaning of applicable securities laws ("forward-looking statements"). Any statements that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions, potentials, future events or performance (often, but not always, using words or phrases such as "believes", "expects" "plans", "estimates" or "intends" or stating that certain actions, events or results "may", "could", "would", "might", "will" or "are projected to" be taken or achieved) are not statements of historical fact, but are forward-looking statements.

The forward-looking statements herein relate to, among other things, Orvana's ability to achieve improvement in free cash flow; the potential to extend EVBC's mine life beyond the life of mine estimate set forth herein; Orvana's ability to optimize its assets to deliver shareholder value; Orvana's ability to optimize production at Boinas; the expected costs associated with the suspension of mining activities at Carles; the Company's ability to emerge stronger from the turnaround work executed at EVBC in 2014; estimates of future production, operating costs and capital expenditures; mineral resource and reserve estimates; statements and information regarding future feasibility studies and their results; future transactions; future metal prices; the ability to achieve additional growth and geographic diversification; future financial performance, including the ability to increase cash flow and profits; future financing requirements; and mine development plans.

Forward-looking statements are necessarily based upon a number of estimates and assumptions that, while considered reasonable by Orvana as of the date of such statements, are inherently subject to significant business, economic and competitive uncertainties and contingencies. The estimates and assumptions of Orvana contained or incorporated by reference in this news release, which may prove to be incorrect, include, but are not limited to, the various assumptions set forth herein and in the Company's most recently filed Management's Discussion & Analysis and Annual Information Form in respect of the Company's most recently completed fiscal year (the "Company Disclosures"), or as otherwise expressly incorporated herein by reference as well as: there being no significant disruptions affecting operations, whether due to labour disruptions, supply disruptions, power disruptions, damage to equipment or otherwise; permitting, development, operations, expansion and acquisitions at the EVBC and Don Mario Mines being consistent with the Company's current expectations; political developments in any jurisdiction in which the Company operates being consistent with its current expectations; certain price assumptions for gold, copper and silver; prices for key supplies being approximately consistent with current levels; production and cost of sales forecasts meeting expectations; the accuracy of the Company's current mineral reserve and mineral resource estimates; and labour and materials costs increasing on a basis consistent with Orvana's current expectations.

A variety of inherent risks, uncertainties and factors, many of which are beyond the Company's control, affect the operations, performance and results of the Company and its business, and could cause actual events or results to differ materially from estimated or anticipated events or results expressed or implied by forward looking statements. Some of these risks, uncertainties and factors include fluctuations in the price of gold, silver and copper; the need to recalculate estimates of resources based on actual production experience; the failure to achieve production estimates; variations in the grade of ore mined; variations in the cost of operations; variations in the costs associated with the suspension of mining at Carles; the availability of qualified personnel; the Company's ability to obtain and maintain all necessary regulatory approvals and licenses; the Company's ability to use cyanide in its mining operations; risks generally associated with mineral exploration and development, including the Company's ability to continue to operate the EVBC Mines and/or the Don Mario Mine; the Company's ability to acquire and develop mineral properties and to successfully integrate such acquisitions; the Company's ability to obtain financing when required on terms that are acceptable to the Company; the Company's ability to execute on its strategy; challenges to the Company's interests in its property and mineral rights; current, pending and proposed legislative or regulatory developments or changes in political, social or economic conditions in the countries in which the Company operates; general economic conditions worldwide; and the risks identified in the Company Disclosures under the heading "Risks and Uncertainties". This list is not exhaustive of the factors that may affect any of the Company's forward-looking statements and reference should also be made to the Company Disclosures for a description of additional risk factors.

Forward-looking statements are based on management's current plans, estimates, projections, beliefs and opinions and, except as required by law, the Company does not undertake any obligation to update forward-looking statements should assumptions related to these plans, estimates, projections, beliefs and opinions change. Readers are cautioned not to put undue reliance on forward-looking statements.

Cautionary Notes to Investors - Reserve and Resource Estimates

In accordance with applicable Canadian securities regulatory requirements, all mineral reserve and mineral resource estimates of the Company disclosed in this news release have been prepared as at September 30, 2014 in accordance with Canadian National Instrument 43-101 - Standards of Disclosure for Mineral Projects ("NI 43-101"), classified in accordance with Canadian Institute of Mining Metallurgy and Petroleum's "CIM Standards on Mineral Resources and Reserves Definitions and Guidelines" (the "CIM Guidelines").

Pursuant to the CIM Guidelines, mineral resources have a higher degree of uncertainty than mineral Reserves as to their existence as well as their economic and legal feasibility. Inferred mineral resources, when compared with measured or indicated mineral resources, have the least certainty as to their existence, and it cannot be assumed that all or any part of an inferred mineral resource will be upgraded to an indicated or measured mineral resource as a result of continued exploration. Pursuant to NI 43-101, inferred mineral resources may not form the basis of any economic analysis, including any feasibility study. Accordingly, readers are cautioned not to assume that all or any part of a mineral resource exists, will ever be converted into a mineral Reserve, or is or will ever be economically or legally mineable or recovered.

                                                                            
                                  APPENDIX                                  
                                   TABLE 1                                  
            Orvana - Updated EVBC Mineral Resource Estimate (1)             
----------------------------------------------------------------------------
                       EVBC Inclusive Mineral Resource Estimate as at Sept. 
ZONE                                        30th, 2014                      
                      ------------------------------------------------------
                                      Au       Cu       Ag       Au       Cu
                         Tonnes    Grade    Grade    Grade   Ounces   Tonnes
                           (kt)    (g/t)      (%)    (g/t)    (koz)      (t)
----------------------------------------------------------------------------
Boinas Oxide                638     4.42     1.05    25.01       91    6,707
Boinas Skarn                666     2.79     0.78    16.58       60    5,201
Carles Skarn                 38     4.55     0.68     5.26        6      258
----------------------------------------------------------------------------
Total Measured            1,342     3.62     0.91    20.27      156   12,166
----------------------------------------------------------------------------
Boinas Oxide              1,835     6.76     0.80    13.47      399   14,687
Boinas Skarn              1,770     3.16     0.58    14.40      180   10,333
Carles Skarn              1,059     3.40     0.41     6.22      116    4,312
----------------------------------------------------------------------------
Total Indicated           4,664     4.63     0.63    12.18      695   29,332
----------------------------------------------------------------------------
Total Measured &                                                            
 Indicated                6,006     4.41     0.69    13.98      851   41,498
----------------------------------------------------------------------------
Boinas Oxide              2,499     7.16     0.46     3.63      575   11,414
Boinas Skarn              2,135     3.35     0.45    12.27      230    9,515
Carles Skarn              1,393     3.90     0.43     4.12      175    5,957
----------------------------------------------------------------------------
Total Inferred            6,027     5.05     0.45     6.80      980   26,886
----------------------------------------------------------------------------

Notes:

1.  Canadian Institute of Mining, Metallurgy and Petroleum ("CIM")
    definitions were followed for estimated mineral resources. 
2.  Mineral resources are estimated using gold equivalent cut-off grade by
    zone, consisting of 3.8 g/t AuEq for Boinas Oxides, 2.5 g/t AuEq for
    Boinas Skarns, and 2.3 g/t AuEq for Carles. Gold equivalent cut-offs
    were calculated using recent operating results for recoveries, off-site
    concentrate costs, and on-site operating costs. 
3.  Mineral resources are estimated using average long-term metal prices of
    US$1,300 per ounce gold, US$3.10 per pound copper, and US$23 per ounce
    silver. An exchange rate of EUR1.00=US$1.33 was used. 
4.  A crown pillar of 10 meters is excluded from the estimated mineral
    resources below El Valle open pit. 
5.  Unrecoverable material in exploited mining areas has been excluded from
    the estimated mineral resources. 
6.  Numbers may not add due to rounding.

                                   TABLE 2                                  
             Orvana - Updated EVBC Mineral Reserve Estimate (1)             
----------------------------------------------------------------------------
                       EVBC Mineral Reserve Estimate as at Sept. 30th, 2014 
                      ------------------------------------------------------
                                      Au       Cu       Ag       Au       Cu
                         Tonnes    Grade    Grade    Grade   Ounces   Tonnes
ZONE                       (kt)    (g/t)      (%)    (g/t)    (koz)      (t)
----------------------------------------------------------------------------
Boinas Oxide                  -        -        -        -        -        -
Boinas Skarn                467     3.36     0.96    20.33       50    4,484
Carles Skarn                  -        -        -        -        -        -
----------------------------------------------------------------------------
Total Proven                467     3.36     0.96    20.33       50    4,484
----------------------------------------------------------------------------
Boinas Oxide                598     6.83     0.41     7.31      131    2,464
Boinas Skarn              1,029     3.39     0.72    14.39      112    7,375
Carles Skarn                 95     2.63     0.37     7.30        8      354
----------------------------------------------------------------------------
Total Probable            1,722     4.54     0.59    11.54      252   10,193
----------------------------------------------------------------------------
Total Proven &                                                              
 Probable                 2,189     4.29     0.67    13.41      302   14,677
----------------------------------------------------------------------------

Notes:

1.  CIM definitions were followed for Mineral Reserves. 
2.  Mineral Reserves are estimated using gold equivalent cut-off grades by
    zone, consisting of 4.5 g/t AuEq for Boinas Oxides, 2.9 g/t AuEq for
    Boinas Skarns, and 2.8 g/t AuEq for Carles. Gold equivalent cut-offs
    were calculated using recent operating results for recoveries, off-site
    concentrate costs, and on-site operating costs. 
3.  Mineral Reserves are estimated using average long-term metal prices of
    US$1,100 per ounce gold, US$2.75 per pound copper, and US$20 per ounce
    silver. An exchange rate of EUR1.00=US$1.33 was used. 
4.  Numbers may not add due to rounding.

Contacts:
Orvana Minerals Corp.
Michael Winship
President and Chief Executive Officer
(416) 369-1629

Orvana Minerals Corp.
Daniella Dimitrov
Chief Financial Officer
(416) 369-1629

Orvana Minerals Corp.
Ann Wilkinson
Investor Relations
(416) 369-6275
[email protected] / [email protected]
www.orvana.com

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
Cloud Expo | DXWorld Expo have announced the conference tracks for Cloud Expo 2018. Cloud Expo will be held June 5-7, 2018, at the Javits Center in New York City, and November 6-8, 2018, at the Santa Clara Convention Center, Santa Clara, CA. Digital Transformation (DX) is a major focus with the introduction of DX Expo within the program. Successful transformation requires a laser focus on being data-driven and on using all the tools available that enable transformation if they plan to survive ov...
A strange thing is happening along the way to the Internet of Things, namely far too many devices to work with and manage. It has become clear that we'll need much higher efficiency user experiences that can allow us to more easily and scalably work with the thousands of devices that will soon be in each of our lives. Enter the conversational interface revolution, combining bots we can literally talk with, gesture to, and even direct with our thoughts, with embedded artificial intelligence, whic...
You know you need the cloud, but you're hesitant to simply dump everything at Amazon since you know that not all workloads are suitable for cloud. You know that you want the kind of ease of use and scalability that you get with public cloud, but your applications are architected in a way that makes the public cloud a non-starter. You're looking at private cloud solutions based on hyperconverged infrastructure, but you're concerned with the limits inherent in those technologies. What do you do?
Recently, REAN Cloud built a digital concierge for a North Carolina hospital that had observed that most patient call button questions were repetitive. In addition, the paper-based process used to measure patient health metrics was laborious, not in real-time and sometimes error-prone. In their session at 21st Cloud Expo, Sean Finnerty, Executive Director, Practice Lead, Health Care & Life Science at REAN Cloud, and Dr. S.P.T. Krishnan, Principal Architect at REAN Cloud, discussed how they built...
Recently, WebRTC has a lot of eyes from market. The use cases of WebRTC are expanding - video chat, online education, online health care etc. Not only for human-to-human communication, but also IoT use cases such as machine to human use cases can be seen recently. One of the typical use-case is remote camera monitoring. With WebRTC, people can have interoperability and flexibility for deploying monitoring service. However, the benefit of WebRTC for IoT is not only its convenience and interopera...
In his general session at 21st Cloud Expo, Greg Dumas, Calligo’s Vice President and G.M. of US operations, discussed the new Global Data Protection Regulation and how Calligo can help business stay compliant in digitally globalized world. Greg Dumas is Calligo's Vice President and G.M. of US operations. Calligo is an established service provider that provides an innovative platform for trusted cloud solutions. Calligo’s customers are typically most concerned about GDPR compliance, application p...
Modern software design has fundamentally changed how we manage applications, causing many to turn to containers as the new virtual machine for resource management. As container adoption grows beyond stateless applications to stateful workloads, the need for persistent storage is foundational - something customers routinely cite as a top pain point. In his session at @DevOpsSummit at 21st Cloud Expo, Bill Borsari, Head of Systems Engineering at Datera, explored how organizations can reap the bene...
With tough new regulations coming to Europe on data privacy in May 2018, Calligo will explain why in reality the effect is global and transforms how you consider critical data. EU GDPR fundamentally rewrites the rules for cloud, Big Data and IoT. In his session at 21st Cloud Expo, Adam Ryan, Vice President and General Manager EMEA at Calligo, examined the regulations and provided insight on how it affects technology, challenges the established rules and will usher in new levels of diligence arou...
Continuous Delivery makes it possible to exploit findings of cognitive psychology and neuroscience to increase the productivity and happiness of our teams. In his session at 22nd Cloud Expo | DXWorld Expo, Daniel Jones, CTO of EngineerBetter, will answer: How can we improve willpower and decrease technical debt? Is the present bias real? How can we turn it to our advantage? Can you increase a team’s effective IQ? How do DevOps & Product Teams increase empathy, and what impact does empath...
"I focus on what we are calling CAST Highlight, which is our SaaS application portfolio analysis tool. It is an extremely lightweight tool that can integrate with pretty much any build process right now," explained Andrew Siegmund, Application Migration Specialist for CAST, in this SYS-CON.tv interview at 21st Cloud Expo, held Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA.
SYS-CON Events announced today that Evatronix will exhibit at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. Evatronix SA offers comprehensive solutions in the design and implementation of electronic systems, in CAD / CAM deployment, and also is a designer and manufacturer of advanced 3D scanners for professional applications.
SYS-CON Events announced today that Synametrics Technologies will exhibit at SYS-CON's 22nd International Cloud Expo®, which will take place on June 5-7, 2018, at the Javits Center in New York, NY. Synametrics Technologies is a privately held company based in Plainsboro, New Jersey that has been providing solutions for the developer community since 1997. Based on the success of its initial product offerings such as WinSQL, Xeams, SynaMan and Syncrify, Synametrics continues to create and hone inn...
As many know, the first generation of Cloud Management Platform (CMP) solutions were designed for managing virtual infrastructure (IaaS) and traditional applications. But that's no longer enough to satisfy evolving and complex business requirements. In his session at 21st Cloud Expo, Scott Davis, Embotics CTO, explored how next-generation CMPs ensure organizations can manage cloud-native and microservice-based application architectures, while also facilitating agile DevOps methodology. He expla...
To get the most out of their data, successful companies are not focusing on queries and data lakes, they are actively integrating analytics into their operations with a data-first application development approach. Real-time adjustments to improve revenues, reduce costs, or mitigate risk rely on applications that minimize latency on a variety of data sources. In his session at @BigDataExpo, Jack Norris, Senior Vice President, Data and Applications at MapR Technologies, reviewed best practices to ...
DevOps promotes continuous improvement through a culture of collaboration. But in real terms, how do you: Integrate activities across diverse teams and services? Make objective decisions with system-wide visibility? Use feedback loops to enable learning and improvement? With technology insights and real-world examples, in his general session at @DevOpsSummit, at 21st Cloud Expo, Andi Mann, Chief Technology Advocate at Splunk, explored how leading organizations use data-driven DevOps to close th...