Orvana Announces Decrease in Resources and Reserves at EVBC and Updates Life-of-Mine Plan

-- EVBC estimated mine life approximately four years with AISC of $1,100

TORONTO, ONTARIO -- (Marketwired) -- 08/13/14 -- Orvana Minerals Corp. ("Orvana" or the "Company") (TSX: ORV) announces that it has received updated mineral resources and reserves estimates (the "MRMR Update") for El Valle-Boinas/Carles ("EVBC") gold-copper mines in northern Spain, showing a year-over-year decrease in reserves and resources. The Company also received an updated life-of-mine plan (the "LOMP Update") using proven and probable mineral reserves reflecting a shortened mine life based on these updated reserves. The Company also announces that it expects to place the Carles Mine on care and maintenance by the end of 2014.

EVBC has had a record of under-performance against plan with respect to gold output. In 2014, Orvana initiated a review of past performance, including measures taken by previous and current management teams to enhance mine performance. As a result of this review, management deemed it appropriate to further assess the assumptions of previous mine plans, particularly in regard to reserves and resources, and engaged Roscoe Postle Associates Inc. ("RPA") to complete the MRMR Update and LOMP Update.

The MRMR Update and the LOMP Update revise certain assumptions used previously and present a different methodology with respect to the application of cut-off grades in certain zones of EVBC. Various other factors resulting in the changes include removal of uneconomic zones and depletion from mining activities since June 1, 2013.

"The reserve and resource reductions are disappointing. Orvana's decisions in response to these decreases and associated life-of-mine adjustments are difficult but necessary steps," said Michael Winship, President and CEO of Orvana. "Orvana will optimize production at Boinas Mine and will focus on producing only profitable ounces. Production will increase at Boinas, while the Carles Mine will be placed on care and maintenance by the end of 2014. We believe that these measures, coupled with the significant repayment of debt, will enable us to achieve improvements in free cash flow."

MRMR Update

The MRMR Update and the LOMP Update were prepared in accordance with National Instrument 43-101 - Standards of Disclosure for Mineral Projects ("NI 43-101") by RPA, an independent mining consulting firm. RPA will be completing a NI 43-101 technical report with respect to the MRMR Update and the LOMP Update, which will be filed on SEDAR within 45 days.

The Company has most recently published mineral resources and reserves estimates for EVBC as at June 1, 2013 in its annual information form dated December 19, 2013 (the "2013 AIF").

The following is a summary of the MRMR Update with more detailed information set forth in Table 1 and Table 2 in the appendix to this press release:


--  Proven and Probable Reserves - approximately 2.2 million tonnes grading
    4.3 g/t gold and 0.7% copper, containing 302,000 ounces of gold and
    14,680 tonnes of copper, a decrease of approximately 66% and 59%,
    respectively;

--  Measured and Indicated Resources - approximately 6.0 million tonnes
    grading 4.4 g/t gold and 0.7% copper, containing 850,900 ounces of gold
    and 41,500 tonnes of copper, a decrease of approximately 32% and 22%,
    respectively; and

--  Inferred Resources - approximately 6.0 million tonnes grading 5.0 g/t
    gold and 0.5% copper, containing 979,500 ounces of gold and 26,900
    tonnes of copper, a decrease of approximately 22% and 5%, respectively.

LOMP Update

RPA completed the LOMP Update based on proven and probable reserves estimated as part of the MRMR Update which estimates mine life for EVBC at approximately four years compared with approximately nine years as previously disclosed. Total gold production is expected to be approximately 282,200 ounces at an average all-in-sustaining cost per ounce of gold sold of approximately $1,100 over the currently estimated mine life.

In addition, the inferred mineral resources are estimated to contain 979,500 gold ounces, providing opportunities to extend the mine life.

"Management will continue to focus on delineation drilling at EVBC, which historically has enabled us to convert mineral resources into reserves. We believe there is upside potential to extend EVBC's mine life beyond this current estimate," said Mr. Winship.

Carles Mine Suspension

Orvana plans to ramp down and put Carles on care and maintenance pending an improved economic mining plan or higher metal prices. In addition to executing on the new optimization plan, which has yielded improved results in recent months, the Company is also undertaking a review of alternatives. This includes evaluating narrow high-grade areas in Carles for more suitable mining methods and further exploration targeting certain zones and satellite deposits in the region.

EVBC Impairment

As a result of the MRMR Update and the Carles suspension and in accordance with its usual policy, Orvana conducted a carrying value assessment of EVBC as at June 30, 2014 and determined that EVBC's net recoverable amount was lower than its carrying amount. As a result, Orvana recognized a non-cash impairment loss in respect of EVBC of $25.5 million in the third quarter of fiscal 2014.

In a separate news release issued today, Orvana announced its operating and financial results as at and for the three and nine months ended June 30, 2014.

Orvana Strategy

In the context of the MRMR Update and the LOMP Update, Orvana is initiating a comprehensive strategic review of the Company and its asset base. This review will encompass the consideration of a number of possible outcomes for Orvana and its shareholders and may include exploration, asset transactions or a corporate transaction. Orvana will report on its progress in due course.

"We continue to build on the progress we have made in recent months," said Mr. Winship. "At the same time, and taking into account the updates to our mine operations, the Board together with management will thoughtfully and deliberately review our strategy for future growth and value creation."

Qualified Persons

The scientific and technical information contained in this press release has been reviewed and approved (i) in respect of the estimated mineral reserves and the LOMP Update by Jason Cox, P.Eng., of RPA, and (ii) in respect of the estimated mineral resources by Sean Horan, P.Geo., of RPA. RPA is an independent mining consultant and each of Messrs. Cox and Horan is a Qualified Person within the meaning of NI 43-101.

About Orvana

Orvana Minerals is a multi-mine gold and copper producer. Orvana's operating assets consist of the EVBC gold-copper mines in northern Spain and copper-gold-silver Don Mario Mine in Bolivia. Additional information is available at Orvana's website (www.orvana.com).

Forward Looking Disclaimer

Certain statements in this press release constitute forward-looking statements or forward-looking information within the meaning of applicable securities laws ("forward-looking statements"). Any statements that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions, potentials, future events or performance (often, but not always, using words or phrases such as "believes", "expects" "plans", "estimates" or "intends" or stating that certain actions, events or results "may", "could", "would", "might", "will" or "are projected to" be taken or achieved) are not statements of historical fact, but are forward-looking statements.

The forward-looking statements herein relate to, among other things, Orvana's ability to achieve improvement in free cash flow; the potential to extend EVBC's mine life beyond the life of mine estimate set forth herein; Orvana's ability to optimize its assets to deliver shareholder value; Orvana's ability to optimize production at Boinas; the expected costs associated with the suspension of mining activities at Carles; the Company's ability to emerge stronger from the turnaround work executed at EVBC in 2014; estimates of future production, operating costs and capital expenditures; mineral resource and reserve estimates; statements and information regarding future feasibility studies and their results; future transactions; future metal prices; the ability to achieve additional growth and geographic diversification; future financial performance, including the ability to increase cash flow and profits; future financing requirements; and mine development plans.

Forward-looking statements are necessarily based upon a number of estimates and assumptions that, while considered reasonable by Orvana as of the date of such statements, are inherently subject to significant business, economic and competitive uncertainties and contingencies. The estimates and assumptions of Orvana contained or incorporated by reference in this news release, which may prove to be incorrect, include, but are not limited to, the various assumptions set forth herein and in the Company's most recently filed Management's Discussion & Analysis and Annual Information Form in respect of the Company's most recently completed fiscal year (the "Company Disclosures"), or as otherwise expressly incorporated herein by reference as well as: there being no significant disruptions affecting operations, whether due to labour disruptions, supply disruptions, power disruptions, damage to equipment or otherwise; permitting, development, operations, expansion and acquisitions at the EVBC and Don Mario Mines being consistent with the Company's current expectations; political developments in any jurisdiction in which the Company operates being consistent with its current expectations; certain price assumptions for gold, copper and silver; prices for key supplies being approximately consistent with current levels; production and cost of sales forecasts meeting expectations; the accuracy of the Company's current mineral reserve and mineral resource estimates; and labour and materials costs increasing on a basis consistent with Orvana's current expectations.

A variety of inherent risks, uncertainties and factors, many of which are beyond the Company's control, affect the operations, performance and results of the Company and its business, and could cause actual events or results to differ materially from estimated or anticipated events or results expressed or implied by forward looking statements. Some of these risks, uncertainties and factors include fluctuations in the price of gold, silver and copper; the need to recalculate estimates of resources based on actual production experience; the failure to achieve production estimates; variations in the grade of ore mined; variations in the cost of operations; variations in the costs associated with the suspension of mining at Carles; the availability of qualified personnel; the Company's ability to obtain and maintain all necessary regulatory approvals and licenses; the Company's ability to use cyanide in its mining operations; risks generally associated with mineral exploration and development, including the Company's ability to continue to operate the EVBC Mines and/or the Don Mario Mine; the Company's ability to acquire and develop mineral properties and to successfully integrate such acquisitions; the Company's ability to obtain financing when required on terms that are acceptable to the Company; the Company's ability to execute on its strategy; challenges to the Company's interests in its property and mineral rights; current, pending and proposed legislative or regulatory developments or changes in political, social or economic conditions in the countries in which the Company operates; general economic conditions worldwide; and the risks identified in the Company Disclosures under the heading "Risks and Uncertainties". This list is not exhaustive of the factors that may affect any of the Company's forward-looking statements and reference should also be made to the Company Disclosures for a description of additional risk factors.

Forward-looking statements are based on management's current plans, estimates, projections, beliefs and opinions and, except as required by law, the Company does not undertake any obligation to update forward-looking statements should assumptions related to these plans, estimates, projections, beliefs and opinions change. Readers are cautioned not to put undue reliance on forward-looking statements.

Cautionary Notes to Investors - Reserve and Resource Estimates

In accordance with applicable Canadian securities regulatory requirements, all mineral reserve and mineral resource estimates of the Company disclosed in this news release have been prepared as at September 30, 2014 in accordance with Canadian National Instrument 43-101 - Standards of Disclosure for Mineral Projects ("NI 43-101"), classified in accordance with Canadian Institute of Mining Metallurgy and Petroleum's "CIM Standards on Mineral Resources and Reserves Definitions and Guidelines" (the "CIM Guidelines").

Pursuant to the CIM Guidelines, mineral resources have a higher degree of uncertainty than mineral Reserves as to their existence as well as their economic and legal feasibility. Inferred mineral resources, when compared with measured or indicated mineral resources, have the least certainty as to their existence, and it cannot be assumed that all or any part of an inferred mineral resource will be upgraded to an indicated or measured mineral resource as a result of continued exploration. Pursuant to NI 43-101, inferred mineral resources may not form the basis of any economic analysis, including any feasibility study. Accordingly, readers are cautioned not to assume that all or any part of a mineral resource exists, will ever be converted into a mineral Reserve, or is or will ever be economically or legally mineable or recovered.



                                  APPENDIX
                                   TABLE 1
            Orvana - Updated EVBC Mineral Resource Estimate (1)
----------------------------------------------------------------------------
                       EVBC Inclusive Mineral Resource Estimate as at Sept.
ZONE                                        30th, 2014
                      ------------------------------------------------------
                                      Au       Cu       Ag       Au       Cu
                         Tonnes    Grade    Grade    Grade   Ounces   Tonnes
                           (kt)    (g/t)      (%)    (g/t)    (koz)      (t)
----------------------------------------------------------------------------
Boinas Oxide                638     4.42     1.05    25.01       91    6,707
Boinas Skarn                666     2.79     0.78    16.58       60    5,201
Carles Skarn                 38     4.55     0.68     5.26        6      258
----------------------------------------------------------------------------
Total Measured            1,342     3.62     0.91    20.27      156   12,166
----------------------------------------------------------------------------
Boinas Oxide              1,835     6.76     0.80    13.47      399   14,687
Boinas Skarn              1,770     3.16     0.58    14.40      180   10,333
Carles Skarn              1,059     3.40     0.41     6.22      116    4,312
----------------------------------------------------------------------------
Total Indicated           4,664     4.63     0.63    12.18      695   29,332
----------------------------------------------------------------------------
Total Measured &
 Indicated                6,006     4.41     0.69    13.98      851   41,498
----------------------------------------------------------------------------
Boinas Oxide              2,499     7.16     0.46     3.63      575   11,414
Boinas Skarn              2,135     3.35     0.45    12.27      230    9,515
Carles Skarn              1,393     3.90     0.43     4.12      175    5,957
----------------------------------------------------------------------------
Total Inferred            6,027     5.05     0.45     6.80      980   26,886
----------------------------------------------------------------------------

Notes:


1.  Canadian Institute of Mining, Metallurgy and Petroleum ("CIM")
    definitions were followed for estimated mineral resources.
2.  Mineral resources are estimated using gold equivalent cut-off grade by
    zone, consisting of 3.8 g/t AuEq for Boinas Oxides, 2.5 g/t AuEq for
    Boinas Skarns, and 2.3 g/t AuEq for Carles. Gold equivalent cut-offs
    were calculated using recent operating results for recoveries, off-site
    concentrate costs, and on-site operating costs.
3.  Mineral resources are estimated using average long-term metal prices of
    US$1,300 per ounce gold, US$3.10 per pound copper, and US$23 per ounce
    silver. An exchange rate of EUR1.00=US$1.33 was used.
4.  A crown pillar of 10 meters is excluded from the estimated mineral
    resources below El Valle open pit.
5.  Unrecoverable material in exploited mining areas has been excluded from
    the estimated mineral resources.
6.  Numbers may not add due to rounding.

                                   TABLE 2
             Orvana - Updated EVBC Mineral Reserve Estimate (1)
----------------------------------------------------------------------------
                       EVBC Mineral Reserve Estimate as at Sept. 30th, 2014
                      ------------------------------------------------------
                                      Au       Cu       Ag       Au       Cu
                         Tonnes    Grade    Grade    Grade   Ounces   Tonnes
ZONE                       (kt)    (g/t)      (%)    (g/t)    (koz)      (t)
----------------------------------------------------------------------------
Boinas Oxide                  -        -        -        -        -        -
Boinas Skarn                467     3.36     0.96    20.33       50    4,484
Carles Skarn                  -        -        -        -        -        -
----------------------------------------------------------------------------
Total Proven                467     3.36     0.96    20.33       50    4,484
----------------------------------------------------------------------------
Boinas Oxide                598     6.83     0.41     7.31      131    2,464
Boinas Skarn              1,029     3.39     0.72    14.39      112    7,375
Carles Skarn                 95     2.63     0.37     7.30        8      354
----------------------------------------------------------------------------
Total Probable            1,722     4.54     0.59    11.54      252   10,193
----------------------------------------------------------------------------
Total Proven &
 Probable                 2,189     4.29     0.67    13.41      302   14,677
----------------------------------------------------------------------------

Notes:


1.  CIM definitions were followed for Mineral Reserves.
2.  Mineral Reserves are estimated using gold equivalent cut-off grades by
    zone, consisting of 4.5 g/t AuEq for Boinas Oxides, 2.9 g/t AuEq for
    Boinas Skarns, and 2.8 g/t AuEq for Carles. Gold equivalent cut-offs
    were calculated using recent operating results for recoveries, off-site
    concentrate costs, and on-site operating costs.
3.  Mineral Reserves are estimated using average long-term metal prices of
    US$1,100 per ounce gold, US$2.75 per pound copper, and US$20 per ounce
    silver. An exchange rate of EUR1.00=US$1.33 was used.
4.  Numbers may not add due to rounding.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
Get deep visibility into the performance of your databases and expert advice for performance optimization and tuning. You can't get application performance without database performance. Give everyone on the team a comprehensive view of how every aspect of the system affects performance across SQL database operations, host server and OS, virtualization resources and storage I/O. Quickly find bottlenecks and troubleshoot complex problems.
Internet of @ThingsExpo has announced today that Chris Matthieu has been named tech chair of Internet of @ThingsExpo 2017 New York The 7th Internet of @ThingsExpo will take place on June 6-8, 2017, at the Javits Center in New York City, New York. Chris Matthieu is the co-founder and CTO of Octoblu, a revolutionary real-time IoT platform recently acquired by Citrix. Octoblu connects things, systems, people and clouds to a global mesh network allowing users to automate and control design flo...
"We are an all-flash array storage provider but our focus has been on VM-aware storage specifically for virtualized applications," stated Dhiraj Sehgal of Tintri in this SYS-CON.tv interview at 19th Cloud Expo, held November 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA.
Unless your company can spend a lot of money on new technology, re-engineering your environment and hiring a comprehensive cybersecurity team, you will most likely move to the cloud or seek external service partnerships. In his session at 18th Cloud Expo, Darren Guccione, CEO of Keeper Security, revealed what you need to know when it comes to encryption in the cloud.
"We're a cybersecurity firm that specializes in engineering security solutions both at the software and hardware level. Security cannot be an after-the-fact afterthought, which is what it's become," stated Richard Blech, Chief Executive Officer at Secure Channels, in this SYS-CON.tv interview at @ThingsExpo, held November 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA.
With 15% of enterprises adopting a hybrid IT strategy, you need to set a plan to integrate hybrid cloud throughout your infrastructure. In his session at 18th Cloud Expo, Steven Dreher, Director of Solutions Architecture at Green House Data, discussed how to plan for shifting resource requirements, overcome challenges, and implement hybrid IT alongside your existing data center assets. Highlights included anticipating workload, cost and resource calculations, integrating services on both sides...
According to Forrester Research, every business will become either a digital predator or digital prey by 2020. To avoid demise, organizations must rapidly create new sources of value in their end-to-end customer experiences. True digital predators also must break down information and process silos and extend digital transformation initiatives to empower employees with the digital resources needed to win, serve, and retain customers.
"We are the public cloud providers. We are currently providing 50% of the resources they need for doing e-commerce business in China and we are hosting about 60% of mobile gaming in China," explained Yi Zheng, CPO and VP of Engineering at CDS Global Cloud, in this SYS-CON.tv interview at 19th Cloud Expo, held November 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA.
The WebRTC Summit New York, to be held June 6-8, 2017, at the Javits Center in New York City, NY, announces that its Call for Papers is now open. Topics include all aspects of improving IT delivery by eliminating waste through automated business models leveraging cloud technologies. WebRTC Summit is co-located with 20th International Cloud Expo and @ThingsExpo. WebRTC is the future of browser-to-browser communications, and continues to make inroads into the traditional, difficult, plug-in web co...
Between 2005 and 2020, data volumes will grow by a factor of 300 – enough data to stack CDs from the earth to the moon 162 times. This has come to be known as the ‘big data’ phenomenon. Unfortunately, traditional approaches to handling, storing and analyzing data aren’t adequate at this scale: they’re too costly, slow and physically cumbersome to keep up. Fortunately, in response a new breed of technology has emerged that is cheaper, faster and more scalable. Yet, in meeting these new needs they...
When it comes to cloud computing, the ability to turn massive amounts of compute cores on and off on demand sounds attractive to IT staff, who need to manage peaks and valleys in user activity. With cloud bursting, the majority of the data can stay on premises while tapping into compute from public cloud providers, reducing risk and minimizing need to move large files. In his session at 18th Cloud Expo, Scott Jeschonek, Director of Product Management at Avere Systems, discussed the IT and busin...
In his general session at 19th Cloud Expo, Manish Dixit, VP of Product and Engineering at Dice, discussed how Dice leverages data insights and tools to help both tech professionals and recruiters better understand how skills relate to each other and which skills are in high demand using interactive visualizations and salary indicator tools to maximize earning potential. Manish Dixit is VP of Product and Engineering at Dice. As the leader of the Product, Engineering and Data Sciences team at D...
The Internet of Things (IoT) promises to simplify and streamline our lives by automating routine tasks that distract us from our goals. This promise is based on the ubiquitous deployment of smart, connected devices that link everything from industrial control systems to automobiles to refrigerators. Unfortunately, comparatively few of the devices currently deployed have been developed with an eye toward security, and as the DDoS attacks of late October 2016 have demonstrated, this oversight can ...
What happens when the different parts of a vehicle become smarter than the vehicle itself? As we move toward the era of smart everything, hundreds of entities in a vehicle that communicate with each other, the vehicle and external systems create a need for identity orchestration so that all entities work as a conglomerate. Much like an orchestra without a conductor, without the ability to secure, control, and connect the link between a vehicle’s head unit, devices, and systems and to manage the ...
"Once customers get a year into their IoT deployments, they start to realize that they may have been shortsighted in the ways they built out their deployment and the key thing I see a lot of people looking at is - how can I take equipment data, pull it back in an IoT solution and show it in a dashboard," stated Dave McCarthy, Director of Products at Bsquare Corporation, in this SYS-CON.tv interview at @ThingsExpo, held November 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA.