China Gold International Reports 2014 Second Quarter and First Half Results and Revises 2014 Annual Production Outlook

The Company completes construction of the facilities for stage one of Phase II expansion at Jiama. The Company reduces total and cash production costs at both mines.

VANCOUVER, Aug. 14, 2014 /CNW/ - China Gold International Resources Corp. Ltd. (TSX: CGG; HKEx: 2099) (the "Company" or "China Gold International Resources") reports financial and operational results for the three months ("Q2", "quarter" or "second quarter 2014") and six months ("first half" or "six months 2014") ended June 30, 2014. The Company revises its 2014 annual production guidance.

Selected Production and Financial Highlights: Q2 2014 Compared to Q2 2013

  • Consolidated revenues of US$48.5 million for the second quarter of 2014 decreased by US$33.1 million, from US$81.6 million for the same period in 2013.
  • Revenues from the Chang Shan Hao Gold Mine (the "CSH Mine", the "CSH Gold Mine" or "CSH") of US$28.1 million (Q2, 2013: US$46.2 million) decreased by US$ 18.1 million due to a 35% decrease in gold sales volume and significantly lower gold prices.
  • Revenue from the Jiama Copper-Gold Polymetallic Mine (the "Jiama Mine" or "Jiama") of US$20.4 million (Q2, 2013: US$35.4 million) decreased by US$15 million due to a 27% decrease in copper sales  due to changes in market demand.  During the three month period, the Company was stockpiling the copper concentrate until market demand improves.
  • Net income of the Company of US$8.4 million for the three months ended June 30, 2014 decreased by US$11.1 million from US$19.5 million for the three months ended June 30, 2013. 
  • Gold production at the CSH Mine decreased to 24,571 ounces for the three months ended June 30, 2014, compared to 32,111 ounces for the three months ended June 30, 2013.  Despite the higher grade of ore, gold output decreased due to lower recovery rates which were a result of longer leaching time with an increased height of the leaching heap.  
  • The cash and total production costs of gold per ounce for the three months ended June 30, 2014 decreased compared with the same period in 2013 due to the lower processing and waste rock removal costs during the current quarter.

CSH Mine

Three months ended June 30,


2014

2013

Total production cost (US$) of gold per ounce

733

877




Total Cash production cost* (US$) of gold per ounce

446

734

* Non-IFRS measure



  • Copper production from the Jiama Mine amounted to 9.6 million pounds during the three months ended June 30, 2014 compared to 7.7 million pounds during the three months ended June 30, 2013.
  • Cash and total production cost of copper per pound decreased in Q2, 2014 compared with the same period in 2013 due to the increase in the grade of ores during the current period.

Jiama Mine

   Three months ended June 30,


2014

2013




Total production cost* (US$) of copper per pound

after by-products credits

1.78

2.11




Cash production cost**  (US$) of copper per pound

after by-products credits

1.09

1.55

*

Production costs include expenditures incurred at the mine sites for the activities related to production including mining, processing, mine site G&A and royalties etc.

**

Non-IFRS measure

Selected Financial Highlights: First Half 2014 Compared to First Half 2013

  • Consolidated revenues of US$85.2 million for the first half of 2014 increased by US$73.2 million, from US$158.4 million for the same period in 2013.
  • Revenues from the Chang Shan Hao Gold Mine of US$59.7 million (first half 2013: US$93.6 million) decreased by US$33.9 million due to a 27% decrease in gold sales volume and significantly lower gold prices.
  • Gold produced by the CSH Mine amounted to 51,689 ounces, compared to 64,274 ounces for the same period in 2013. The decrease is due to longer recovery periods as a result of the increased height of the leaching heap.
  • Revenue from the Jiama Copper-Gold Polymetallic Mine of US$25.5 million (first half 2013: US$64.7 million) decreased mostly due to a significant decrease in copper production during the first quarter of 2014, due to a seasonal electricity shortage experienced by the Jiama Mine.
  • Net income of the Company of US$9.7 million for the six months ended June 30, 2014, decreased by US$24.9 million from US$34.6 million for the six months ended June 30, 2013. 

Mr. Bing Liu, the CEO and Executive Director of the Company, commented, "We have achieved numerous milestones so far in 2014. We have completed the first stage of construction of the Jiama Mine's Phase II expansion on time.  We have successfully managed a US$500 million bond issue.  We are reducing costs at both of our mines. At the same time, our company and the rest of the industry are facing challenging market conditions. We believe our superior technical and operating experience and our ability to raise financing will help us weather this downturn in the industry and still deliver profits and growth to our shareholders".

Selected 2014 Operational Achievements

  • Phase II expansion at the Jiama Mine is progressing as planned. The first stage of Phase II expansion facilities construction, including ore storage silo, crusher, mills floatation circuits, thickeners, and power and water supply systems was completed in the second quarter of 2014. This increased the mill processing capacity from 6,000 tpd to 28,000 tpd. The pre-striping for open pits and ore transportation system for the first stage of the Phase II production facility will be completed in the second half of 2014. The new production facility is currently under testing. The output of copper concentrate from the first stage of the production facility is expected during the second half of 2014.
  • The Company continues its company-wide cost reduction strategy which has resulted in significant decreases in total and cash operating costs for both mines.

2014 Revised Production and Operating Outlook for CSH and Jiama

  • On May 15, 2014, the Company reported expected 2014 annual gold production guidance to be 208,000 ounces. The Company revises this 2014 annual gold production guidance to 165,000 ounces. This is an 11% increase from the 2013 actual gold output of 148,326 ounces of gold. The revision of the forecast is due to the longer commissioning period of the expansion at CSH, caused by repair and reinforcement of the heap leach pad. In addition, the revision is in consideration of the longer gold recovery period due to the increased heap leach height which resulted in reduced gold production in the first half of 2014.  The company has sufficient funding and operational and technical expertise to successfully resolve those challenges.
  • In the first half of 2014 the Company had reported that its ongoing initiatives to increase production, productivity and efficiency at the Jiama Mine were expected to enable it to meet its previously mentioned 2014 production guidance of approximately 50 million pounds of copper. The Company revises its 2014 expected copper production guidance to 28.6 million pounds, which is a slight increase from the 2013 actual copper output of 28.3 million pounds. This revision is due to the reduced production in the first quarter of 2014, as Jiama experienced power supply shortages.  In addition, the revision is in consideration of expected lower recovery rate from the high oxide ore from the south pit during the second half of 2014, uncertainties relating to power supply shortage in the fourth quarter and duration of the commissioning period of the Phase II expansion. 
  • The Company will continue to leverage the technical and operating experience of the Company's controlling shareholder, China National Gold Group Corporation ("CNG"), to improve operations at its mines, increase production and minimize costs.
  • To fulfill its growth strategy, the Company is continually working with CNG and other interested parties to identify potential international mining opportunities, mainly outside of China, which can be readily and quickly brought into production with the possibility of further expansion through continued exploration.

Analysts, investors, media and general public are encouraged to visit the Company's website, sedar.com or hkexnews.hk to view the complete set of the financial statements and MD&A or contact the Company with any questions.

About China Gold International Resources

China Gold International Resources Corp. Ltd. is based in Vancouver, BC, Canada and operates both profitable and growing mines, the CSH Gold Mine in Inner Mongolia, and the Jiama Copper-Polymetallic Mine in Tibet Autonomous Region of the People's Republic of China. The Company's objective is to continue to build shareholder value by growing production at its current mining operations, expanding its resource base, and aggressively acquiring and developing new projects internationally. The Company is listed on the Toronto Stock Exchange (TSX: CGG) and the Main Board of The Stock Exchange of Hong Kong Limited (HKEx: 2099).

For a detailed look at the financial statements and MD&A for the quarter ended March 31, 2013, please visit the Company's website at www.chinagoldintl.com, The Stock Exchange of Hong Kong Limited's website at www.hkex.com.hk or SEDAR at www.sedar.com.

Cautionary Note About Forward-Looking Statements

Certain information regarding China Gold International Resources contained herein may constitute forward-looking statements within the meaning of applicable securities laws. Forward-looking statements may include estimates, plans, expectations, opinions, forecasts, projections, guidance or other statements that are not statements of fact. Although China Gold International Resources believes that the expectations reflected in such forward-looking statements are reasonable, it can give no assurance that such expectations will prove to have been correct. China Gold International Resources cautions that actual performance will be affected by a number of factors, most of which are beyond its control, and that future events and results may vary substantially from what China Gold International Resources currently foresees. Factors that could cause actual results to differ materially from those in forward-looking statements include market prices, exploitation and exploration results, continued availability of capital and financing and general economic, market or business conditions. The forward-looking statements are expressly qualified in their entirety by this cautionary statement. The information contained herein is stated as of the current date and subject to change after that date.

SOURCE China Gold International Resources Corp. Ltd.

More Stories By PR Newswire

Copyright © 2007 PR Newswire. All rights reserved. Republication or redistribution of PRNewswire content is expressly prohibited without the prior written consent of PRNewswire. PRNewswire shall not be liable for any errors or delays in the content, or for any actions taken in reliance thereon.

Latest Stories
Cognitive Computing is becoming the foundation for a new generation of solutions that have the potential to transform business. Unlike traditional approaches to building solutions, a cognitive computing approach allows the data to help determine the way applications are designed. This contrasts with conventional software development that begins with defining logic based on the current way a business operates. In her session at 18th Cloud Expo, Judith S. Hurwitz, President and CEO of Hurwitz & ...
SYS-CON Events announced today that Tintri Inc., a leading producer of VM-aware storage (VAS) for virtualization and cloud environments, will exhibit at the 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. Tintri VM-aware storage is the simplest for virtualized applications and cloud. Organizations including GE, Toyota, United Healthcare, NASA and 6 of the Fortune 15 have said “No to LUNs.” With Tintri they mana...
In his keynote at 18th Cloud Expo, Andrew Keys, Co-Founder of ConsenSys Enterprise, provided an overview of the evolution of the Internet and the Database and the future of their combination – the Blockchain. Andrew Keys is Co-Founder of ConsenSys Enterprise. He comes to ConsenSys Enterprise with capital markets, technology and entrepreneurial experience. Previously, he worked for UBS investment bank in equities analysis. Later, he was responsible for the creation and distribution of life sett...
Fifty billion connected devices and still no winning protocols standards. HTTP, WebSockets, MQTT, and CoAP seem to be leading in the IoT protocol race at the moment but many more protocols are getting introduced on a regular basis. Each protocol has its pros and cons depending on the nature of the communications. Does there really need to be only one protocol to rule them all? Of course not. In his session at @ThingsExpo, Chris Matthieu, co-founder and CTO of Octoblu, walk you through how Oct...
Fact is, enterprises have significant legacy voice infrastructure that’s costly to replace with pure IP solutions. How can we bring this analog infrastructure into our shiny new cloud applications? There are proven methods to bind both legacy voice applications and traditional PSTN audio into cloud-based applications and services at a carrier scale. Some of the most successful implementations leverage WebRTC, WebSockets, SIP and other open source technologies. In his session at @ThingsExpo, Da...
SYS-CON Events announced today that ReadyTalk, a leading provider of online conferencing and webinar services, has been named Vendor Presentation Sponsor at the 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. ReadyTalk delivers audio and web conferencing services that inspire collaboration and enable the Future of Work for today’s increasingly digital and mobile workforce. By combining intuitive, innovative tec...
Major trends and emerging technologies – from virtual reality and IoT, to Big Data and algorithms – are helping organizations innovate in the digital era. However, to create real business value, IT must think beyond the ‘what’ of digital transformation to the ‘how’ to harness emerging trends, innovation and disruption. Architecture is the key that underpins and ties all these efforts together. In the digital age, it’s important to invest in architecture, extend the enterprise footprint to the cl...
SYS-CON Events announced today that Secure Channels will exhibit at the 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. The bedrock of Secure Channels Technology is a uniquely modified and enhanced process based on superencipherment. Superencipherment is the process of encrypting an already encrypted message one or more times, either using the same or a different algorithm.
Vidyo, Inc., has joined the Alliance for Open Media. The Alliance for Open Media is a non-profit organization working to define and develop media technologies that address the need for an open standard for video compression and delivery over the web. As a member of the Alliance, Vidyo will collaborate with industry leaders in pursuit of an open and royalty-free AOMedia Video codec, AV1. Vidyo’s contributions to the organization will bring to bear its long history of expertise in codec technolo...
Traditional on-premises data centers have long been the domain of modern data platforms like Apache Hadoop, meaning companies who build their business on public cloud were challenged to run Big Data processing and analytics at scale. But recent advancements in Hadoop performance, security, and most importantly cloud-native integrations, are giving organizations the ability to truly gain value from all their data. In his session at 19th Cloud Expo, David Tishgart, Director of Product Marketing ...
SYS-CON Events announced today that Bsquare has been named “Silver Sponsor” of SYS-CON's @ThingsExpo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. For more than two decades, Bsquare has helped its customers extract business value from a broad array of physical assets by making them intelligent, connecting them, and using the data they generate to optimize business processes.
If you’re responsible for an application that depends on the data or functionality of various IoT endpoints – either sensors or devices – your brand reputation depends on the security, reliability, and compliance of its many integrated parts. If your application fails to deliver the expected business results, your customers and partners won't care if that failure stems from the code you developed or from a component that you integrated. What can you do to ensure that the endpoints work as expect...
Digitization is driving a fundamental change in society that is transforming the way businesses work with their customers, their supply chains and their people. Digital transformation leverages DevOps best practices, such as Agile Parallel Development, Continuous Delivery and Agile Operations to capitalize on opportunities and create competitive differentiation in the application economy. However, information security has been notably absent from the DevOps movement. Speed doesn’t have to negat...
The Transparent Cloud-computing Consortium (abbreviation: T-Cloud Consortium) will conduct research activities into changes in the computing model as a result of collaboration between "device" and "cloud" and the creation of new value and markets through organic data processing High speed and high quality networks, and dramatic improvements in computer processing capabilities, have greatly changed the nature of applications and made the storing and processing of data on the network commonplace.
Your business relies on your applications and your employees to stay in business. Whether you develop apps or manage business critical apps that help fuel your business, what happens when users experience sluggish performance? You and all technical teams across the organization – application, network, operations, among others, as well as, those outside the organization, like ISPs and third-party providers – are called in to solve the problem.