RB Energy Reports Q2 2014 Results

VANCOUVER, BRITISH COLUMBIA -- (Marketwired) -- 08/15/14 -- RB Energy Inc. (the "Company" or "RBI" or RB Energy") (TSX:RBI)(OTCQX:RBEIF) is pleased to report financial and operating results for the three and six months ended June 30, 2014. The consolidated financial statements together with Management's Discussion and Analysis will be available on the Company's web site (www.rb-e.com) and on SEDAR (www.sedar.com).

SECOND QUARTER HIGHLIGHTS

Quebec Lithium

With the onset of warmer temperatures in the second quarter, the crushing, grinding and concentrator circuits were re-started with the objective of achieving continuous battery grade(1 ) lithium carbonate production from run of mine operations. Production of limited quantities of EV grade(1) lithium carbonate were achieved, however, ramp up issues encountered with the kiln and bi-carbonate reactors delayed production of commercial volumes.

The primary optical ore sorter was delivered to site in late Q2 2014. Installation and commissioning of the ore sorter commenced in July and will be completed in August. The diversion of a road running through the open pit to will allow full access to the open pit commenced in Q2 2014. The diversion is scheduled to be completed by the end of Q3 2014. The construction of a natural gas pipeline to the mine site commenced in Q2 2014 and is on schedule for completion in Q4 2014.

As a result of the commissioning delays, it is now anticipated that commercial production levels of battery grade lithium will be achieved by the end of 2014. Production of EV grade lithium carbonate is targeted for early 2015. The ramp-up to the annual design capacity of 20,000 tonnes is now expected to be achieved in Q1 2015.

The aforementioned delays in the ramp up of production have deferred the anticipated production and sale of commercial quantities of lithium carbonate, thereby accelerating the depletion of the Company's treasury to a greater extent than anticipated. As a result, the Company is working to secure additional sources of funding to complete commissioning, achieve commercial production and realize positive operating cash flow at Quebec Lithium.

Aguas Blancas

For the three months ended June 30, 2014, Aguas Blancas produced 314 tonnes of iodine at a cash cost of US $22 per kg and sold 518 tonnes at an average price of US $36 per kg during Q2 2014. High sales volumes in Q2 2014 offset the low volumes of sales in Q1 2014, which were due principally to disrupted shipments from Chile as a result of earthquakes and a port strike.

(1) Quebec Lithium specifications (lithium carbonate content)


--------------------------------------------------
Technical grade                    99.0%          
--------------------------------------------------
Battery grade                      99.7%          
--------------------------------------------------
Electric Vehicle (EV) grade        99.9%          
--------------------------------------------------

RESULTS FROM OPERATIONS

Quebec Lithium is in the commissioning stage and had not yet generated sales and revenues at the end of Q2 2014. Revenues only included the Aguas Blancas operations of since February 2014 (2013: none) and reflected sales of iodine inventory acquired at its fair value on January 31, 2014 and iodine produced since the Arrangement.

During the three and six months ended June 30, 2014, the Company earned a net profit of $1.3 million ($0.01 earnings per share) and incurred a net loss of $6.2 million ($0.03 loss per share), respectively, compared with net losses of $1.3 million ($0.01 loss per share) and $3.9 million ($0.03 loss per share), respectively, for the same periods in 2013. Included in the Q2 2014 profit is an unrealized foreign exchange gain of $1.5 million due principally to the positive impact of the strengthening of the Canadian dollar against the US dollar on the carrying values of the US dollar denominated convertible debentures, finance lease liabilities, and cash advances from a customer since the end of Q1 2014. More than half of the loss for the six months ended June 30, 2014 ($3.3 million) is due to the one-time transaction costs associated with the Arrangement.

RB Energy incurred general and administrative expenses of $1.8 million (2013: $2.0 million) and $3.6 million (2013: $4.3 million) for the three and six months ended June 30, 2014, respectively, which include costs to maintain offices and staff in Toronto and Montreal to the end of April.


----------------------------------------------------------------------------
                               Three months ended       Six months ended    
(Canadian dollars)             June-14     Jun-13     June-14      Jun-13   
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Total revenues ($000's)                                                     
 (Note 1)                         20,145          -      25,189           - 
----------------------------------------------------------------------------
Net income (loss) ($000's)         1,307     (1,330)     (6,167)     (3,885)
----------------------------------------------------------------------------
Income (loss) per share,                                                    
 basic and diluted ($)              0.01      (0.01)      (0.03)      (0.03)
----------------------------------------------------------------------------
Total assets ($000's) (Note                                                 
 2)                              484,265    344,076                         
----------------------------------------------------                        
Total liabilities ($000's)                                                  
 (Note 2)                        205,215    163,337                         
----------------------------------------------------                        
                                                                            
----------------------------------------------------------------------------
Iodine produced (t) (Note 1)         314          -         525           - 
----------------------------------------------------------------------------
Iodine sold (t) (Note 1)             518          -         644           - 
----------------------------------------------------------------------------
Iodine avg. price ($/kg)                                                    
 (Note 1)                             39          -          39           - 
----------------------------------------------------------------------------
Iodine cash operating cost                                                  
 ($/kg) (Note 1, 3)                   24          -          26           - 
----------------------------------------------------------------------------

Note 1: revenues and iodine data are from February 1 to June 30, 2014, the period post acquisition of Sirocco.

Note 2: comparative data provided as at December 31, 2013.

Note 3: this is a non-GAAP measure. It was calculated by dividing cost of sales, adjusted for the change in inventory and the related depreciation, by quantities of iodine produced in the period.

Note 4: for complete details, refer to the June 30, 2014 interim consolidated financial statements and MD&A.

The increase in total assets and liabilities from December 31, 2013 is due to the acquisition of Sirocco and the consolidation of its net assets as well as the ongoing construction and commissioning of the lithium processing plant in Quebec. Capitalized items include borrowing and operating costs for Quebec Lithium during the period.

OUTLOOK

Quebec Lithium

The operating focus is to ramp up commercial production volumes, achieve commercial production before the end of 2014 and name plate production by the end of Q1 2015. Shipments of lithium carbonate to the Company's main off take partner commenced in August. Modifications to the processing plant to produce EV grade lithium carbonate are scheduled for Q4 2014.

The timetable to Q1 2015 includes four main operating objectives:


1.  achieve continuous shipments of lithium carbonate in Q3 2014; 
2.  complete the commissioning of the primary optical ore sorter (to reduce
    ore dilution) thereby increasing concentrate grade in Q3; 
3.  reach commercial production levels of lithium carbonate by the end of
    2014 and name plate production by the end of Q1 2015; and 
4.  produce EV grade lithium carbonate before the end of Q1 2014 as a result
    of modifications to the processing plant. 

Aguas Blancas

Production at Aguas Blancas was reduced in late 2013 by placing the Agitated Leach Plant ("ALP") on care and maintenance in response to further softening prices in the market. As a result, operations in 2014 are limited to heap leaching. In 2014, production of iodine is estimated at approximately 1,000 tonnes at a cash cost of approximately US $26/kg. Aguas Blancas expects to supplement the sales of its 2014 production by reducing the level of finished product inventory on hand. Subsequent to Q2 2014, the Company has committed to the delivery of approximately 190 tonnes of iodine over the next twelve months to generate additional cash flows in support of commissioning at Quebec Lithium.

About RB Energy Inc.

RBI is a Canadian company formed pursuant to the arrangement involving Sirocco Mining Inc. and Canada Lithium Corp. It currently owns Aguas Blancas, an iodine producing mine in northern Chile, and Quebec Lithium near Val d'Or, the geographical heart of the Quebec mining industry. The Aguas Blancas mine is currently in production. The Quebec Lithium has completed construction and is in the commissioning phase. For more information regarding RBI, please refer to its public filings available at www.sedar.com.

The technical contents of this release have been reviewed by Mr. Kevin Ross, Eur. Ing., a Qualified Person pursuant to NI-43-101. Mr. Ross is Chief Operating Officer of the Company and a Member of The Institute of Materials, Minerals and Mining.

Forward-Looking Statements

Certain information contained in this news release, including any information relating to the state of the lithium and iodine industries; statements regarding our ability and the timing to achieve and sustain commercial production and name-plate production levels of iodine; ; our ability to secure additional financing; our ability to secure commercial orders from our customers; and our ability to become a material player in the lithium market are "forward-looking statements". These forward-looking statements relate to future events or future performance and reflect the Company's expectations regarding the future growth, results of operations, business prospects and opportunities of RBI. These forward-looking statements also reflect the Company's current internal projections, expectations or beliefs and are based on information currently available to the Company. In some cases forward-looking information can be identified by terminology such as "may", "will", "should", "expect", "intend", "plan", "anticipate", "believe", "estimate", "projects", "potential", "scheduled", "forecast", "budget" or the negative of those terms or other comparable terminology. The estimates and assumptions of RBI underlying the forward-looking statements in this news release may prove to be incorrect. Assumptions upon which such forward looking information include, among other things, successful and timely commissioning, ramp-up and production at the Quebec Lithium Project; the lack of any further significant capital expenditures during the commissioning stage or to bring the hydrometallurgical process plant into production; the continuing support and cooperation of RBI's off-take partners; as well as financial predictions premised on such assumptions. Although the Company believes that the forward-looking information contained in this news release is based on reasonable assumptions, readers cannot be assured that actual results will be consistent with such statements. Accordingly, readers are cautioned against placing undue reliance on forward-looking information. RBI expressly disclaims any intention or obligation to update or revise any forward-looking information, whether as a result of new information, events or otherwise, except in accordance with applicable securities laws.

On behalf of the Board,

Richard P. Clark, President and CEO

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
"We're here to tell the world about our cloud-scale infrastructure that we have at Juniper combined with the world-class security that we put into the cloud," explained Lisa Guess, VP of Systems Engineering at Juniper Networks, in this SYS-CON.tv interview at 20th Cloud Expo, held June 6-8, 2017, at the Javits Center in New York City, NY.
There is a huge demand for responsive, real-time mobile and web experiences, but current architectural patterns do not easily accommodate applications that respond to events in real time. Common solutions using message queues or HTTP long-polling quickly lead to resiliency, scalability and development velocity challenges. In his session at 21st Cloud Expo, Ryland Degnan, a Senior Software Engineer on the Netflix Edge Platform team, will discuss how by leveraging a reactive stream-based protocol,...
"Outscale was founded in 2010, is based in France, is a strategic partner to Dassault Systémes and has done quite a bit of work with divisions of Dassault," explained Jackie Funk, Digital Marketing exec at Outscale, in this SYS-CON.tv interview at 20th Cloud Expo, held June 6-8, 2017, at the Javits Center in New York City, NY.
"With Digital Experience Monitoring what used to be a simple visit to a web page has exploded into app on phones, data from social media feeds, competitive benchmarking - these are all components that are only available because of some type of digital asset," explained Leo Vasiliou, Director of Web Performance Engineering at Catchpoint Systems, in this SYS-CON.tv interview at DevOps Summit at 20th Cloud Expo, held June 6-8, 2017, at the Javits Center in New York City, NY.
"I think DevOps is now a rambunctious teenager – it’s starting to get a mind of its own, wanting to get its own things but it still needs some adult supervision," explained Thomas Hooker, VP of marketing at CollabNet, in this SYS-CON.tv interview at DevOps Summit at 20th Cloud Expo, held June 6-8, 2017, at the Javits Center in New York City, NY.
Your homes and cars can be automated and self-serviced. Why can't your storage? From simply asking questions to analyze and troubleshoot your infrastructure, to provisioning storage with snapshots, recovery and replication, your wildest sci-fi dream has come true. In his session at @DevOpsSummit at 20th Cloud Expo, Dan Florea, Director of Product Management at Tintri, provided a ChatOps demo where you can talk to your storage and manage it from anywhere, through Slack and similar services with...
"We want to show that our solution is far less expensive with a much better total cost of ownership so we announced several key features. One is called geo-distributed erasure coding, another is support for KVM and we introduced a new capability called Multi-Part," explained Tim Desai, Senior Product Marketing Manager at Hitachi Data Systems, in this SYS-CON.tv interview at 20th Cloud Expo, held June 6-8, 2017, at the Javits Center in New York City, NY.
"I'm here to leverage my secret sauce, which is using outsourced development and the company that I utilize is delaPlex Software and they've basically allowed me to win Fortune 500 companies," noted Justin Witz, CTO of FRA and PlanTools, in this SYS-CON.tv interview at 20th Cloud Expo, held June 6-8, 2017, at the Javits Center in New York City, NY.
"We provide IoT solutions. We provide the most compatible solutions for many applications. Our solutions are industry agnostic and also protocol agnostic," explained Richard Han, Head of Sales and Marketing and Engineering at Systena America, in this SYS-CON.tv interview at @ThingsExpo, held June 6-8, 2017, at the Javits Center in New York City, NY.
"As we've gone out into the public cloud we've seen that over time we may have lost a few things - we've lost control, we've given up cost to a certain extent, and then security, flexibility," explained Steve Conner, VP of Sales at Cloudistics,in this SYS-CON.tv interview at 20th Cloud Expo, held June 6-8, 2017, at the Javits Center in New York City, NY.
"We are an IT services solution provider and we sell software to support those solutions. Our focus and key areas are around security, enterprise monitoring, and continuous delivery optimization," noted John Balsavage, President of A&I Solutions, in this SYS-CON.tv interview at 20th Cloud Expo, held June 6-8, 2017, at the Javits Center in New York City, NY.
SYS-CON Events announced today that Calligo, an innovative cloud service provider offering mid-sized companies the highest levels of data privacy and security, has been named "Bronze Sponsor" of SYS-CON's 21st International Cloud Expo ®, which will take place on Oct 31 - Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. Calligo offers unparalleled application performance guarantees, commercial flexibility and a personalised support service from its globally located cloud plat...
As enterprise cloud becomes the norm, businesses and government programs must address compounded regulatory compliance related to data privacy and information protection. The most recent, Controlled Unclassified Information and the EU’s GDPR have board level implications and companies still struggle with demonstrating due diligence. Developers and DevOps leaders, as part of the pre-planning process and the associated supply chain, could benefit from updating their code libraries and design by in...
"Peak 10 is a hybrid infrastructure provider across the nation. We are in the thick of things when it comes to hybrid IT," explained Michael Fuhrman, Chief Technology Officer at Peak 10, in this SYS-CON.tv interview at 20th Cloud Expo, held June 6-8, 2017, at the Javits Center in New York City, NY.
"We were founded in 2003 and the way we were founded was about good backup and good disaster recovery for our clients, and for the last 20 years we've been pretty consistent with that," noted Marc Malafronte, Territory Manager at StorageCraft, in this SYS-CON.tv interview at 20th Cloud Expo, held June 6-8, 2017, at the Javits Center in New York City, NY.