RB Energy Reports Q2 2014 Results

VANCOUVER, BRITISH COLUMBIA -- (Marketwired) -- 08/14/14 -- RB Energy Inc. (the "Company" or "RBI" or RB Energy") (TSX: RBI)(OTCQX: RBEIF) is pleased to report financial and operating results for the three and six months ended June 30, 2014. The consolidated financial statements together with Management's Discussion and Analysis will be available on the Company's web site (www.rb-e.com) and on SEDAR (www.sedar.com).

SECOND QUARTER HIGHLIGHTS

Quebec Lithium

With the onset of warmer temperatures in the second quarter, the crushing, grinding and concentrator circuits were re-started with the objective of achieving continuous battery grade(1 ) lithium carbonate production from run of mine operations. Production of limited quantities of EV grade(1) lithium carbonate were achieved, however, ramp up issues encountered with the kiln and bi-carbonate reactors delayed production of commercial volumes.

The primary optical ore sorter was delivered to site in late Q2 2014. Installation and commissioning of the ore sorter commenced in July and will be completed in August. The diversion of a road running through the open pit to will allow full access to the open pit commenced in Q2 2014. The diversion is scheduled to be completed by the end of Q3 2014. The construction of a natural gas pipeline to the mine site commenced in Q2 2014 and is on schedule for completion in Q4 2014.

As a result of the commissioning delays, it is now anticipated that commercial production levels of battery grade lithium will be achieved by the end of 2014. Production of EV grade lithium carbonate is targeted for early 2015. The ramp-up to the annual design capacity of 20,000 tonnes is now expected to be achieved in Q1 2015.

The aforementioned delays in the ramp up of production have deferred the anticipated production and sale of commercial quantities of lithium carbonate, thereby accelerating the depletion of the Company's treasury to a greater extent than anticipated. As a result, the Company is working to secure additional sources of funding to complete commissioning, achieve commercial production and realize positive operating cash flow at Quebec Lithium.

Aguas Blancas

For the three months ended June 30, 2014, Aguas Blancas produced 314 tonnes of iodine at a cash cost of US $22 per kg and sold 518 tonnes at an average price of US $36 per kg during Q2 2014. High sales volumes in Q2 2014 offset the low volumes of sales in Q1 2014, which were due principally to disrupted shipments from Chile as a result of earthquakes and a port strike.

(1) Quebec Lithium specifications (lithium carbonate content)


--------------------------------------------------
Technical grade                    99.0%
--------------------------------------------------
Battery grade                      99.7%
--------------------------------------------------
Electric Vehicle (EV) grade        99.9%
--------------------------------------------------

RESULTS FROM OPERATIONS

Quebec Lithium is in the commissioning stage and had not yet generated sales and revenues at the end of Q2 2014. Revenues only included the Aguas Blancas operations of since February 2014 (2013: none) and reflected sales of iodine inventory acquired at its fair value on January 31, 2014 and iodine produced since the Arrangement.

During the three and six months ended June 30, 2014, the Company earned a net profit of $1.3 million ($0.01 earnings per share) and incurred a net loss of $6.2 million ($0.03 loss per share), respectively, compared with net losses of $1.3 million ($0.01 loss per share) and $3.9 million ($0.03 loss per share), respectively, for the same periods in 2013. Included in the Q2 2014 profit is an unrealized foreign exchange gain of $1.5 million due principally to the positive impact of the strengthening of the Canadian dollar against the US dollar on the carrying values of the US dollar denominated convertible debentures, finance lease liabilities, and cash advances from a customer since the end of Q1 2014. More than half of the loss for the six months ended June 30, 2014 ($3.3 million) is due to the one-time transaction costs associated with the Arrangement.

RB Energy incurred general and administrative expenses of $1.8 million (2013: $2.0 million) and $3.6 million (2013: $4.3 million) for the three and six months ended June 30, 2014, respectively, which include costs to maintain offices and staff in Toronto and Montreal to the end of April.


----------------------------------------------------------------------------
                               Three months ended       Six months ended
(Canadian dollars)             June-14     Jun-13     June-14      Jun-13
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Total revenues ($000's)
 (Note 1)                         20,145          -      25,189           -
----------------------------------------------------------------------------
Net income (loss) ($000's)         1,307     (1,330)     (6,167)     (3,885)
----------------------------------------------------------------------------
Income (loss) per share,
 basic and diluted ($)              0.01      (0.01)      (0.03)      (0.03)
----------------------------------------------------------------------------
Total assets ($000's) (Note
 2)                              484,265    344,076
----------------------------------------------------
Total liabilities ($000's)
 (Note 2)                        205,215    163,337
----------------------------------------------------

----------------------------------------------------------------------------
Iodine produced (t) (Note 1)         314          -         525           -
----------------------------------------------------------------------------
Iodine sold (t) (Note 1)             518          -         644           -
----------------------------------------------------------------------------
Iodine avg. price ($/kg)
 (Note 1)                             39          -          39           -
----------------------------------------------------------------------------
Iodine cash operating cost
 ($/kg) (Note 1, 3)                   24          -          26           -
----------------------------------------------------------------------------

Note 1: revenues and iodine data are from February 1 to June 30, 2014, the period post acquisition of Sirocco.

Note 2: comparative data provided as at December 31, 2013.

Note 3: this is a non-GAAP measure. It was calculated by dividing cost of sales, adjusted for the change in inventory and the related depreciation, by quantities of iodine produced in the period.

Note 4: for complete details, refer to the June 30, 2014 interim consolidated financial statements and MD&A.

The increase in total assets and liabilities from December 31, 2013 is due to the acquisition of Sirocco and the consolidation of its net assets as well as the ongoing construction and commissioning of the lithium processing plant in Quebec. Capitalized items include borrowing and operating costs for Quebec Lithium during the period.

OUTLOOK

Quebec Lithium

The operating focus is to ramp up commercial production volumes, achieve commercial production before the end of 2014 and name plate production by the end of Q1 2015. Shipments of lithium carbonate to the Company's main off take partner commenced in August. Modifications to the processing plant to produce EV grade lithium carbonate are scheduled for Q4 2014.

The timetable to Q1 2015 includes four main operating objectives:


1.  achieve continuous shipments of lithium carbonate in Q3 2014;
2.  complete the commissioning of the primary optical ore sorter (to reduce
    ore dilution) thereby increasing concentrate grade in Q3;
3.  reach commercial production levels of lithium carbonate by the end of
    2014 and name plate production by the end of Q1 2015; and
4.  produce EV grade lithium carbonate before the end of Q1 2014 as a result
    of modifications to the processing plant.

Aguas Blancas

Production at Aguas Blancas was reduced in late 2013 by placing the Agitated Leach Plant ("ALP") on care and maintenance in response to further softening prices in the market. As a result, operations in 2014 are limited to heap leaching. In 2014, production of iodine is estimated at approximately 1,000 tonnes at a cash cost of approximately US $26/kg. Aguas Blancas expects to supplement the sales of its 2014 production by reducing the level of finished product inventory on hand. Subsequent to Q2 2014, the Company has committed to the delivery of approximately 190 tonnes of iodine over the next twelve months to generate additional cash flows in support of commissioning at Quebec Lithium.

About RB Energy Inc.

RBI is a Canadian company formed pursuant to the arrangement involving Sirocco Mining Inc. and Canada Lithium Corp. It currently owns Aguas Blancas, an iodine producing mine in northern Chile, and Quebec Lithium near Val d'Or, the geographical heart of the Quebec mining industry. The Aguas Blancas mine is currently in production. The Quebec Lithium has completed construction and is in the commissioning phase. For more information regarding RBI, please refer to its public filings available at www.sedar.com.

The technical contents of this release have been reviewed by Mr. Kevin Ross, Eur. Ing., a Qualified Person pursuant to NI-43-101. Mr. Ross is Chief Operating Officer of the Company and a Member of The Institute of Materials, Minerals and Mining.

Forward-Looking Statements

Certain information contained in this news release, including any information relating to the state of the lithium and iodine industries; statements regarding our ability and the timing to achieve and sustain commercial production and name-plate production levels of iodine; ; our ability to secure additional financing; our ability to secure commercial orders from our customers; and our ability to become a material player in the lithium market are "forward-looking statements". These forward-looking statements relate to future events or future performance and reflect the Company's expectations regarding the future growth, results of operations, business prospects and opportunities of RBI. These forward-looking statements also reflect the Company's current internal projections, expectations or beliefs and are based on information currently available to the Company. In some cases forward-looking information can be identified by terminology such as "may", "will", "should", "expect", "intend", "plan", "anticipate", "believe", "estimate", "projects", "potential", "scheduled", "forecast", "budget" or the negative of those terms or other comparable terminology. The estimates and assumptions of RBI underlying the forward-looking statements in this news release may prove to be incorrect. Assumptions upon which such forward looking information include, among other things, successful and timely commissioning, ramp-up and production at the Quebec Lithium Project; the lack of any further significant capital expenditures during the commissioning stage or to bring the hydrometallurgical process plant into production; the continuing support and cooperation of RBI's off-take partners; as well as financial predictions premised on such assumptions. Although the Company believes that the forward-looking information contained in this news release is based on reasonable assumptions, readers cannot be assured that actual results will be consistent with such statements. Accordingly, readers are cautioned against placing undue reliance on forward-looking information. RBI expressly disclaims any intention or obligation to update or revise any forward-looking information, whether as a result of new information, events or otherwise, except in accordance with applicable securities laws.

On behalf of the Board,

Richard P. Clark, President and CEO

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
Building a cross-cloud operational model can be a daunting task. Per-cloud silos are not the answer, but neither is a fully generic abstraction plane that strips out capabilities unique to a particular provider. In his session at 20th Cloud Expo, Chris Wolf, VP & Chief Technology Officer, Global Field & Industry at VMware, will discuss how successful organizations approach cloud operations and management, with insights into where operations should be centralized and when it’s best to decentraliz...
The 20th International Cloud Expo has announced that its Call for Papers is open. Cloud Expo, to be held June 6-8, 2017, at the Javits Center in New York City, brings together Cloud Computing, Big Data, Internet of Things, DevOps, Containers, Microservices and WebRTC to one location. With cloud computing driving a higher percentage of enterprise IT budgets every year, it becomes increasingly important to plant your flag in this fast-expanding business opportunity. Submit your speaking proposal ...
“DevOps is really about the business. The business is under pressure today, competitively in the marketplace to respond to the expectations of the customer. The business is driving IT and the problem is that IT isn't responding fast enough," explained Mark Levy, Senior Product Marketing Manager at Serena Software, in this SYS-CON.tv interview at DevOps Summit, held Nov 4–6, 2014, at the Santa Clara Convention Center in Santa Clara, CA.
@DevOpsSummit at Cloud taking place June 6-8, 2017, at Javits Center, New York City, is co-located with the 20th International Cloud Expo and will feature technical sessions from a rock star conference faculty and the leading industry players in the world. The widespread success of cloud computing is driving the DevOps revolution in enterprise IT. Now as never before, development teams must communicate and collaborate in a dynamic, 24/7/365 environment. There is no time to wait for long developm...
Grape Up is a software company, specialized in cloud native application development and professional services related to Cloud Foundry PaaS. With five expert teams that operate in various sectors of the market across the USA and Europe, we work with a variety of customers from emerging startups to Fortune 1000 companies.
Financial Technology has become a topic of intense interest throughout the cloud developer and enterprise IT communities. Accordingly, attendees at the upcoming 20th Cloud Expo at the Javits Center in New York, June 6-8, 2017, will find fresh new content in a new track called FinTech.
@GonzalezCarmen has been ranked the Number One Influencer and @ThingsExpo has been named the Number One Brand in the “M2M 2016: Top 100 Influencers and Brands” by Analytic. Onalytica analyzed tweets over the last 6 months mentioning the keywords M2M OR “Machine to Machine.” They then identified the top 100 most influential brands and individuals leading the discussion on Twitter.
Cloud Expo, Inc. has announced today that Aruna Ravichandran, vice president of DevOps Product and Solutions Marketing at CA Technologies, has been named co-conference chair of DevOps at Cloud Expo 2017. The @DevOpsSummit at Cloud Expo New York will take place on June 6-8, 2017, at the Javits Center in New York City, New York, and @DevOpsSummit at Cloud Expo Silicon Valley will take place Oct. 31-Nov. 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA.
Cognitive Computing is becoming the foundation for a new generation of solutions that have the potential to transform business. Unlike traditional approaches to building solutions, a cognitive computing approach allows the data to help determine the way applications are designed. This contrasts with conventional software development that begins with defining logic based on the current way a business operates. In her session at 18th Cloud Expo, Judith S. Hurwitz, President and CEO of Hurwitz & ...
In his keynote at @ThingsExpo, Chris Matthieu, Director of IoT Engineering at Citrix and co-founder and CTO of Octoblu, focused on building an IoT platform and company. He provided a behind-the-scenes look at Octoblu’s platform, business, and pivots along the way (including the Citrix acquisition of Octoblu).
SYS-CON Events announced today that Interoute, owner-operator of one of Europe's largest networks and a global cloud services platform, has been named “Bronze Sponsor” of SYS-CON's 20th Cloud Expo, which will take place on June 6-8, 2017 at the Javits Center in New York, New York. Interoute is the owner-operator of one of Europe's largest networks and a global cloud services platform which encompasses 12 data centers, 14 virtual data centers and 31 colocation centers, with connections to 195 add...
With billions of sensors deployed worldwide, the amount of machine-generated data will soon exceed what our networks can handle. But consumers and businesses will expect seamless experiences and real-time responsiveness. What does this mean for IoT devices and the infrastructure that supports them? More of the data will need to be handled at - or closer to - the devices themselves.
Translating agile methodology into real-world best practices within the modern software factory has driven widespread DevOps adoption, yet much work remains to expand workflows and tooling across the enterprise. As models evolve from pockets of experimentation into wholescale organizational reinvention, practitioners find themselves challenged to incorporate the culture and architecture necessary to support DevOps at scale. In his session at @DevOpsSummit at 20th Cloud Expo, Anand Akela, Senior...
Join IBM November 2 at 19th Cloud Expo at the Santa Clara Convention Center in Santa Clara, CA, and learn how to go beyond multi-speed it to bring agility to traditional enterprise applications. Technology innovation is the driving force behind modern business and enterprises must respond by increasing the speed and efficiency of software delivery. The challenge is that existing enterprise applications are expensive to develop and difficult to modernize. This often results in what Gartner calls ...
Today we can collect lots and lots of performance data. We build beautiful dashboards and even have fancy query languages to access and transform the data. Still performance data is a secret language only a couple of people understand. The more business becomes digital the more stakeholders are interested in this data including how it relates to business. Some of these people have never used a monitoring tool before. They have a question on their mind like “How is my application doing” but no id...