RB Energy Reports Q2 2014 Results

VANCOUVER, BRITISH COLUMBIA -- (Marketwired) -- 08/14/14 -- RB Energy Inc. (the "Company" or "RBI" or RB Energy") (TSX: RBI)(OTCQX: RBEIF) is pleased to report financial and operating results for the three and six months ended June 30, 2014. The consolidated financial statements together with Management's Discussion and Analysis will be available on the Company's web site (www.rb-e.com) and on SEDAR (www.sedar.com).

SECOND QUARTER HIGHLIGHTS

Quebec Lithium

With the onset of warmer temperatures in the second quarter, the crushing, grinding and concentrator circuits were re-started with the objective of achieving continuous battery grade(1 ) lithium carbonate production from run of mine operations. Production of limited quantities of EV grade(1) lithium carbonate were achieved, however, ramp up issues encountered with the kiln and bi-carbonate reactors delayed production of commercial volumes.

The primary optical ore sorter was delivered to site in late Q2 2014. Installation and commissioning of the ore sorter commenced in July and will be completed in August. The diversion of a road running through the open pit to will allow full access to the open pit commenced in Q2 2014. The diversion is scheduled to be completed by the end of Q3 2014. The construction of a natural gas pipeline to the mine site commenced in Q2 2014 and is on schedule for completion in Q4 2014.

As a result of the commissioning delays, it is now anticipated that commercial production levels of battery grade lithium will be achieved by the end of 2014. Production of EV grade lithium carbonate is targeted for early 2015. The ramp-up to the annual design capacity of 20,000 tonnes is now expected to be achieved in Q1 2015.

The aforementioned delays in the ramp up of production have deferred the anticipated production and sale of commercial quantities of lithium carbonate, thereby accelerating the depletion of the Company's treasury to a greater extent than anticipated. As a result, the Company is working to secure additional sources of funding to complete commissioning, achieve commercial production and realize positive operating cash flow at Quebec Lithium.

Aguas Blancas

For the three months ended June 30, 2014, Aguas Blancas produced 314 tonnes of iodine at a cash cost of US $22 per kg and sold 518 tonnes at an average price of US $36 per kg during Q2 2014. High sales volumes in Q2 2014 offset the low volumes of sales in Q1 2014, which were due principally to disrupted shipments from Chile as a result of earthquakes and a port strike.

(1) Quebec Lithium specifications (lithium carbonate content)


--------------------------------------------------
Technical grade                    99.0%
--------------------------------------------------
Battery grade                      99.7%
--------------------------------------------------
Electric Vehicle (EV) grade        99.9%
--------------------------------------------------

RESULTS FROM OPERATIONS

Quebec Lithium is in the commissioning stage and had not yet generated sales and revenues at the end of Q2 2014. Revenues only included the Aguas Blancas operations of since February 2014 (2013: none) and reflected sales of iodine inventory acquired at its fair value on January 31, 2014 and iodine produced since the Arrangement.

During the three and six months ended June 30, 2014, the Company earned a net profit of $1.3 million ($0.01 earnings per share) and incurred a net loss of $6.2 million ($0.03 loss per share), respectively, compared with net losses of $1.3 million ($0.01 loss per share) and $3.9 million ($0.03 loss per share), respectively, for the same periods in 2013. Included in the Q2 2014 profit is an unrealized foreign exchange gain of $1.5 million due principally to the positive impact of the strengthening of the Canadian dollar against the US dollar on the carrying values of the US dollar denominated convertible debentures, finance lease liabilities, and cash advances from a customer since the end of Q1 2014. More than half of the loss for the six months ended June 30, 2014 ($3.3 million) is due to the one-time transaction costs associated with the Arrangement.

RB Energy incurred general and administrative expenses of $1.8 million (2013: $2.0 million) and $3.6 million (2013: $4.3 million) for the three and six months ended June 30, 2014, respectively, which include costs to maintain offices and staff in Toronto and Montreal to the end of April.


----------------------------------------------------------------------------
                               Three months ended       Six months ended
(Canadian dollars)             June-14     Jun-13     June-14      Jun-13
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Total revenues ($000's)
 (Note 1)                         20,145          -      25,189           -
----------------------------------------------------------------------------
Net income (loss) ($000's)         1,307     (1,330)     (6,167)     (3,885)
----------------------------------------------------------------------------
Income (loss) per share,
 basic and diluted ($)              0.01      (0.01)      (0.03)      (0.03)
----------------------------------------------------------------------------
Total assets ($000's) (Note
 2)                              484,265    344,076
----------------------------------------------------
Total liabilities ($000's)
 (Note 2)                        205,215    163,337
----------------------------------------------------

----------------------------------------------------------------------------
Iodine produced (t) (Note 1)         314          -         525           -
----------------------------------------------------------------------------
Iodine sold (t) (Note 1)             518          -         644           -
----------------------------------------------------------------------------
Iodine avg. price ($/kg)
 (Note 1)                             39          -          39           -
----------------------------------------------------------------------------
Iodine cash operating cost
 ($/kg) (Note 1, 3)                   24          -          26           -
----------------------------------------------------------------------------

Note 1: revenues and iodine data are from February 1 to June 30, 2014, the period post acquisition of Sirocco.

Note 2: comparative data provided as at December 31, 2013.

Note 3: this is a non-GAAP measure. It was calculated by dividing cost of sales, adjusted for the change in inventory and the related depreciation, by quantities of iodine produced in the period.

Note 4: for complete details, refer to the June 30, 2014 interim consolidated financial statements and MD&A.

The increase in total assets and liabilities from December 31, 2013 is due to the acquisition of Sirocco and the consolidation of its net assets as well as the ongoing construction and commissioning of the lithium processing plant in Quebec. Capitalized items include borrowing and operating costs for Quebec Lithium during the period.

OUTLOOK

Quebec Lithium

The operating focus is to ramp up commercial production volumes, achieve commercial production before the end of 2014 and name plate production by the end of Q1 2015. Shipments of lithium carbonate to the Company's main off take partner commenced in August. Modifications to the processing plant to produce EV grade lithium carbonate are scheduled for Q4 2014.

The timetable to Q1 2015 includes four main operating objectives:


1.  achieve continuous shipments of lithium carbonate in Q3 2014;
2.  complete the commissioning of the primary optical ore sorter (to reduce
    ore dilution) thereby increasing concentrate grade in Q3;
3.  reach commercial production levels of lithium carbonate by the end of
    2014 and name plate production by the end of Q1 2015; and
4.  produce EV grade lithium carbonate before the end of Q1 2014 as a result
    of modifications to the processing plant.

Aguas Blancas

Production at Aguas Blancas was reduced in late 2013 by placing the Agitated Leach Plant ("ALP") on care and maintenance in response to further softening prices in the market. As a result, operations in 2014 are limited to heap leaching. In 2014, production of iodine is estimated at approximately 1,000 tonnes at a cash cost of approximately US $26/kg. Aguas Blancas expects to supplement the sales of its 2014 production by reducing the level of finished product inventory on hand. Subsequent to Q2 2014, the Company has committed to the delivery of approximately 190 tonnes of iodine over the next twelve months to generate additional cash flows in support of commissioning at Quebec Lithium.

About RB Energy Inc.

RBI is a Canadian company formed pursuant to the arrangement involving Sirocco Mining Inc. and Canada Lithium Corp. It currently owns Aguas Blancas, an iodine producing mine in northern Chile, and Quebec Lithium near Val d'Or, the geographical heart of the Quebec mining industry. The Aguas Blancas mine is currently in production. The Quebec Lithium has completed construction and is in the commissioning phase. For more information regarding RBI, please refer to its public filings available at www.sedar.com.

The technical contents of this release have been reviewed by Mr. Kevin Ross, Eur. Ing., a Qualified Person pursuant to NI-43-101. Mr. Ross is Chief Operating Officer of the Company and a Member of The Institute of Materials, Minerals and Mining.

Forward-Looking Statements

Certain information contained in this news release, including any information relating to the state of the lithium and iodine industries; statements regarding our ability and the timing to achieve and sustain commercial production and name-plate production levels of iodine; ; our ability to secure additional financing; our ability to secure commercial orders from our customers; and our ability to become a material player in the lithium market are "forward-looking statements". These forward-looking statements relate to future events or future performance and reflect the Company's expectations regarding the future growth, results of operations, business prospects and opportunities of RBI. These forward-looking statements also reflect the Company's current internal projections, expectations or beliefs and are based on information currently available to the Company. In some cases forward-looking information can be identified by terminology such as "may", "will", "should", "expect", "intend", "plan", "anticipate", "believe", "estimate", "projects", "potential", "scheduled", "forecast", "budget" or the negative of those terms or other comparable terminology. The estimates and assumptions of RBI underlying the forward-looking statements in this news release may prove to be incorrect. Assumptions upon which such forward looking information include, among other things, successful and timely commissioning, ramp-up and production at the Quebec Lithium Project; the lack of any further significant capital expenditures during the commissioning stage or to bring the hydrometallurgical process plant into production; the continuing support and cooperation of RBI's off-take partners; as well as financial predictions premised on such assumptions. Although the Company believes that the forward-looking information contained in this news release is based on reasonable assumptions, readers cannot be assured that actual results will be consistent with such statements. Accordingly, readers are cautioned against placing undue reliance on forward-looking information. RBI expressly disclaims any intention or obligation to update or revise any forward-looking information, whether as a result of new information, events or otherwise, except in accordance with applicable securities laws.

On behalf of the Board,

Richard P. Clark, President and CEO

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
In their session at 17th Cloud Expo, Hal Schwartz, CEO of Secure Infrastructure & Services (SIAS), and Chuck Paolillo, CTO of Secure Infrastructure & Services (SIAS), provide a study of cloud adoption trends and the power and flexibility of IBM Power and Pureflex cloud solutions. In his role as CEO of Secure Infrastructure & Services (SIAS), Hal Schwartz provides leadership and direction for the company.
There are many considerations when moving applications from on-premise to cloud. It is critical to understand the benefits and also challenges of this migration. A successful migration will result in lower Total Cost of Ownership, yet offer the same or higher level of robustness. In his session at 15th Cloud Expo, Michael Meiner, an Engineering Director at Oracle, Corporation, analyzed a range of cloud offerings (IaaS, PaaS, SaaS) and discussed the benefits/challenges of migrating to each offe...
SYS-CON Events announced today that the "Second Containers & Microservices Expo" will take place November 3-5, 2015, at the Santa Clara Convention Center in Santa Clara, CA. Containers and microservices have become topics of intense interest throughout the cloud developer and enterprise IT communities.
As organizations shift towards IT-as-a-service models, the need for managing and protecting data residing across physical, virtual, and now cloud environments grows with it. CommVault can ensure protection and E-Discovery of your data – whether in a private cloud, a Service Provider delivered public cloud, or a hybrid cloud environment – across the heterogeneous enterprise. In his session at 17th Cloud Expo, Randy De Meno, Chief Technologist - Windows Products and Microsoft Partnerships at Com...
The Software Defined Data Center (SDDC), which enables organizations to seamlessly run in a hybrid cloud model (public + private cloud), is here to stay. IDC estimates that the software-defined networking market will be valued at $3.7 billion by 2016. Security is a key component and benefit of the SDDC, and offers an opportunity to build security 'from the ground up' and weave it into the environment from day one. In his session at 16th Cloud Expo, Reuven Harrison, CTO and Co-Founder of Tufin,...
Scrum Alliance has announced the release of its 2015 State of Scrum Report. Almost 5,000 individuals and companies worldwide participated in this year's survey. Most organizations in the market today are still leading and managing under an Industrial Age model. Not only is the speed of change growing exponentially, Agile and Scrum frameworks are showing companies how to draw on the full talents and capabilities of those doing the work in order to continue innovating for success.
SYS-CON Events announced today that MobiDev, a software development company, will exhibit at the 17th International Cloud Expo®, which will take place November 3–5, 2015, at the Santa Clara Convention Center in Santa Clara, CA. MobiDev is a software development company with representative offices in Atlanta (US), Sheffield (UK) and Würzburg (Germany); and development centers in Ukraine. Since 2009 it has grown from a small group of passionate engineers and business managers to a full-scale mobi...
Between the compelling mockups and specs produced by your analysts and designers, and the resulting application built by your developers, there is a gulf where projects fail, costs spiral out of control, and applications fall short of requirements. In his session at @DevOpsSummit, Charles Kendrick, CTO and Chief Architect at Isomorphic Software, presented a new approach where business and development users collaborate – each using tools appropriate to their goals and expertise – to build mocku...
Container technology is sending shock waves through the world of cloud computing. Heralded as the 'next big thing,' containers provide software owners a consistent way to package their software and dependencies while infrastructure operators benefit from a standard way to deploy and run them. Containers present new challenges for tracking usage due to their dynamic nature. They can also be deployed to bare metal, virtual machines and various cloud platforms. How do software owners track the usag...
SYS-CON Events announced today that VividCortex, the monitoring solution for the modern data system, will exhibit at the 17th International Cloud Expo®, which will take place on November 3–5, 2015, at the Santa Clara Convention Center in Santa Clara, CA. The database is the heart of most applications, but it’s also the part that’s hardest to scale, monitor, and optimize even as it’s growing 50% year over year. VividCortex is the first unified suite of database monitoring tools specifically desi...
Graylog, Inc., has added the capability to collect, centralize and analyze application container logs from within Docker. The Graylog logging driver for Docker addresses the challenges of extracting intelligence from within Docker containers, where most workloads are dynamic and log data is not persisted or stored. Using Graylog, DevOps and IT Ops teams can pinpoint the root cause of problems to deliver new applications faster and minimize downtime.
As Marc Andreessen says software is eating the world. Everything is rapidly moving toward being software-defined – from our phones and cars through our washing machines to the datacenter. However, there are larger challenges when implementing software defined on a larger scale - when building software defined infrastructure. In his session at 16th Cloud Expo, Boyan Ivanov, CEO of StorPool, provided some practical insights on what, how and why when implementing "software-defined" in the datacent...
Learn how you can use the CoSN SEND II Decision Tree for Education Technology to make sure that your K–12 technology initiatives create a more engaging learning experience that empowers students, teachers, and administrators alike.
Mobile, social, Big Data, and cloud have fundamentally changed the way we live. “Anytime, anywhere” access to data and information is no longer a luxury; it’s a requirement, in both our personal and professional lives. For IT organizations, this means pressure has never been greater to deliver meaningful services to the business and customers.
In a recent research, analyst firm IDC found that the average cost of a critical application failure is $500,000 to $1 million per hour and the average total cost of unplanned application downtime is $1.25 billion to $2.5 billion per year for Fortune 1000 companies. In addition to the findings on the cost of the downtime, the research also highlighted best practices for development, testing, application support, infrastructure, and operations teams.