IAMGOLD Provides an Exploration Update on the Monster Lake Project - Beginning 5,000-Metre Second Phase of Diamond Drilling

TSX: IMG NYSE: IAG

TORONTO, Aug. 20, 2014 /CNW/ - IAMGOLD Corporation ("IAMGOLD" or the "Company") today provided an update from its ongoing exploration program at its newly optioned Monster Lake project located 50 kilometres southwest of Chibougamau, Quebec, Canada.

IAMGOLD initiated the current exploration program on the project at the end of 2013 pursuant to an Earn-In Agreement finalized with TomaGold Corporation, in which IAMGOLD may earn a 50% interest in each of the Monster Lake, Winchester and Lac à l'eau jaune properties, collectively referred to as the Monster Lake Project. To earn its interest IAMGOLD must complete scheduled cash payments and exploration expenditures totaling US$17.6 million over five years.

As previously reported in a news release dated May 27, 2014, the Company had completed a phase one diamond drilling program totaling 4,528 metres (nine holes) targeting mainly the direct down-dip and lateral extensions of the 325-Megane mineralized zone previously drilled by TomaGold. All assay results have now been received and validated for the entire phase one drilling program and are provided in Table I below.  A drill hole plan map and longitudinal section are attached to this news release.

Highlights from the last four holes of the phase one program include:

  • 2.12 metres grading 2.30 g/t Au from 422.50 metres depth and 5.86 metres grading 2.62 g/t Au from 426.10 metres depth (including 2.21 metres grading 6.21 g/t Au from 426.94 metres) in hole ML-14-115 (325-Megane Zone),
  • 3.15 metres grading 2.42 g/t Au from 278.07 metres depth in hole ML-14-116 (325-Megane Zone)

The phase one program has provided encouraging results as it expanded the 325-Megane Zone and identified two additional mineralized zones: the Upper 325-Megane Zone, a newly intersected zone, and the Lower 325-Megane Zone which was tested only in a few areas by previous drilling. The three zones appear sub-parallel and are spaced approximately 100 to 400 metres apart. Initial results reported last May also included: 10.47 metres grading 11.55 g/t Au from 457.0 metres depth (including 48.90 g/t Au over 2.0 metres) in hole ML-14-108 (325-Megane Zone), and an intersection of a footwall zone referred to as the Lower 325-Megane Zone and grading 13.65 g/t Au over 3.77 metres from 636.86m depth, including 46.0 g/t Au over 1.08 metres in hole ML-14-110. The newly discovered Upper 325-Megane Zone is systematically anomalous in gold where intersected to date.

A summer field program comprised of geologic mapping, aided by a shallow penetrating electromagnetic survey (Beep Mat of GDD Instrumentation Inc.) to detect potentially sub-cropping conductive shear zones, is currently in progress to help delineate structural trends and confirm priority targets in the central core of the Monster Lake property and in the regional extension of the deformation corridor on the Lac à l'eau jaune and Winchester properties.  Detailed structural and lithological mapping on well exposed historic gold occurrences will be used to assist the final targeting for the next drill program currently being finalized.

Craig MacDougall, Senior Vice President, Exploration for IAMGOLD, stated, "Our involvement in the Monster Lake Project was based on the potential to delineate high grade mineralization in a prospective area possibly hosting several gold zones. These first drill results on the 325-Megane Zone are positive and confirmed the presence of several mineralized structures as well as high grades. The ongoing exploration program is progressing well and we look forward to next round of drilling once the targets are finalized.."

The Monster Lake project is underlain by Archean volcanic rocks of the Obatogamau Formation and is traversed by an important deformation corridor and gold-bearing mineralized structures. Historical drilling and recent success by TomaGold have identified at least a four-kilometre long mineralized structure hosting most of the gold surface showings and diamond drilling intersections, including the 325-Megane Zone.

Next Steps
The summer field program continues and is expected to include a limited outcrop stripping and trenching program to expose key areas identified from the ongoing mapping and geophysical surveys. A property scale glacial till sampling survey and some specific ground geophysical surveys are also in progress over selected areas. A second phase of diamond drilling totaling approximately 5,000 metres is scheduled by the end of October 2014 to test selected target areas along the main mineralized corridor and the down plunge of the 325-Megane zone. The first diamond drill rig mobilizes today and the second rig by the end of the week.

Technical Information and Quality Control Notes
The drilling results contained in this news release have been prepared in accordance with National Instrument 43-101 Standards of Disclosure for Mineral Projects ("NI 43-101").

The "Qualified Person" responsible for the supervision of the preparation and review of this information is Marie-France Bugnon, P. Geo., General Manager Exploration. Marie-France is considered a "Qualified Person" for the purposes of National Instrument 43-101 with respect to the technical information being reported on. The technical information has been included herein with the consent and prior review of the above noted Qualified Person. The Qualified person has verified the data disclosed, and data underlying the information or opinions contained herein.

The sampling of, and assay data from, drill core is monitored through the implementation of a quality assurance - quality control (QA-QC)  program designed to follow industry best practice. Drill core (NQ size) samples are selected by the IAMGOLD geologists and sawn in half with a diamond saw at the project site. Half of the core is retained at the site for reference purposes. Sample intervals may vary from half a metre to one and a half metres in length depending on the geological observations.

Samples are transported in sealed bags to the AGAT Laboratory prep lab facility in Val-d'Or, Québec.  Samples are coarse crushed to a -10 mesh and then a 1000 gram split is pulverized to 95% passing -150 mesh.  Analytical pulps are forwarded for analysis at the AGAT Laboratories  (ISO / IEC 17025 Certified by the Standards Council of Canada) in Mississauga, Ontario. Samples are analyzed using a standard fire assay with a 50 gram charge with an Atomic Absorption (AA) finish. For samples that return assay values over 5.0 grams per tonne (g/t), another pulp is taken and fire assayed with a gravimetric finish. Core samples showing visible gold or samples which have returned values greater than 10.0 g/t are re-analyzed by pulp metallic analysis. IAMGOLD inserts blanks and certified reference standard in the sample sequence for quality control.

CAUTIONARY STATEMENT ON FORWARD-LOOKING INFORMATION
All information included in this news release, including any information as to the Company's future financial or operating performance, and other statements that express management's expectations or estimates of future performance, other than statements of historical fact, constitute forward looking information or forward-looking statements and are based on expectations, estimates and projections as of the date of this news release. Forward-looking statements contained in this news release include, but are not limited to, statements with respect to: the Company's guidance for production, exploration, rock hardness, grade, strip ratios, the future price of gold, the estimation of mineral reserves and mineral resources, the realization of mineral reserve and mineral resource estimates, the timing and amount of estimated future production, costs of production,  permitting timelines, requirements for additional capital, government regulation of mining operations, environmental risks, unanticipated reclamation expenses and title disputes or claims.  Forward-looking statements are provided for the purpose of providing information about management's current expectations and plans relating to the future. Forward-looking statements are generally identifiable by, but are not limited to the, use of the words "may", "will", "should", "could", "intends", "potential", "continue", "expect" or "anticipate" or the negative of these words or other variations on these words or comparable terminology. Forward-looking statements are necessarily based upon a number of estimates and assumptions that, while considered reasonable by management, are inherently subject to significant business, economic and competitive uncertainties and contingencies. The Company cautions the reader not to place any reliance whatsoever on forward-looking information or forward-looking statements. Forward- looking information and  forward-looking statements involve risks, uncertainties and other factors that may cause the actual financial results, performance or achievements of IAMGOLD to be materially different from the Company's estimated future results, performance or achievements expressed or implied by those forward-looking statements, and the forward-looking statements are not guarantees of future performance. Risks and unknowns inherent in all projects include the inaccuracy of estimated reserves and resources, metallurgical recoveries, capital and operating costs of such projects, and the future prices for the relevant minerals. The capital expenditures and time required to develop new mines or other projects are considerable, and changes in costs or construction schedules can affect project economics. Actual costs and economic returns may differ materially from IAMGOLD's estimates or IAMGOLD could fail to obtain the governmental approvals necessary for the operation of a project; in either case, the project may not proceed, either on its original timing or at all.

The Company disclaims any intention or obligation to update or revise any forward-looking statements whether as a result of new information, future events or otherwise except as required by applicable law.

About IAMGOLD

IAMGOLD (www.iamgold.com) is a mid-tier mining company with five operating gold mines (including current joint ventures) on three continents and one of the world's top three niobium mines. A solid base of strategic assets in Canada, South America and Africa is complemented by development and exploration projects and continued assessment of accretive acquisition opportunities.  IAMGOLD is in a strong financial position with extensive management and operational expertise. 

Please note:

This entire news release may be accessed via fax, e-mail, IAMGOLD's website at www.iamgold.com and through CNW Group's website at www.newswire.ca.  All material information on IAMGOLD can be found at www.sedar.com or at www.sec.gov.

Si vous désirez obtenir la version française de ce communiqué, veuillez consulter le http://www.iamgold.com/French/Home/default.aspx.

Table 1

Monster Lake Project Drilling Final Results - 2014 Winter Drilling program

Hole No.

UTMNAD83Zone18(1)

AZ

DIP

EOH

from

To

Interval

True Width(2)

Au

NOTE


Easting

Northing

Elevation



(m)

(m)

(m)

(m)

(m)

(g/t)  


ML-14-108

520296

5488383

370

290

-55

480

56.1

58

1.9

1.65

1.81

Upper 325-Megane Zone








445.25

446.5

1.25

1.08

6.44









457

467.47

10.47

9.07

11.55

325-Megane Zone

Including(3)







458

460

2

1.73

48.9


Including(3)







466

467.47

1.47

1.27

11.1


ML-14-109

520316

5488270

370

290

-55

582

66

71.16

5.16

4.47

1.3

Upper 325-Megane Zone

Including(3)







69

71.16

2.16

1.87

1.64

Upper 325-Megane Zone








559.77

560.41

0.64

0.55

0.95

325-Megane Zone

ML-14-110

520302

5488169

370

290

-50

667

210.1

211.26

1.16

1.00

1.04









508

509.45

1.45

1.26

0.71

325-Megane Zone








636.86

640.63

3.77

3.26

13.65

Lower 325-Megane Zone

Including(3)







638.8

639.88

1.08

0.94

46.17


ML-14-111

520318

5488324

370

290

-60

454

59.59

60.13

0.54

0.47

3.48

Upper 325-Megane Zone








300.92

301.92

1

0.87

1.4

325-Megane Zone








420.18

421.16

0.98

0.85

1.85

Lower 325-Megane Zone

ML-14-112

520315

5488321

370

291

-53

652

480.9

489.27

8.37

7.25

1.32

325-Megane Zone

Including(3)







485.18

487.27

2.09

1.81

2.97









596.51

597.65

1.14

1.00

1.48

Lower 325-Megane Zone

ML-14-113

520322

5488221

370

295

-51

550

514

518.47

4.47

3.87

1.50

325-Megane Zone

ML-14-114

520195

5488592

370

290

-60

313

273.8

274.99

1.19

1.03

1.89

325-Megane Zone

ML-14-115

520296

5488383

370

290

-50

304

53.62

54.86

1.24

1.07

1.58

Upper 325-Megane Zone








422.5

424.62

2.12

1.84

2.30

325-Megane Zone








426.1

431.96

5.86

5.07

2.62


Including(3)







426.94

429.15

2.21

1.91

6.21


ML-14-116

520000

5488115

370

291

-61

451

83.92

84.46

0.54

0.47

5.84

Upper 325-Megane Zone








278.07

281.22

3.15

2.73

2.42

325-Megane Zone

Notes:

  1. Drill hole intercepts are calculated with a lower cut of 0.50 g/t Au and represents the best results associated to the intersected structure.
  2. True widths of intersections are approximately 85-90% of the core interval.
  3. Assays are reported uncut but high grade sub-intervals are highlighted.

SOURCE IAMGOLD Corporation

More Stories By PR Newswire

Copyright © 2007 PR Newswire. All rights reserved. Republication or redistribution of PRNewswire content is expressly prohibited without the prior written consent of PRNewswire. PRNewswire shall not be liable for any errors or delays in the content, or for any actions taken in reliance thereon.

Latest Stories
SYS-CON Events announced today that Pulzze Systems will exhibit at the 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. Pulzze Systems, Inc. provides infrastructure products for the Internet of Things to enable any connected device and system to carry out matched operations without programming. For more information, visit http://www.pulzzesystems.com.
SYS-CON Events announced today that Commvault, a global leader in enterprise data protection and information management, has been named “Bronze Sponsor” of SYS-CON's 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. Commvault is a leading provider of data protection and information management solutions, helping companies worldwide activate their data to drive more value and business insight and to transform moder...
Fact is, enterprises have significant legacy voice infrastructure that’s costly to replace with pure IP solutions. How can we bring this analog infrastructure into our shiny new cloud applications? There are proven methods to bind both legacy voice applications and traditional PSTN audio into cloud-based applications and services at a carrier scale. Some of the most successful implementations leverage WebRTC, WebSockets, SIP and other open source technologies. In his session at @ThingsExpo, Da...
SYS-CON Events announced today that Secure Channels will exhibit at the 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. The bedrock of Secure Channels Technology is a uniquely modified and enhanced process based on superencipherment. Superencipherment is the process of encrypting an already encrypted message one or more times, either using the same or a different algorithm.
Traditional on-premises data centers have long been the domain of modern data platforms like Apache Hadoop, meaning companies who build their business on public cloud were challenged to run Big Data processing and analytics at scale. But recent advancements in Hadoop performance, security, and most importantly cloud-native integrations, are giving organizations the ability to truly gain value from all their data. In his session at 19th Cloud Expo, David Tishgart, Director of Product Marketing ...
SYS-CON Events announced today that Bsquare has been named “Silver Sponsor” of SYS-CON's @ThingsExpo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. For more than two decades, Bsquare has helped its customers extract business value from a broad array of physical assets by making them intelligent, connecting them, and using the data they generate to optimize business processes.
DevOps at Cloud Expo – being held November 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA – announces that its Call for Papers is open. Born out of proven success in agile development, cloud computing, and process automation, DevOps is a macro trend you cannot afford to miss. From showcase success stories from early adopters and web-scale businesses, DevOps is expanding to organizations of all sizes, including the world's largest enterprises – and delivering real results. Am...
Almost two-thirds of companies either have or soon will have IoT as the backbone of their business in 2016. However, IoT is far more complex than most firms expected. How can you not get trapped in the pitfalls? In his session at @ThingsExpo, Tony Shan, a renowned visionary and thought leader, will introduce a holistic method of IoTification, which is the process of IoTifying the existing technology and business models to adopt and leverage IoT. He will drill down to the components in this fra...
The vision of a connected smart home is becoming reality with the application of integrated wireless technologies in devices and appliances. The use of standardized and TCP/IP networked wireless technologies in line-powered and battery operated sensors and controls has led to the adoption of radios in the 2.4GHz band, including Wi-Fi, BT/BLE and 802.15.4 applied ZigBee and Thread. This is driving the need for robust wireless coexistence for multiple radios to ensure throughput performance and th...
SYS-CON Events announced today the Kubernetes and Google Container Engine Workshop, being held November 3, 2016, in conjunction with @DevOpsSummit at 19th Cloud Expo at the Santa Clara Convention Center in Santa Clara, CA. This workshop led by Sebastian Scheele introduces participants to Kubernetes and Google Container Engine (GKE). Through a combination of instructor-led presentations, demonstrations, and hands-on labs, students learn the key concepts and practices for deploying and maintainin...
Enterprise IT has been in the era of Hybrid Cloud for some time now. But it seems most conversations about Hybrid are focused on integrating AWS, Microsoft Azure, or Google ECM into existing on-premises systems. Where is all the Private Cloud? What do technology providers need to do to make their offerings more compelling? How should enterprise IT executives and buyers define their focus, needs, and roadmap, and communicate that clearly to the providers?
SYS-CON Events announced today that SoftLayer, an IBM Company, has been named “Gold Sponsor” of SYS-CON's 18th Cloud Expo, which will take place on June 7-9, 2016, at the Javits Center in New York, New York. SoftLayer, an IBM Company, provides cloud infrastructure as a service from a growing number of data centers and network points of presence around the world. SoftLayer’s customers range from Web startups to global enterprises.
There is little doubt that Big Data solutions will have an increasing role in the Enterprise IT mainstream over time. Big Data at Cloud Expo - to be held November 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA - has announced its Call for Papers is open. Cloud computing is being adopted in one form or another by 94% of enterprises today. Tens of billions of new devices are being connected to The Internet of Things. And Big Data is driving this bus. An exponential increase is...
Digital innovation is the next big wave of business transformation based on digital technologies of which IoT and Big Data are key components, For example: Business boundary innovation is a challenge to excavate third-party business value using IoT and BigData, like Nest Business structure innovation may propose re-building business structure from scratch, as Uber does in the taxicab industry The social model innovation is also a big challenge to the new social architecture with the design fr...
DevOps at Cloud Expo, taking place Nov 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA, is co-located with 19th Cloud Expo and will feature technical sessions from a rock star conference faculty and the leading industry players in the world. The widespread success of cloud computing is driving the DevOps revolution in enterprise IT. Now as never before, development teams must communicate and collaborate in a dynamic, 24/7/365 environment. There is no time to wait for long dev...