Wood Pole Inspection and Replacement Program Continues at Penelec to Enhance Service Reliability

READING, Pa., Aug. 20, 2014 /PRNewswire/ -- To help enhance the reliability of its system, Pennsylvania Electric Company (Penelec) crews have replaced or repaired nearly 600 wooden utility poles so far this year as part of the company's annual inspection program. 

Overall, Penelec, a FirstEnergy Corp. (NYSE: FE) utility, expects to inspect more than 41,100 of its 493,339 wooden poles in 2014 for signs of wear, insect infestation or damage from a car accident.

A standard 40-foot wooden distribution pole typically is expected to last more than 50 years.  The most common utility pole is made from a Southern Yellow Pine tree and costs about $400.

"Wooden utility poles form the backbone of our distribution network that delivers electricity to the homes and businesses throughout Penelec's service area.  We expect to replace or repair about 850 poles by the end of the year as part of our ongoing efforts to enhance service reliability for our customers," said Scott Wyman, regional president, Penelec.  "While certainly durable, these poles are in the elements 365 days of the year and subject to damage from severe weather, falling trees, and traffic accidents.  Over time, some poles need to be replaced to help maintain our system's reliability and resiliency."

Typically, specialized contractors perform the pole inspections.  As part of the process, a visual inspection is completed, along with inspecting the pole to determine if the interior is sound.  Poles also can be reinforced rather than replaced.  One of the most common reinforcement techniques is to snug a C-shaped steel beam against the pole, jackhammer the beam into the ground, and secure it to the pole with tight, metal bands. 

All wood poles throughout the 31-county Penelec service territory are inspected on a 12-year cycle.  Inspections began in January and will continue through summer, with the remaining pole replacements and repairs scheduled to be completed during the fall. 

Year-to-date, Penelec has inspected more than 36,500 wooden poles in and around the following communities:

  • Altoona – 4,863
  • Clearfield – 246
  • Philipsburg – 3,494
  • Dubois – 3,455
  • Indiana – 2,222
  • Erie – 8,802
  • Johnstown – 3,139
  • Somerset – 1,700
  • Lewistown – 3,250
  • Shippensburg – 764
  • Oil City – 1,988
  • Meadville – 1,771
  • Bradford – 870

Penelec serves approximately 600,000 customers in 31 Pennsylvania counties. Follow Penelec on Twitter @Penelec.  Visit FirstEnergy on the web at www.firstenergycorp.com.

FirstEnergy is a diversified energy company dedicated to safety, reliability and operational excellence.  Its 10 electric distribution companies form one of the nation's largest investor-owned electric systems, serving customers in Ohio, Pennsylvania, New Jersey, West Virginia, Maryland and New York. 

Editor's Note:  Photos showing pole repairs are available for download on Flickr.

Forward-Looking Statements: This news release includes forward-looking statements based on information currently available to management. Such statements are subject to certain risks and uncertainties. These statements include declarations regarding management's intents, beliefs and current expectations. These statements typically contain, but are not limited to, the terms "anticipate," "potential," "expect," "will," "intend," "believe," "estimate" and similar words. Forward-looking statements involve estimates, assumptions, known and unknown risks, uncertainties and other factors that may cause actual results, performance or achievements to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements, which may include the following: the speed and nature of increased competition in the electric utility industry, in general, and the retail sales market in particular; the ability to experience growth in the Regulated Distribution and Regulated Transmission segments and to successfully implement our revised sales strategy in the Competitive Energy Services segment; the accomplishment of our regulatory and operational goals in connection with our transmission plan and planned distribution rate cases and the effectiveness of our repositioning strategy; the impact of the regulatory process on the pending matters before the Federal Energy Regulatory Commission and in the various states in which we do business including, but not limited to, matters related to rates and pending rate cases and the Electric Security Plan IV; the uncertainties of various cost recovery and cost allocation issues resulting from American Transmission Systems, Incorporated's realignment into PJM Interconnection, L.L.C.; economic or weather conditions affecting future sales and margins such as the polar vortex or other significant weather events, and all associated regulatory events or actions; regulatory outcomes associated with storm restoration, including but not limited to, Hurricane Sandy, Hurricane Irene and the October snowstorm of 2011; changing energy, capacity and commodity market prices including, but not limited to, coal, natural gas and oil, and their availability and impact on margins; the continued ability of our regulated utilities to recover their costs; costs being higher than anticipated and the success of our policies to control costs and to mitigate low energy, capacity and market prices; other legislative and regulatory changes, and revised environmental requirements, including, but not limited to, possible greenhouse gas emission, water discharge, and coal combustion residual regulations, the potential impacts of Cross State Air Pollution Rule, and the effects of the United States Environmental Protection Agency's Mercury and Air Toxics Standards rules including our estimated costs of compliance; the uncertainty of the timing and amounts of the capital expenditures that may arise in connection with any litigation, including New Source Review litigation or potential regulatory initiatives or rulemakings (including that such expenditures could result in our decision to deactivate or idle certain generating units); the uncertainties associated with the deactivation of certain older regulated and competitive fossil units including the impact on vendor commitments, and the timing thereof as they relate to, among other things, Reliability Must Run arrangements and the reliability of the transmission grid; adverse regulatory or legal decisions and outcomes with respect to our nuclear operations (including, but not limited to the revocation or non-renewal of necessary licenses, approvals or operating permits by the Nuclear Regulatory Commission or as a result of the incident at Japan's Fukushima Daiichi Nuclear Plant); issues arising from the indications of cracking in the shield building at Davis-Besse; the impact of future changes to the operational status or availability of our generating units; the risks and uncertainties associated with litigation, arbitration, mediation and like proceedings, including, but not limited to, any such proceedings related to vendor commitments; replacement power costs being higher than anticipated or not fully hedged; the ability to comply with applicable state and federal reliability standards and energy efficiency and peak demand reduction mandates; changes in customers' demand for power, including but not limited to, changes resulting from the implementation of state and federal energy efficiency and peak demand reduction mandates; the ability to accomplish or realize anticipated benefits from strategic and financial goals including, but not limited to, the ability to reduce costs and to successfully complete our announced financial plans designed to improve our credit metrics and strengthen our balance sheet, including but not limited to, our announced dividend reduction and our proposed capital raising initiatives; our ability to improve electric commodity margins and the impact of, among other factors, the increased cost of fuel and fuel transportation on such margins; changing market conditions that could affect the measurement of certain liabilities and the value of assets held in our Nuclear Decommissioning Trusts, pension trusts and other trust funds, and cause us and our subsidiaries to make additional contributions sooner, or in amounts that are larger than currently anticipated; the impact of changes to material accounting policies; the ability to access the public securities and other capital and credit markets in accordance with our announced financial plans, the cost of such capital and overall condition of the capital and credit markets affecting us and our subsidiaries; actions that may be taken by credit rating agencies that could negatively affect us and our subsidiaries' access to financing, increase the costs thereof, and increase requirements to post additional collateral to support outstanding commodity positions, letters of credit and other financial guarantees; changes in national and regional economic conditions affecting us, our subsidiaries and our major industrial and commercial customers, and other counterparties including fuel suppliers, with which we do business; the impact of any changes in tax laws or regulations or adverse tax audit results or rulings; issues concerning the stability of domestic and foreign financial institutions and counterparties with which we do business; the risks and other factors discussed from time to time in our United States Securities and Exchange Commission filings, and other similar factors. The foregoing review of factors should not be construed as exhaustive. New factors emerge from time to time, and it is not possible for management to predict all such factors, nor assess the impact of any such factor on FirstEnergy's business or the extent to which any factor, or combination of factors, may cause results to differ materially from those contained in any forward-looking statements. FirstEnergy expressly disclaims any current intention to update, except as required by law, any forward-looking statements contained herein as a result of new information, future events or otherwise.

SOURCE FirstEnergy Corp.

More Stories By PR Newswire

Copyright © 2007 PR Newswire. All rights reserved. Republication or redistribution of PRNewswire content is expressly prohibited without the prior written consent of PRNewswire. PRNewswire shall not be liable for any errors or delays in the content, or for any actions taken in reliance thereon.

Latest Stories
Container technology is sending shock waves through the world of cloud computing. Heralded as the 'next big thing,' containers provide software owners a consistent way to package their software and dependencies while infrastructure operators benefit from a standard way to deploy and run them. Containers present new challenges for tracking usage due to their dynamic nature. They can also be deployed to bare metal, virtual machines and various cloud platforms. How do software owners track the usag...
"We do data integration for B2B also application to application, and we do data management and enable Big Data," explained Pat Adamiak, Vice President, Product Marketing at Liaison Technologies, in this SYS-CON.tv interview at 16th Cloud Expo, held June 9-11, 2015, at the Javits Center in New York City.
The Cloud industry has moved from being more than just being able to provide infrastructure and management services on the Cloud. Enter a new era of Cloud computing where monetization’s services through the Cloud are an essential piece of strategy to feed your organizations bottom-line, your revenue and Profitability. In their session at 16th Cloud Expo, Ermanno Bonifazi, CEO & Founder of Solgenia, and Ian Khan, Global Strategic Positioning & Brand Manager at Solgenia, discussed how to easily o...
Chuck Piluso presented a study of cloud adoption trends and the power and flexibility of IBM Power and Pureflex cloud solutions. Prior to Secure Infrastructure and Services, Mr. Piluso founded North American Telecommunication Corporation, a facilities-based Competitive Local Exchange Carrier licensed by the Public Service Commission in 10 states, serving as the company's chairman and president from 1997 to 2000. Between 1990 and 1997, Mr. Piluso served as chairman & founder of International Te...
"ProfitBricks was founded in 2010 and we are the painless cloud - and we are also the Infrastructure as a Service 2.0 company," noted Achim Weiss, Chief Executive Officer and Co-Founder of ProfitBricks, in this SYS-CON.tv interview at 16th Cloud Expo, held June 9-11, 2015, at the Javits Center in New York City.
Puppet Labs has announced the next major update to its flagship product: Puppet Enterprise 2015.2. This release includes new features providing DevOps teams with clarity, simplicity and additional management capabilities, including an all-new user interface, an interactive graph for visualizing infrastructure code, a new unified agent and broader infrastructure support.
For IoT to grow as quickly as analyst firms’ project, a lot is going to fall on developers to quickly bring applications to market. But the lack of a standard development platform threatens to slow growth and make application development more time consuming and costly, much like we’ve seen in the mobile space. In his session at @ThingsExpo, Mike Weiner, Product Manager of the Omega DevCloud with KORE Telematics Inc., discussed the evolving requirements for developers as IoT matures and conducte...
SYS-CON Events announced today that MobiDev, a software development company, will exhibit at the 17th International Cloud Expo®, which will take place November 3–5, 2015, at the Santa Clara Convention Center in Santa Clara, CA. MobiDev is a software development company with representative offices in Atlanta (US), Sheffield (UK) and Würzburg (Germany); and development centers in Ukraine. Since 2009 it has grown from a small group of passionate engineers and business managers to a full-scale mobi...
One of the hottest areas in cloud right now is DRaaS and related offerings. In his session at 16th Cloud Expo, Dale Levesque, Disaster Recovery Product Manager with Windstream's Cloud and Data Center Marketing team, will discuss the benefits of the cloud model, which far outweigh the traditional approach, and how enterprises need to ensure that their needs are properly being met.
The time is ripe for high speed resilient software defined storage solutions with unlimited scalability. ISS has been working with the leading open source projects and developed a commercial high performance solution that is able to grow forever without performance limitations. In his session at Cloud Expo, Alex Gorbachev, President of Intelligent Systems Services Inc., shared foundation principles of Ceph architecture, as well as the design to deliver this storage to traditional SAN storage co...
The speed of software changes in growing and large scale rapid-paced DevOps environments presents a challenge for continuous testing. Many organizations struggle to get this right. Practices that work for small scale continuous testing may not be sufficient as the requirements grow. In his session at DevOps Summit, Marc Hornbeek, Sr. Solutions Architect of DevOps continuous test solutions at Spirent Communications, explained the best practices of continuous testing at high scale, which is rele...
"We got started as search consultants. On the services side of the business we have help organizations save time and save money when they hit issues that everyone more or less hits when their data grows," noted Otis Gospodnetić, Founder of Sematext, in this SYS-CON.tv interview at @DevOpsSummit, held June 9-11, 2015, at the Javits Center in New York City.
"We've just seen a huge influx of new partners coming into our ecosystem, and partners building unique offerings on top of our API set," explained Seth Bostock, Chief Executive Officer at IndependenceIT, in this SYS-CON.tv interview at 16th Cloud Expo, held June 9-11, 2015, at the Javits Center in New York City.
Learn how to solve the problem of keeping files in sync between multiple Docker containers. In his session at 16th Cloud Expo, Aaron Brongersma, Senior Infrastructure Engineer at Modulus, discussed using rsync, GlusterFS, EBS and Bit Torrent Sync. He broke down the tools that are needed to help create a seamless user experience. In the end, can we have an environment where we can easily move Docker containers, servers, and volumes without impacting our applications? He shared his results so yo...
Explosive growth in connected devices. Enormous amounts of data for collection and analysis. Critical use of data for split-second decision making and actionable information. All three are factors in making the Internet of Things a reality. Yet, any one factor would have an IT organization pondering its infrastructure strategy. How should your organization enhance its IT framework to enable an Internet of Things implementation? In his session at @ThingsExpo, James Kirkland, Red Hat's Chief Arch...