Caza Oil & Gas Announces Results of Second Well at Gramma Ridge

HOUSTON, TEXAS -- (Marketwired) -- 08/27/14 -- Caza Oil & Gas, Inc. ("Caza" or the "Company") (TSX: CAZ)(AIM: CAZA) is pleased to announce another good result at Gramma Ridge and provide a drilling update at Lennox. Both properties are operated by the Company.

Gramma Ridge Property, Lea County, New Mexico: The Gramma Ridge 27 State #2H horizontal Bone Spring test well (the "27-2H well") reached the intended total measured depth of approximately 14,650 feet in the targeted 2nd Bone Spring Sand interval and was subsequently fracture stimulated in 24 stages beginning on August 4, 2014. Under controlled flowback the producing rates have steadily increased, and the well produced at a 24 hour gross rate of 870 barrels (bbls) of oil equivalent, which is comprised of 679 bbls of oil and 1.15 million cubic feet of natural gas, on August 24, 2014. The well was producing on a 42/64ths adjustable choke at 370 pounds per square inch flowing tubing pressure. Facilities are already in place on the property, and both oil and natural gas will be flowing to sales in short order.

In addition to proving up the 2nd Bone Spring Sand interval, log data was obtained across the Brushy Canyon, Avalon and 1st Bone Spring Sand intervals in the 27-2H well. The data indicates the presence of oil and natural gas across each of these intervals, which is favorable for future development on this 320 acre lease. The 3rd Bone Spring Sand is already proven and producing on the property from the Gramma Ridge 27 State #1H directly offsetting the 27-2H well. Management believes the deeper Wolfcamp formation on the property is also prospective for oil and natural gas.

Caza currently has a 52.5% working interest (approximate 40.82% net revenue interest) in the Gramma Ridge 27-2H well and the property.

Lennox Property, Lea County, New Mexico: The rig from the Gramma Ridge property was moved to the Lennox property. The Company commenced drilling operations on the Lennox 32 State Unit #4H horizontal Bone Spring well (the "32-4H well") on August 17, 2014. The 32-4H well is currently drilling ahead at approximately 5,760 feet to an intended total vertical depth of 11,300 feet before drilling the lateral section, which is intended to reach a total measured depth of 15,740 feet.

Caza has a 50.00% working interest (approximate 38.98% net revenue interest) in the 32-4H well and the Lennox property.

W. Michael Ford, Chief Executive Officer commented:

"We are extremely pleased with this result at Gramma Ridge. The initial 3rd Bone Spring test well on the property was a step out from our recent successes in the play, so proving up the 2nd Bone Spring interval with the offset 27-2H test well is an excellent result that again demonstrates the significant upside to be realized from stacked pay intervals in the play. This result will have a positive effect on both reserves and drilling locations on the property.

We are also happy to be drilling ahead on the Lennox 32-4H well and look forward to updating the market once this well has been drilled and completed."

About Caza

Caza is engaged in the acquisition, exploration, development and production of hydrocarbons in the following regions of the United States of America through its subsidiary, Caza Petroleum, Inc.: Permian Basin (West Texas and Southeast New Mexico) and Texas and Louisiana Gulf Coast (on-shore).

The Toronto Stock Exchange has neither approved nor disapproved the information contained herein.

In accordance with AIM Rules - Guidance Note for Mining, Oil and Gas Companies, the information contained in this announcement has been reviewed and approved by Anthony B. Sam, Vice President Operations of Caza who is a Petroleum Engineer and a member of The Society of Petroleum Engineers.


Information in this news release that is not current or historical factual information may constitute forward-looking information within the meaning of securities laws. Such information is often, but not always, identified by the use of words such as "seek", "anticipate", "plan", "schedule", "continue", "estimate", "expect", "excellent", "may", "will", "hope", "project", "predict", "potential", "intend", "could", "might", "should", "believe", "develop", "test", "anticipation", "looks to be", "suggests" and similar expressions. In particular, information regarding the potential or future development of any property, the timing of future sales, or the timing, depth, scope or success of, and information to be obtained from, drilling or completion operations, reserves, drilling locations, future sales and potential pay zones contained in this news release constitutes forward-looking information within the meaning of securities laws.

Implicit in this information, are assumptions regarding the success and timing of drilling operations, rig availability, projected production, projected revenue and expenses and well performance. These assumptions, although considered reasonable by the Company at the time of preparation, may prove to be incorrect. Readers are cautioned that actual future operations, operating results and economic performance of the Company are subject to a number of risks and uncertainties, including general economic, market and business conditions, well performance and operating risks and could differ materially from what is currently expected as set out above. The Gramma Ridge 27 State #2H horizontal Bone Spring well is in early stages of production. Future flow rates may vary, perhaps materially, and the tests disclosed herein are not necessarily indicative of long-term performance or of ultimate recovery.

For more exhaustive information on these risks and uncertainties you should refer to the Company's most recently filed annual information form which is available at and the Company's website at You should not place undue importance on forward-looking information and should not rely upon this information as of any other date. While we may elect to, we are under no obligation and do not undertake to update this information at any particular time except as may be required by securities laws.

Boe or barrel of oil equivalent may be misleading, particularly if used in isolation. A boe conversion of six thousand cubic feet: 1 barrel is based on an energy equivalency conversion method primarily applicable at the burner tip and does not represent a value equivalency at the well head. Given that the value ratio based on the current price of oil as compared to natural gas is significantly different from the energy equivalency of 6:1, utilizing a conversion on a 6:1 basis may be misleading as an indication of value.

Caza Oil & Gas, Inc.
Michael Ford
+1 432 682 7424

Caza Oil & Gas, Inc.
John McGoldrick
+65 9731 7471 (Singapore)

Cenkos Securities plc
Beth McKiernan
+44 131 220 9778 (Edinburgh)

Cenkos Securities plc
Neil McDonald
+44 131 220 6939 (Edinburgh)

Vigo Communications
Chris McMahon
+44 20 7016 9570

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
For almost two decades, businesses have discovered great opportunities to engage with customers and even expand revenue through digital systems, including web and mobile applications. Yet, even now, the conversation between the business and the technologists that deliver these systems is strained, in large part due to misaligned objectives. In his session at DevOps Summit, James Urquhart, Senior Vice President of Performance Analytics at SOASTA, Inc., will discuss how measuring user outcomes –...
As a company adopts a DevOps approach to software development, what are key things that both the Dev and Ops side of the business must keep in mind to ensure effective continuous delivery? In his session at DevOps Summit, Mark Hydar, Head of DevOps, Ericsson TV Platforms, will share best practices and provide helpful tips for Ops teams to adopt an open line of communication with the development side of the house to ensure success between the two sides.
SYS-CON Events announced today that ProfitBricks, the provider of painless cloud infrastructure, will exhibit at SYS-CON's 17th International Cloud Expo®, which will take place on November 3–5, 2015, at the Santa Clara Convention Center in Santa Clara, CA. ProfitBricks is the IaaS provider that offers a painless cloud experience for all IT users, with no learning curve. ProfitBricks boasts flexible cloud servers and networking, an integrated Data Center Designer tool for visual control over the...
Recently announced Azure Data Lake addresses the big data 3V challenges; volume, velocity and variety. It is one more storage feature in addition to blobs and SQL Azure database. Azure Data Lake (should have been Azure Data Ocean IMHO) is really omnipotent. Just look at the key capabilities of Azure Data Lake:
The IoT market is on track to hit $7.1 trillion in 2020. The reality is that only a handful of companies are ready for this massive demand. There are a lot of barriers, paint points, traps, and hidden roadblocks. How can we deal with these issues and challenges? The paradigm has changed. Old-style ad-hoc trial-and-error ways will certainly lead you to the dead end. What is mandatory is an overarching and adaptive approach to effectively handle the rapid changes and exponential growth.
DevOps is here to stay because it works. Most businesses using this methodology are already realizing a wide range of real, measurable benefits as a result of implementing DevOps, including the breakdown of inter-departmental silos, faster delivery of new features and more stable operating environments. To take advantage of the cloud’s improved speed and flexibility, development and operations teams need to work together more closely and productively. In his session at DevOps Summit, Prashanth...
As a CIO, are your direct reports IT managers or are they IT leaders? The hard truth is that many IT managers have risen through the ranks based on their technical skills, not their leadership ability. Many are unable to effectively engage and inspire, creating forward momentum in the direction of desired change. Renowned for its approach to leadership and emphasis on their people, organizations increasingly look to our military for insight into these challenges.
Achim Weiss is Chief Executive Officer and co-founder of ProfitBricks. In 1995, he broke off his studies to co-found the web hosting company "Schlund+Partner." The company "Schlund+Partner" later became the 1&1 web hosting product line. From 1995 to 2008, he was the technical director for several important projects: the largest web hosting platform in the world, the second largest DSL platform, a video on-demand delivery network, the largest eMail backend in Europe, and a universal billing syste...
Docker is hot. However, as Docker container use spreads into more mature production pipelines, there can be issues about control of Docker images to ensure they are production-ready. Is a promotion-based model appropriate to control and track the flow of Docker images from development to production? In his session at DevOps Summit, Fred Simon, Co-founder and Chief Architect of JFrog, will demonstrate how to implement a promotion model for Docker images using a binary repository, and then show h...
Too often with compelling new technologies market participants become overly enamored with that attractiveness of the technology and neglect underlying business drivers. This tendency, what some call the “newest shiny object syndrome,” is understandable given that virtually all of us are heavily engaged in technology. But it is also mistaken. Without concrete business cases driving its deployment, IoT, like many other technologies before it, will fade into obscurity.
The IoT is upon us, but today’s databases, built on 30-year-old math, require multiple platforms to create a single solution. Data demands of the IoT require Big Data systems that can handle ingest, transactions and analytics concurrently adapting to varied situations as they occur, with speed at scale. In his session at @ThingsExpo, Chad Jones, chief strategy officer at Deep Information Sciences, will look differently at IoT data so enterprises can fully leverage their IoT potential. He’ll sha...
In his session at DevOps Summit, Bryan Cantrill, CTO at Joyent, will demonstrate a third path: containers on multi-tenant bare metal that maximizes performance, security, and networking connectivity.
DevOps has often been described in terms of CAMS: Culture, Automation, Measuring, Sharing. While we’ve seen a lot of focus on the “A” and even on the “M”, there are very few examples of why the “C" is equally important in the DevOps equation. In her session at @DevOps Summit, Lori MacVittie, of F5 Networks, will explore HTTP/1 and HTTP/2 along with Microservices to illustrate why a collaborative culture between Dev, Ops, and the Network is critical to ensuring success.
Manufacturing has widely adopted standardized and automated processes to create designs, build them, and maintain them through their life cycle. However, many modern manufacturing systems go beyond mechanized workflows to introduce empowered workers, flexible collaboration, and rapid iteration. Such behaviors also characterize open source software development and are at the heart of DevOps culture, processes, and tooling.
Containers have changed the mind of IT in DevOps. They enable developers to work with dev, test, stage and production environments identically. Containers provide the right abstraction for microservices and many cloud platforms have integrated them into deployment pipelines. DevOps and Containers together help companies to achieve their business goals faster and more effectively.