PRD Energy Announces Operational Update

CALGARY, ALBERTA -- (Marketwired) -- 08/27/14 -- PRD Energy Inc. ("PRD" or the "Company") (TSX VENTURE: PRD) announces completion of its financial statements and operating results as at and for the six months ended June 30, 2014 and provides an operational update on activities to date as well as an outlook for the remainder of 2014. The Company's interim condensed consolidated financial statements and management's discussion and analysis for the reporting period will be filed today on SEDAR at www.sedar.com and posted on the Company's website at www.prdenergy.de.

Development of the Volkensen Production Licence

In early August, the Company applied for a four well development permit on its Volkensen Production Licence. Volkensen is an oil pool which was abandoned in 1993 after producing approximately 900,000 barrels. The Company believes that potential recoveries can be enhanced through a three stage development plan:


--  Stage 1: Drill two horizontal wells adjacent to the existing vertical
    wells based on existing 2D seismic, well control, reservoir data and
    other geological data available to the Company. This stage is expected
    to evaluate reservoir pressures, flow rates, and logs, amongst other
    things, to be used in stage 2 of the development.

--  Stage 2: Drill two additional horizontal wells from the existing pad
    after the completion of the first two horizontal wells and evaluation of
    the planned 3D seismic program described below.

--  Stage 3: Development of several additional wells depending on the
    results of the completed development program.

Subject to the receipt of all required regulatory approvals, site construction and drilling for the first stage is expected to commence in the fourth quarter of 2014 and continue into the first half of 2015.

The Volkensen well site design is expected to significantly reduce the environmental impact associated with large concrete pad structures typically utilized in the North West German Basin. The proposed matting and asphalt design is anticipated to have a secondary benefit of reducing costs of construction and remediation especially. This approach should also reduce the well site footprint, particularly when combined with the surface benefits of horizontal drilling.

Volkensen/Sittensen Seismic Program

The Company has commenced the permitting of a 90 sq. km 3D seismic program for its Volkensen and Sittensen licences. Early indications from both the reservoir and 2D seismic data obtained to date have led the Company to believe that its Sittensen licence is highly prospective for conventional horizontal oil development. Subject to the receipt of all required regulatory approvals, the seismic program is expected to start in the fourth quarter of 2014 and be completed and interpreted in the first quarter of 2015.

The seismic data is expected to enable the Company to further delineate Volkensen and four additional high impact exploration prospects which it has identified to date. Other pools in the North West German Basin with reservoir intervals and trapping geometries similar to the Company's prospects have each recovered more than five million barrels of oil during their development. The seismic program will be funded from existing cash balances at a cost of approximately $5,000,000 CDN.

PRD is the operator and 100% holder of both the Volkensen and Sittensen licences, subject to a 50% back-in right in favour of the prior operator in respect of the Volkensen production licence only. Given the scope and prospects of these licences, the Company is evaluating one or more farm-out transactions with strategic partners with the goal of increasing activity and development on the Company's other licences.

Boerger Field

PRD has received an expanded 3D seismic data set covering the Boerger field and surrounding area. It has completed its reprocessing of this data and submitted a field development plan to the operator, which the operator is currently reviewing. The Company is also in discussions with the operator to become the designated operator for all future field re-development in order to accelerate development timeframes for this pool. The Company has proposed drilling two wells from the Boerger 7A well site in the first quarter of 2015 as the next stage of development for the Boerger pool. In effect, the Company's accelerated Volkensen development drilling has substituted the well development activity originally planned for Boerger in the last quarter of 2014.

The operator and the Company completed facility modifications at Boerger 7A during June, 2014 and are assessing the effectiveness of these modifications. In that regard, the operator has shut-in production in order to carry out certain pressure transient tests and is expected to produce the Boerger 7A well intermittently for the remainder of the third quarter. Since being placed on production, the Boerger 7A well has completed 102 operating days between February 24 and June 30, 2014 and produced a total of 15,729 barrels of oil. PRD is encouraged by the initial results of this well, however feels that the well is not producing to its full capability due to production being limited to a portion of the horizontal length. The Company has proposed a work-over plan to the operator utilizing an acid squeeze to improve productive capability, a method which the Company believes would optimize completion methods for future wells.

The Boerger 7A well represents a significant milestone in the Company's development which it can use to expand its business in Germany over its significant land position. This operation has provided the Company with valuable operating experience which it is currently using to develop cost reduction strategies to apply to its independent operations elsewhere in Germany. Further, the knowledge gained of the regulations and regulatory process, the understanding of the local service company dynamics, and our improved public communication methods which incorporate transparency to all German stakeholders, are all as a result of drilling Boerger 7A. The permitting for the development of Volkensen and the 3D seismic shoot over the Volkensen and Sittensen Licences stand to be substantial beneficiaries of this experience which bodes well for our ability to be able to substantially increase activity in 2015 and beyond.

Other Licences

The Company recently obtained legacy geophysical and production data over one of its production licences from one of the largest oil & gas companies in the North West German Basin marking the first transaction between PRD and this company. This transaction expands the Company's strategic access to legacy data which is an important step in advancing activity on its licences. The Company is evaluating the data received to date.

PRD is continuing to augment its understanding of its existing land base of 2,413,300 acres with improved access to data of Germany's major oil & gas companies. Management has recently completed a technical review of its existing licences and prospects resulting in the high-grading of certain exploration and production licences. These licenses are expected to be the focus of corporate activity in late 2015 and throughout 2016.

PRD remains committed to the German marketplace both environmentally and economically. In the last twelve months, the Company has increased its staffing levels in Germany from three professionals to over ten while continuing to manage its general and administrative expenses to a modest level. We are committed to expanding our business in Germany with highly skilled German people and expect to continue to increase employment in the country. World class netbacks and an attractive underdeveloped geologic environment, combined with the current geopolitical situation in Eastern Europe, provide incentives for both the oil and gas industry and its stakeholders to progress with development of Germany's vast natural resources.

About PRD Energy

PRD Energy Inc. is a Calgary based oil and gas company engaged in the exploration, development and acquisition of, natural gas and crude oil in Germany. PRD's common shares are listed on the TSX Venture Exchange with the symbol "PRD".

Forward looking information

This news release contains forward-looking information relating to enhancing potential recoveries from the Volkensen oil pool, expected results from first stage of the Volkensen development program, expected timing for commencement of the first stage of the Volkensen development program, environmental impacts and reduction of costs associated with operations, prospectivity of the Sittensen licence, expected timing for commencement and completion of the Volkensen/Sittensen seismic program and costs and funding in respect of that program, delineation of exploration prospects, production from the Boerger 7A well, optimizing production capabilities of future wells, cost reduction strategies, focus of corporate activities in 2015 and 2016, expanding the Company's business in Germany and other statements that are forward-looking in nature. Such forward-looking information is subject to important risks, uncertainties and assumptions. The results or events predicated in this forward-looking information may differ materially from actual results or events. As a result, you are cautioned not to place undue reliance on this forward-looking information.

Forward-looking information is based on certain factors and assumptions regarding, among other things, the Company's licenses, and in particular: (i) statements relating to the development of the Volkensen license including wellsite construction and drilling plans are based on a variety of assumptions including, the Company's ability to obtain permits by the end of October 2014, the reservoir pressure and net pay, and the economic feasibility; (ii) statements relating to the seismic program, the source of funding for the shooting the seismic and the results from the seismic data are based on a variety of assumptions including the Company's ability to obtain permits by the end of October 2014 and PRD Energy's ability finance or farmout a portion of the license; and (iii) statements relating to the ability of the Company to successfully increase production through the completion of a workover, are based on a variety of assumptions including that the Company will be named operator, the Company will obtain permits in a timely manner for additional wells and that PRD Energy will successfully complete a workover on the wells, the future performance of the Boerger 7A well, the success of future exploration and development activities, the impact of increasing competition; the general stability of the economic and political environments in which the Company operates or owns interests; the timely receipt of any required regulatory approvals; the ability of the Company to obtain qualified staff, equipment and services in a timely and cost efficient manner; drilling results; the ability to operate in a safe, efficient and effective manner; the ability of the Company to obtain financing to fund its operations on acceptable terms; field production rates and decline rates; the ability to replace and expand oil and natural gas reserves through acquisition, development of exploration; the timing and costs of pipeline, storage and facility construction and expansion and the ability of the Company to secure adequate product transportation; future oil and natural gas prices; currency, exchange and interest rates; the regulatory framework regarding royalties, taxes and environmental matters in the jurisdictions in which the Company operates; and the ability of the Company to successfully market its oil and natural gas products, and other similar matters. While the Company considers these assumptions to be reasonable based on information currently available to it, they may prove to be incorrect.

Forward looking-information is subject to certain factors, including risks and uncertainties that could cause actual results to differ materially from what is currently expected. These factors include risks associated with the failure to obtain permits when expected, the failure identify economic operations in the Boerger pool following the proposed work-over, declining production from the Boerger 7A well, timing of field operations at Volkensen and Sittensen and the ability to attract a joint venture or farm-in partner, instability of the economic and political environments in which the Company operates or owns interests, ability to manage water production and disposal, oil and gas exploration, development, exploitation, production, marketing and transportation, loss of markets, volatility of commodity prices, currency fluctuations, environmental risks, competition from other producers, inability to retain drilling rigs and other services, incorrect assessment of the value of acquisitions, the inability to settle the definitive terms of the farmout arrangements, failure to realize the anticipated benefits of acquisitions, delays resulting from or inability to obtain required regulatory approvals, inability to obtain approvals from the Company's partners in operations, and ability to access sufficient capital from internal and external sources, reliance on key personnel, regulatory risks and delays, including risks relating to the acquisition of necessary licenses and permits, environmental risks and insurance risks.

Certain information contained herein is considered "analogous information" as defined in National Instrument 51-101 ("NI 51-101"), including the production history for areas outside the Company's Sittensen and Volkensen licences. Such analogous information has not been prepared in accordance with NI 51-101 and the Canadian Oil and Gas Evaluation Handbook and PRD is unable to confirm whether such information has been prepared by a qualified reserves evaluator. Such information is based on independent public data and public information received from other producers and PRD has no way of verifying the accuracy of such information. Such information has been presented to help demonstrate the basis for the Company's business plans and strategies. There is no certainty that such results will be achieved by PRD and such information should not be construed as an estimate of future reserves or resources or future production levels from the Company's licences.

You should not place undue importance on forward-looking information and should not rely upon this information as of any other date. While the Company may elect to, the Company is under no obligation and does not undertake to update this information at any particular time, except as required by law.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Contacts:
PRD Energy Inc.
Michael Greenwood
Chairman and Chief Executive Officer
(403) 234-0501
(403) 234-0511 (FAX)

PRD Energy Inc.
Mark Hornett
President and Chief Operating Officer
(403) 234-0501
(403) 234-0511 (FAX)

PRD Energy Inc.
Jeff Scott
Vice President, Finance and Chief Financial Officer
(403) 234-0501
(403) 234-0511 (FAX)

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
Kubernetes is a new and revolutionary open-sourced system for managing containers across multiple hosts in a cluster. Ansible is a simple IT automation tool for just about any requirement for reproducible environments. In his session at @DevOpsSummit at 18th Cloud Expo, Patrick Galbraith, a principal engineer at HPE, discussed how to build a fully functional Kubernetes cluster on a number of virtual machines or bare-metal hosts. Also included will be a brief demonstration of running a Galera M...
Why do your mobile transformations need to happen today? Mobile is the strategy that enterprise transformation centers on to drive customer engagement. In his general session at @ThingsExpo, Roger Woods, Director, Mobile Product & Strategy – Adobe Marketing Cloud, covered key IoT and mobile trends that are forcing mobile transformation, key components of a solid mobile strategy and explored how brands are effectively driving mobile change throughout the enterprise.
Developing software for the Internet of Things (IoT) comes with its own set of challenges. Security, privacy, and unified standards are a few key issues. In addition, each IoT product is comprised of (at least) three separate application components: the software embedded in the device, the back-end service, and the mobile application for the end user’s controls. Each component is developed by a different team, using different technologies and practices, and deployed to a different stack/target –...
Identity is in everything and customers are looking to their providers to ensure the security of their identities, transactions and data. With the increased reliance on cloud-based services, service providers must build security and trust into their offerings, adding value to customers and improving the user experience. Making identity, security and privacy easy for customers provides a unique advantage over the competition.
All clouds are not equal. To succeed in a DevOps context, organizations should plan to develop/deploy apps across a choice of on-premise and public clouds simultaneously depending on the business needs. This is where the concept of the Lean Cloud comes in - resting on the idea that you often need to relocate your app modules over their life cycles for both innovation and operational efficiency in the cloud. In his session at @DevOpsSummit at19th Cloud Expo, Valentin (Val) Bercovici, CTO of So...
SYS-CON Events announced today that Commvault, a global leader in enterprise data protection and information management, has been named “Bronze Sponsor” of SYS-CON's 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. Commvault is a leading provider of data protection and information management solutions, helping companies worldwide activate their data to drive more value and business insight and to transform moder...
SYS-CON Events announced today that eCube Systems, a leading provider of middleware modernization, integration, and management solutions, will exhibit at @DevOpsSummit at 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. eCube Systems offers a family of middleware evolution products and services that maximize return on technology investment by leveraging existing technical equity to meet evolving business needs. ...
SYS-CON Events has announced today that Roger Strukhoff has been named conference chair of Cloud Expo and @ThingsExpo 2016 Silicon Valley. The 19th Cloud Expo and 6th @ThingsExpo will take place on November 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. "The Internet of Things brings trillions of dollars of opportunity to developers and enterprise IT, no matter how you measure it," stated Roger Strukhoff. "More importantly, it leverages the power of devices and the Interne...
Personalization has long been the holy grail of marketing. Simply stated, communicate the most relevant offer to the right person and you will increase sales. To achieve this, you must understand the individual. Consequently, digital marketers developed many ways to gather and leverage customer information to deliver targeted experiences. In his session at @ThingsExpo, Lou Casal, Founder and Principal Consultant at Practicala, discussed how the Internet of Things (IoT) has accelerated our abil...
Digital innovation is the next big wave of business transformation based on digital technologies of which IoT and Big Data are key components, For example: Business boundary innovation is a challenge to excavate third-party business value using IoT and BigData, like Nest Business structure innovation may propose re-building business structure from scratch, as Uber does in the taxicab industry The social model innovation is also a big challenge to the new social architecture with the design fr...
Whether they’re located in a public, private, or hybrid cloud environment, cloud technologies are constantly evolving. While the innovation is exciting, the end mission of delivering business value and rapidly producing incremental product features is paramount. In his session at @DevOpsSummit at 19th Cloud Expo, Kiran Chitturi, CTO Architect at Sungard AS, will discuss DevOps culture, its evolution of frameworks and technologies, and how it is achieving maturity. He will also cover various st...
So, you bought into the current machine learning craze and went on to collect millions/billions of records from this promising new data source. Now, what do you do with them? Too often, the abundance of data quickly turns into an abundance of problems. How do you extract that "magic essence" from your data without falling into the common pitfalls? In her session at @ThingsExpo, Natalia Ponomareva, Software Engineer at Google, provided tips on how to be successful in large scale machine learning...
If you had a chance to enter on the ground level of the largest e-commerce market in the world – would you? China is the world’s most populated country with the second largest economy and the world’s fastest growing market. It is estimated that by 2018 the Chinese market will be reaching over $30 billion in gaming revenue alone. Admittedly for a foreign company, doing business in China can be challenging. Often changing laws, administrative regulations and the often inscrutable Chinese Interne...
In his session at @ThingsExpo, Kausik Sridharabalan, founder and CTO of Pulzze Systems, Inc., will focus on key challenges in building an Internet of Things solution infrastructure. He will shed light on efficient ways of defining interactions within IoT solutions, leading to cost and time reduction. He will also introduce ways to handle data and how one can develop IoT solutions that are lean, flexible and configurable, thus making IoT infrastructure agile and scalable.
Creating replica copies to tolerate a certain number of failures is easy, but very expensive at cloud-scale. Conventional RAID has lower overhead, but it is limited in the number of failures it can tolerate. And the management is like herding cats (overseeing capacity, rebuilds, migrations, and degraded performance). Download Slide Deck: ▸ Here In his general session at 18th Cloud Expo, Scott Cleland, Senior Director of Product Marketing for the HGST Cloud Infrastructure Business Unit, discusse...