PRD Energy Announces Operational Update

CALGARY, ALBERTA -- (Marketwired) -- 08/27/14 -- PRD Energy Inc. ("PRD" or the "Company") (TSX VENTURE: PRD) announces completion of its financial statements and operating results as at and for the six months ended June 30, 2014 and provides an operational update on activities to date as well as an outlook for the remainder of 2014. The Company's interim condensed consolidated financial statements and management's discussion and analysis for the reporting period will be filed today on SEDAR at www.sedar.com and posted on the Company's website at www.prdenergy.de.

Development of the Volkensen Production Licence

In early August, the Company applied for a four well development permit on its Volkensen Production Licence. Volkensen is an oil pool which was abandoned in 1993 after producing approximately 900,000 barrels. The Company believes that potential recoveries can be enhanced through a three stage development plan:


--  Stage 1: Drill two horizontal wells adjacent to the existing vertical
    wells based on existing 2D seismic, well control, reservoir data and
    other geological data available to the Company. This stage is expected
    to evaluate reservoir pressures, flow rates, and logs, amongst other
    things, to be used in stage 2 of the development.

--  Stage 2: Drill two additional horizontal wells from the existing pad
    after the completion of the first two horizontal wells and evaluation of
    the planned 3D seismic program described below.

--  Stage 3: Development of several additional wells depending on the
    results of the completed development program.

Subject to the receipt of all required regulatory approvals, site construction and drilling for the first stage is expected to commence in the fourth quarter of 2014 and continue into the first half of 2015.

The Volkensen well site design is expected to significantly reduce the environmental impact associated with large concrete pad structures typically utilized in the North West German Basin. The proposed matting and asphalt design is anticipated to have a secondary benefit of reducing costs of construction and remediation especially. This approach should also reduce the well site footprint, particularly when combined with the surface benefits of horizontal drilling.

Volkensen/Sittensen Seismic Program

The Company has commenced the permitting of a 90 sq. km 3D seismic program for its Volkensen and Sittensen licences. Early indications from both the reservoir and 2D seismic data obtained to date have led the Company to believe that its Sittensen licence is highly prospective for conventional horizontal oil development. Subject to the receipt of all required regulatory approvals, the seismic program is expected to start in the fourth quarter of 2014 and be completed and interpreted in the first quarter of 2015.

The seismic data is expected to enable the Company to further delineate Volkensen and four additional high impact exploration prospects which it has identified to date. Other pools in the North West German Basin with reservoir intervals and trapping geometries similar to the Company's prospects have each recovered more than five million barrels of oil during their development. The seismic program will be funded from existing cash balances at a cost of approximately $5,000,000 CDN.

PRD is the operator and 100% holder of both the Volkensen and Sittensen licences, subject to a 50% back-in right in favour of the prior operator in respect of the Volkensen production licence only. Given the scope and prospects of these licences, the Company is evaluating one or more farm-out transactions with strategic partners with the goal of increasing activity and development on the Company's other licences.

Boerger Field

PRD has received an expanded 3D seismic data set covering the Boerger field and surrounding area. It has completed its reprocessing of this data and submitted a field development plan to the operator, which the operator is currently reviewing. The Company is also in discussions with the operator to become the designated operator for all future field re-development in order to accelerate development timeframes for this pool. The Company has proposed drilling two wells from the Boerger 7A well site in the first quarter of 2015 as the next stage of development for the Boerger pool. In effect, the Company's accelerated Volkensen development drilling has substituted the well development activity originally planned for Boerger in the last quarter of 2014.

The operator and the Company completed facility modifications at Boerger 7A during June, 2014 and are assessing the effectiveness of these modifications. In that regard, the operator has shut-in production in order to carry out certain pressure transient tests and is expected to produce the Boerger 7A well intermittently for the remainder of the third quarter. Since being placed on production, the Boerger 7A well has completed 102 operating days between February 24 and June 30, 2014 and produced a total of 15,729 barrels of oil. PRD is encouraged by the initial results of this well, however feels that the well is not producing to its full capability due to production being limited to a portion of the horizontal length. The Company has proposed a work-over plan to the operator utilizing an acid squeeze to improve productive capability, a method which the Company believes would optimize completion methods for future wells.

The Boerger 7A well represents a significant milestone in the Company's development which it can use to expand its business in Germany over its significant land position. This operation has provided the Company with valuable operating experience which it is currently using to develop cost reduction strategies to apply to its independent operations elsewhere in Germany. Further, the knowledge gained of the regulations and regulatory process, the understanding of the local service company dynamics, and our improved public communication methods which incorporate transparency to all German stakeholders, are all as a result of drilling Boerger 7A. The permitting for the development of Volkensen and the 3D seismic shoot over the Volkensen and Sittensen Licences stand to be substantial beneficiaries of this experience which bodes well for our ability to be able to substantially increase activity in 2015 and beyond.

Other Licences

The Company recently obtained legacy geophysical and production data over one of its production licences from one of the largest oil & gas companies in the North West German Basin marking the first transaction between PRD and this company. This transaction expands the Company's strategic access to legacy data which is an important step in advancing activity on its licences. The Company is evaluating the data received to date.

PRD is continuing to augment its understanding of its existing land base of 2,413,300 acres with improved access to data of Germany's major oil & gas companies. Management has recently completed a technical review of its existing licences and prospects resulting in the high-grading of certain exploration and production licences. These licenses are expected to be the focus of corporate activity in late 2015 and throughout 2016.

PRD remains committed to the German marketplace both environmentally and economically. In the last twelve months, the Company has increased its staffing levels in Germany from three professionals to over ten while continuing to manage its general and administrative expenses to a modest level. We are committed to expanding our business in Germany with highly skilled German people and expect to continue to increase employment in the country. World class netbacks and an attractive underdeveloped geologic environment, combined with the current geopolitical situation in Eastern Europe, provide incentives for both the oil and gas industry and its stakeholders to progress with development of Germany's vast natural resources.

About PRD Energy

PRD Energy Inc. is a Calgary based oil and gas company engaged in the exploration, development and acquisition of, natural gas and crude oil in Germany. PRD's common shares are listed on the TSX Venture Exchange with the symbol "PRD".

Forward looking information

This news release contains forward-looking information relating to enhancing potential recoveries from the Volkensen oil pool, expected results from first stage of the Volkensen development program, expected timing for commencement of the first stage of the Volkensen development program, environmental impacts and reduction of costs associated with operations, prospectivity of the Sittensen licence, expected timing for commencement and completion of the Volkensen/Sittensen seismic program and costs and funding in respect of that program, delineation of exploration prospects, production from the Boerger 7A well, optimizing production capabilities of future wells, cost reduction strategies, focus of corporate activities in 2015 and 2016, expanding the Company's business in Germany and other statements that are forward-looking in nature. Such forward-looking information is subject to important risks, uncertainties and assumptions. The results or events predicated in this forward-looking information may differ materially from actual results or events. As a result, you are cautioned not to place undue reliance on this forward-looking information.

Forward-looking information is based on certain factors and assumptions regarding, among other things, the Company's licenses, and in particular: (i) statements relating to the development of the Volkensen license including wellsite construction and drilling plans are based on a variety of assumptions including, the Company's ability to obtain permits by the end of October 2014, the reservoir pressure and net pay, and the economic feasibility; (ii) statements relating to the seismic program, the source of funding for the shooting the seismic and the results from the seismic data are based on a variety of assumptions including the Company's ability to obtain permits by the end of October 2014 and PRD Energy's ability finance or farmout a portion of the license; and (iii) statements relating to the ability of the Company to successfully increase production through the completion of a workover, are based on a variety of assumptions including that the Company will be named operator, the Company will obtain permits in a timely manner for additional wells and that PRD Energy will successfully complete a workover on the wells, the future performance of the Boerger 7A well, the success of future exploration and development activities, the impact of increasing competition; the general stability of the economic and political environments in which the Company operates or owns interests; the timely receipt of any required regulatory approvals; the ability of the Company to obtain qualified staff, equipment and services in a timely and cost efficient manner; drilling results; the ability to operate in a safe, efficient and effective manner; the ability of the Company to obtain financing to fund its operations on acceptable terms; field production rates and decline rates; the ability to replace and expand oil and natural gas reserves through acquisition, development of exploration; the timing and costs of pipeline, storage and facility construction and expansion and the ability of the Company to secure adequate product transportation; future oil and natural gas prices; currency, exchange and interest rates; the regulatory framework regarding royalties, taxes and environmental matters in the jurisdictions in which the Company operates; and the ability of the Company to successfully market its oil and natural gas products, and other similar matters. While the Company considers these assumptions to be reasonable based on information currently available to it, they may prove to be incorrect.

Forward looking-information is subject to certain factors, including risks and uncertainties that could cause actual results to differ materially from what is currently expected. These factors include risks associated with the failure to obtain permits when expected, the failure identify economic operations in the Boerger pool following the proposed work-over, declining production from the Boerger 7A well, timing of field operations at Volkensen and Sittensen and the ability to attract a joint venture or farm-in partner, instability of the economic and political environments in which the Company operates or owns interests, ability to manage water production and disposal, oil and gas exploration, development, exploitation, production, marketing and transportation, loss of markets, volatility of commodity prices, currency fluctuations, environmental risks, competition from other producers, inability to retain drilling rigs and other services, incorrect assessment of the value of acquisitions, the inability to settle the definitive terms of the farmout arrangements, failure to realize the anticipated benefits of acquisitions, delays resulting from or inability to obtain required regulatory approvals, inability to obtain approvals from the Company's partners in operations, and ability to access sufficient capital from internal and external sources, reliance on key personnel, regulatory risks and delays, including risks relating to the acquisition of necessary licenses and permits, environmental risks and insurance risks.

Certain information contained herein is considered "analogous information" as defined in National Instrument 51-101 ("NI 51-101"), including the production history for areas outside the Company's Sittensen and Volkensen licences. Such analogous information has not been prepared in accordance with NI 51-101 and the Canadian Oil and Gas Evaluation Handbook and PRD is unable to confirm whether such information has been prepared by a qualified reserves evaluator. Such information is based on independent public data and public information received from other producers and PRD has no way of verifying the accuracy of such information. Such information has been presented to help demonstrate the basis for the Company's business plans and strategies. There is no certainty that such results will be achieved by PRD and such information should not be construed as an estimate of future reserves or resources or future production levels from the Company's licences.

You should not place undue importance on forward-looking information and should not rely upon this information as of any other date. While the Company may elect to, the Company is under no obligation and does not undertake to update this information at any particular time, except as required by law.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Contacts:
PRD Energy Inc.
Michael Greenwood
Chairman and Chief Executive Officer
(403) 234-0501
(403) 234-0511 (FAX)

PRD Energy Inc.
Mark Hornett
President and Chief Operating Officer
(403) 234-0501
(403) 234-0511 (FAX)

PRD Energy Inc.
Jeff Scott
Vice President, Finance and Chief Financial Officer
(403) 234-0501
(403) 234-0511 (FAX)

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
For organizations that have amassed large sums of software complexity, taking a microservices approach is the first step toward DevOps and continuous improvement / development. Integrating system-level analysis with microservices makes it easier to change and add functionality to applications at any time without the increase of risk. Before you start big transformation projects or a cloud migration, make sure these changes won’t take down your entire organization.
SYS-CON Events announced today that Hitrons Solutions will exhibit at the 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. Hitrons Solutions Inc. is distributor in the North American market for unique products and services of small and medium-size businesses, including cloud services and solutions, SEO marketing platforms, and mobile applications.
With the introduction of IoT and Smart Living in every aspect of our lives, one question has become relevant: What are the security implications? To answer this, first we have to look and explore the security models of the technologies that IoT is founded upon. In his session at @ThingsExpo, Nevi Kaja, a Research Engineer at Ford Motor Company, will discuss some of the security challenges of the IoT infrastructure and relate how these aspects impact Smart Living. The material will be delivered i...
Historically, some banking activities such as trading have been relying heavily on analytics and cutting edge algorithmic tools. The coming of age of powerful data analytics solutions combined with the development of intelligent algorithms have created new opportunities for financial institutions. In his session at 20th Cloud Expo, Sebastien Meunier, Head of Digital for North America at Chappuis Halder & Co., will discuss how these tools can be leveraged to develop a lasting competitive advanta...
What if you could build a web application that could support true web-scale traffic without having to ever provision or manage a single server? Sounds magical, and it is! In his session at 20th Cloud Expo, Chris Munns, Senior Developer Advocate for Serverless Applications at Amazon Web Services, will show how to build a serverless website that scales automatically using services like AWS Lambda, Amazon API Gateway, and Amazon S3. We will review several frameworks that can help you build serverle...
Your homes and cars can be automated and self-serviced. Why can't your storage? From simply asking questions to analyze and troubleshoot your infrastructure, to provisioning storage with snapshots, recovery and replication, your wildest sci-fi dream has come true. In his session at @DevOpsSummit at 20th Cloud Expo, Dan Florea, Director of Product Management at Tintri, will provide a ChatOps demo where you can talk to your storage and manage it from anywhere, through Slack and similar services ...
VeriStor Systems has announced that CRN has named VeriStor to its 2017 Managed Service Provider (MSP) 500 list in the Elite 150 category. This annual list recognizes North American solution providers with cutting-edge approaches to delivering managed services. Their offerings help companies navigate the complex and ever-changing landscape of IT, improve operational efficiencies, and maximize their return on IT investments. In today’s fast-paced business environments, MSPs play an important role...
SYS-CON Events announced today that CA Technologies has been named “Platinum Sponsor” of SYS-CON's 20th International Cloud Expo®, which will take place on June 6-8, 2017, at the Javits Center in New York City, NY, and the 21st International Cloud Expo®, which will take place October 31-November 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. CA Technologies helps customers succeed in a future where every business – from apparel to energy – is being rewritten by software. From ...
SYS-CON Events announced today that Cloudistics, an on-premises cloud computing company, has been named “Bronze Sponsor” of SYS-CON's 20th International Cloud Expo®, which will take place on June 6-8, 2017, at the Javits Center in New York City, NY. Cloudistics delivers a complete public cloud experience with composable on-premises infrastructures to medium and large enterprises. Its software-defined technology natively converges network, storage, compute, virtualization, and management into a ...
Keeping pace with advancements in software delivery processes and tooling is taxing even for the most proficient organizations. Point tools, platforms, open source and the increasing adoption of private and public cloud services requires strong engineering rigor - all in the face of developer demands to use the tools of choice. As Agile has settled in as a mainstream practice, now DevOps has emerged as the next wave to improve software delivery speed and output. To make DevOps work, organization...
SYS-CON Events announced today that Juniper Networks (NYSE: JNPR), an industry leader in automated, scalable and secure networks, will exhibit at SYS-CON's 20th International Cloud Expo®, which will take place on June 6-8, 2017, at the Javits Center in New York City, NY. Juniper Networks challenges the status quo with products, solutions and services that transform the economics of networking. The company co-innovates with customers and partners to deliver automated, scalable and secure network...
My team embarked on building a data lake for our sales and marketing data to better understand customer journeys. This required building a hybrid data pipeline to connect our cloud CRM with the new Hadoop Data Lake. One challenge is that IT was not in a position to provide support until we proved value and marketing did not have the experience, so we embarked on the journey ourselves within the product marketing team for our line of business within Progress. In his session at @BigDataExpo, Sum...
DevOps is often described as a combination of technology and culture. Without both, DevOps isn't complete. However, applying the culture to outdated technology is a recipe for disaster; as response times grow and connections between teams are delayed by technology, the culture will die. A Nutanix Enterprise Cloud has many benefits that provide the needed base for a true DevOps paradigm. In his Day 3 Keynote at 20th Cloud Expo, Chris Brown, a Solutions Marketing Manager at Nutanix, will explore t...
SYS-CON Events announced today that Ocean9will exhibit at SYS-CON's 20th International Cloud Expo®, which will take place on June 6-8, 2017, at the Javits Center in New York City, NY. Ocean9 provides cloud services for Backup, Disaster Recovery (DRaaS) and instant Innovation, and redefines enterprise infrastructure with its cloud native subscription offerings for mission critical SAP workloads.
DevOps is often described as a combination of technology and culture. Without both, DevOps isn't complete. However, applying the culture to outdated technology is a recipe for disaster; as response times grow and connections between teams are delayed by technology, the culture will die. A Nutanix Enterprise Cloud has many benefits that provide the needed base for a true DevOps paradigm.