True Gold Mining Reports Q2 2014 Financial Results

VANCOUVER, BRITISH COLUMBIA -- (Marketwired) -- 08/29/14 -- True Gold Mining Inc. (TSX VENTURE: TGM) ("True Gold" or the "Company") is pleased to announce financial results and business highlights for the six-months ended June 30, 2014.

"We delivered on a number of key milestones related to financing, permitting, project development and exploration," stated Dwayne Melrose, True Gold's President & CEO. "We are now the clear leader among our development peers and as we continue to execute over the next 15 months we will emerge as a new and highly profitable gold producer with a long life gold mine in Burkina Faso."

SECOND-QUARTER 2014 HIGHLIGHTS AND SUBSEQUENT EVENTS INCLUDE:


--  Project Finance - Karma Project Fully Funded:

    --  Secured up to US$120 million financing from Franco-Nevada
        Corporation and Sandstorm Gold Inc. to fully fund the Karma Project
        construction as well as certain corporate and Burkina general and
        administrative costs.

    --  Since May 2013, True Gold has arranged approximately $200 million in
        funding. In February 2014, we closed a public market bought deal
        financing, which included participation from our second largest
        shareholder Teck Resources Limited, and a concurrent private
        placement with Liberty Metals & Mining Holdings, LLC, for total
        gross proceeds of $51.9 million. These proceeds provided the project
        equity component necessary to develop and construct the Karma
        Project and support ongoing exploration.

    --  With development fully funded and mining permits secured to commence
        construction, True Gold's Board of Directors has approved a
        construction decision and is targeting commercial production for the
        end of 2015.



--  Permitting:

    --  Received the Karma Project exploitation (mining) permit to conduct
        mine construction and operations at three of the development
        deposits. A ground breaking ceremony was held in May 2014.

    --  Burkina Faso Ministry of Environment granting of the final
        environmental permits for all Karma development deposits.

    --  Burkina Faso Ministry of Mines Technical Committee approval of the
        application to extend the Karma exploitation permit to include the
        Nami and Kao deposits. We are expecting approval of the extension of
        the Karma exploitation permit to be granted by the end of Q3.



--  Project Development:

    --  Commenced construction activities including upgrading the site
        access road and the start of plant site earthworks.

    --  Ordered and put deposits on the mining fleet for delivery to site in
        Q4 - 2014.

    --  Continued to strengthen our mine-building team in Burkina Faso.

    --  Completed detailed engineering and design, results of which indicate
        a potential for cost savings in a number of important areas.

    --  Completed Phase 2 barrage construction ahead of schedule and under
        budget. The barrage is currently filled to full capacity and will
        provide sufficient water for mine construction and operational
        needs, as well as potentially providing a year-round water source
        for local communities.

    --  Awarded SENET (Pty) Ltd., a leading South African based mineral
        process and engineering firm, the engineering, procurement and
        construction management contract for the construction of the Karma
        Project.



--  Reserves:

    --  Probable Mineral Reserves of 949 kozs gold (33.2 Mt at 0.89g/t Au).



--  Resource Update:

    --  Reported a significant new resource north of the Kao deposit ("North
        Kao") that adds 1.66 million ounces of gold (Inferred Mineral
        Resource of 47.8 Mt at 1.08 g/t Au) to Karma's overall resource
        inventory and potential future production profile. This includes in-
        pit leachable material of 423 kozs of gold (Inferred Mineral
        Resource of 16.4 Mt at 0.80 g/t Au), potentially doubling the
        leachable material at Karma's largest deposit (Kao). The updated
        Karma Project mineral resource, including North Kao is as follows:



----------------------------------------------------------------------------
Category                                   Indicated                Inferred
----------------------------------------------------------------------------
                                  Mt  Au g/t  Au koz      Mt  Au g/t  Au koz
----------------------------------------------------------------------------

----------------------------------------------------------------------------
In-Pit (shell-constrained)      75.2    1.08   2,621    65.3    1.13   2,362
----------------------------------------------------------------------------

----------------------------------------------------------------------------
Global Mineral Inventory        82.6    1.04   2,776      80    1.05   2,704
----------------------------------------------------------------------------
1.   The Mineral Resource estimate is quoted at the same cut-off grades and
     economic parameters for the constrained pit optimizations that were
     used for mineral resources in the updated Karma Technical Report: 0.20
     grams per tonne ("g/t") gold ("Au") for Oxide, 0.22 g/t Au for
     Transition and 0.5 g/t Au for Sulphide, and a gold price of US$1,557/oz
     (refer to NI 43-101 technical report titled "Technical Report
     andUpdated Resource Estimate on the Karma Gold Project, Burkina Faso,
     West Africa", dated March 13, 2014 and filed on SEDAR on April 28,
     2014).

2.   Mineral Resources presented above are inclusive of Probable Mineral
     Reserves (refer to NI 43-101 technical report titled "Technical Report
     andUpdated Resource Estimate on the Karma Gold Project, Burkina Faso,
     West Africa", dated March 13, 2014 and filed on SEDAR on April 28,
     2014).

3.   Mineral resources which are not mineral reserves do not have
     demonstrated economic viability. The estimate of mineral resources may
     be materially affected by environmental, permitting, legal, title,
     taxation, sociopolitical, marketing, or other relevant issues.

4.   The quantity and grade of reported Inferred mineral resources in this
     estimation are uncertain in nature and there has been insufficient
     exploration to define these Inferred mineral resources as an Indicated
     or Measured mineral resource and it is uncertain if further exploration
     will result in upgrading them to an Indicated or Measured mineral
     resource category.

5.   The mineral resources in this MD&A were estimated using the Canadian
     Institute of Mining, Metallurgy and Petroleum (CIM), CIM Standards on
     Mineral Resources and Reserves, Definitions and Guidelines prepared by
     the CIM Standing Committee on Reserve Definitions and adopted by CIM
     Council.


--  Commenced a Preliminary Economic Assessment ("PEA") on the new inferred
    resource to evaluate the potential economic impact of an extension of
    the mine life as laid out in the technical report entitled "Updated
    Resource Estimate and Feasibility Study on the Karma Gold Project,"
    prepared by P&E Mining Consultants Inc. dated effective December 17,
    2013 ("Karma FS"), a copy of which is available under the Company's
    profile on SEDAR at http://www.sedar.com/. The PEA is anticipated to be
    completed in the second half of 2014.


Exploration


--  Completed a 15,000 metre drill program at key exploration targets at the
    Karma Gold Project. The program is designed to discover new domains of
    open-pit, leachable material that could ultimately be incorporated into
    the current feasibility mine plan for potential mine life extensions or
    throughput increases. Results are expected in Q3 2014.

--  Reported positive drilling results at priority targets that expand and
    demonstrate continuity of gold mineralization and the potential to add
    more near-surface leachable material within the Karma Project.


SELECTED FINANCIAL DATA

The following selected financial data is derived from the unaudited condensed interim consolidated financial statements and related notes thereto for the periods indicated, as prepared in accordance with International Financial Reporting Standards. Details of these results are described in the unaudited condensed interim consolidated financial statements and Management's Discussion and Analysis for the six months ended June 30, 2014. These documents can be found on the Company's website (www.truegold.com) or on SEDAR at www.sedar.com. All amounts are presented in Canadian dollars unless otherwise stated.


----------------------------------------------------------------------------
----------------------------------------------------------------------------
                             Three months ended            Six months ended
                         June 30,      June 30,      June 30,      June 30,
                             2014          2013          2014          2013
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Net loss for the
 period              $ (6,647,327) $ (9,349,714) $(10,942,836) $(14,921,723)
Loss and
 comprehensive loss
 for the period      $ (6,680,098) $ (9,410,256) $(11,008,378) $(15,284,975)
Basic and diluted
 loss per share      $      (0.02) $      (0.05) $      (0.03) $      (0.08)
----------------------------------------------------------------------------
----------------------------------------------------------------------------


----------------------------------------------------------------------------
----------------------------------------------------------------------------
                                                                      As at
                                                     June 30,      December
                                                         2014      31, 2013
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Cash and short term
 investments                                     $ 51,228,202  $ 24,014,411
Working capital                                  $ 47,316,508  $ 21,189,672
Total assets                                     $ 82,591,723  $ 42,758,028
Current liabilities                              $  4,527,182  $  3,162,074
Non-current
 liabilities                                     $        nil  $        nil
Shareholders' equity                             $ 78,064,541  $ 39,595,954
----------------------------------------------------------------------------
----------------------------------------------------------------------------

For the three and six month period ended June 30, 2014, we reported a net loss of $6.6 million and $10.9 million respectively, compared to net losses of $9.3 million and $14.9 million for the three and six month period ended June 30, 2013. Operating expenses totalled $6.9 million for the three months ended June 30, 2014 down 26% from $9.3 million a year earlier. The principle reason for the decrease was lower exploration and evaluation expenditures of $4.9 million (as compared to $6.6 in the comparative period) as the Company has begun pre-development work on the Karma Project. The Company has commenced capitalizing costs related to pre-development in the current period. Decreases in office and general expenses also contributed to the decrease in operating expenses. Operating expenses totalled $11.6 million for the six months ended June 30, 2014 down 22% from $14.9 million a year earlier. The principle reason for the decrease was lower exploration and evaluation expenditures of $6.7 million (as compared to $9.7 in the comparative period) as the Company has begun pre-development work on the Karma Project.

Total assets as at June 30, 2014 have increased since December 31, 2013 by $40.0 million to $82.6 million, mainly due to (i) to an increase in cash and short term investments reflecting cash inflows from financing transactions through the six months ended June 30, 2014; and (ii) the capitalization of pre-development costs related to the Karma Project, including: Phase 2 of the barrage and other construction activities such as upgrading the site access road and the start of plant site earthworks. This increase was partially offset by cash outflows from operations.

Scott Heffernan, M.Sc., P.Geo., Vice President Exploration of the Company, and Peter C. Carter, P. Eng., Chief Operating Officer and Vice President Engineering of the Company, are the designated Qualified Persons within the meaning of NI 43-101 for this news release. They have reviewed and verified that the scientific and technical information contained in this release is accurate and approves of the written disclosure of same.

About True Gold

True Gold Mining Inc. is where gold comes to life. We are committed to growing a successful gold exploration, development and production company, by focusing on projects with low costs, low technical risks and solid economics. The Company's board, management and technical teams have proven track records in gold exploration, development, operations and production worldwide.

Additional information about the Company and its activities may be found on the Company's website at www.truegoldmining.com and under the Company's profile at www.sedar.com.

ON BEHALF OF THE BOARD

Dwayne Melrose, President & CEO

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Unless stated otherwise, information of a scientific or technical nature in this press release regarding the Karma Project is summarized, derived or extracted from the technical report entitled "Updated Resource Estimate on the Karma Gold Project, Burkina Faso, West Africa", dated March 13, 2014 prepared by P&E Mining Consultants Inc.,and filed on SEDAR on April 28, 2014.

Mineral resources which are not mineral reserves do not have demonstrated economic viability. The estimate of mineral resources may be materially affected by environmental, permitting, legal, title, taxation, sociopolitical, marketing, or other relevant issues.

The quantity and grade of reported Inferred mineral resources in this estimation are uncertain in nature and there has been insufficient exploration to define these Inferred mineral resources as an Indicated or Measured mineral resource and it is uncertain if further exploration will result in upgrading them to an Indicated or Measured mineral resource category.

The mineral resources were estimated using the Canadian Institute of Mining, Metallurgy and Petroleum (CIM), CIM Standards on Mineral Resources and Reserves, Definitions and Guidelines prepared by the CIM Standing Committee on Reserve Definitions and adopted by CIM Council.

All statements in this press release, other than statements of historical fact, are "forward-looking information" with respect to True Gold within the meaning of applicable securities laws, including statements with respect to the potential quantity and/or grade of minerals, potential size and expansion of a mineralized zone, proposed timing of exploration and development plans. Forward-looking information is often, but not always, identified by the use of words such as "seek", "anticipate", "plan", "continue", "planned", "expect", "project", "predict", "potential", "targeting", "intends", "believe", "potential", and similar expressions, or describes a "goal", or variation of such words and phrases or state that certain actions, events or results "may", "should", "could", "would", "might" or "will" be taken, occur or be achieved. Forward-looking information is not a guarantee of future performance and is based upon a number of estimates and assumptions of management at the date the statements are made including, among others, assumptions about future prices of gold, copper, silver and other metal prices, currency exchange rates and interest rates, favourable operating conditions, political stability, obtaining governmental approvals and financing on time, obtaining renewals for existing licences and permits and obtaining required licences and permits, labour stability, stability in market conditions, availability of equipment, accuracy of any mineral resources, successful resolution of disputes and anticipated costs and expenditures. Many assumptions are based on factors and events that are not within the control of Pilot Gold and there is no assurance they will prove to be correct.

Such forward-looking information, involves known and unknown risks, which may cause the actual results to be materially different from any future results expressed or implied by such forward-looking information, including, risks related to the interpretation of results at the Karma Project, reliance on technical information provided by third parties as related to the Karma Project; changes in project parameters as plans continue to be refined; current economic conditions; future prices of commodities; possible variations in grade or recovery rates; the costs and timing of the development of new deposits; failure of equipment or processes to operate as anticipated; the failure of contracted parties to perform; the timing and success of exploration activities generally; satisfaction of Burkina Faso requirements relating to the periodic submissions of Environmental Impact Assessments; possible claims against the Company or its joint venture partners; labour disputes and other risks of the mining industry; delays in obtaining governmental approvals, financing or in the completion of exploration, uncertainties relating to the interpretation of drill results and the estimation of mineral resources, the geology, grade and continuity of mineral deposits, accidents, equipment breakdowns, risk of undiscovered, title defects and surface access, the potential for delays in exploration and permitting activities, the potential for unexpected costs and expenses, commodity price fluctuations, currency fluctuations, political risk

as well as those factors discussed in the Annual Information Form of the Company dated April 30, 2014 in the section entitled "Risk Factors", under True Gold's SEDAR profile at www.sedar.com.

Although True Gold has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking information, there may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. There can be no assurance that such information will prove to be accurate as actual results and future events could differ materially from those anticipated in such statements. True Gold disclaims any intention or obligation to update or revise any forward-looking information, whether as a result of new information, future events or otherwise unless required by law.

Cautionary Note to United States Investors Concerning Estimates of Measured, Indicated and Inferred Resources Mineral resources that are not mineral reserves do not have demonstrated economic viability. Mineral resource estimates do not account for mineability, selectivity, mining loss and dilution. There is also no certainty that these inferred mineral resources will be converted to measured and indicated categories through further drilling, or into mineral reserves, once economic considerations are applied. The mineral resource estimates referenced in this press release use the terms "Indicated Mineral Resources" and "Inferred Mineral Resources". While these terms are defined in and required by Canadian regulations (under NI 43-101), these terms are not recognized by the U.S. Securities and Exchange Commission ("SEC"). "Inferred Mineral Resources" have a great amount of uncertainty as to their existence, and great uncertainty as to their economic and legal feasibility. The SEC normally only permits issuers to report mineralization that does not constitute SEC Industry Guide 7 compliant "reserves" as in-place tonnage and grade without reference to unit measures. U.S. investors are cautioned not to assume that any part or all of mineral deposits in these categories will ever be converted into reserves. True Gold is not an SEC registered company.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
SYS-CON Events announced today that FalconStor Software® Inc., a 15-year innovator of software-defined storage solutions, will exhibit at SYS-CON's 18th International Cloud Expo®, which will take place on June 7-9, 2016, at the Javits Center in New York City, NY. FalconStor Software®, Inc. (NASDAQ: FALC) is a leading software-defined storage company offering a converged, hardware-agnostic, software-defined storage and data services platform. Its flagship solution FreeStor®, utilizes a horizonta...
WebSocket is effectively a persistent and fat pipe that is compatible with a standard web infrastructure; a "TCP for the Web." If you think of WebSocket in this light, there are other more hugely interesting applications of WebSocket than just simply sending data to a browser. In his session at 18th Cloud Expo, Frank Greco, Director of Technology for Kaazing Corporation, will compare other modern web connectivity methods such as HTTP/2, HTTP Streaming, Server-Sent Events and new W3C event APIs ...
At first adopted by enterprises to consolidate physical servers, virtualization is now widely used in cloud computing to offer elasticity and scalability. On the other hand, Docker has developed a new way to handle Linux containers, inspired by version control software such as Git, which allows you to keep all development versions. In his session at 17th Cloud Expo, Dominique Rodrigues, the co-founder and CTO of Nanocloud Software, discussed how in order to also handle QEMU / KVM virtual machin...
Silver Spring Networks, Inc. (NYSE: SSNI) extended its Internet of Things technology platform with performance enhancements to Gen5 – its fifth generation critical infrastructure networking platform. Already delivering nearly 23 million devices on five continents as one of the leading networking providers in the market, Silver Spring announced it is doubling the maximum speed of its Gen5 network to up to 2.4 Mbps, increasing computational performance by 10x, supporting simultaneous mesh communic...
Sensors and effectors of IoT are solving problems in new ways, but small businesses have been slow to join the quantified world. They’ll need information from IoT using applications as varied as the businesses themselves. In his session at @ThingsExpo, Roger Meike, Distinguished Engineer, Director of Technology Innovation at Intuit, showed how IoT manufacturers can use open standards, public APIs and custom apps to enable the Quantified Small Business. He used a Raspberry Pi to connect sensors...
Father business cycles and digital consumers are forcing enterprises to respond faster to customer needs and competitive demands. Successful integration of DevOps and Agile development will be key for business success in today’s digital economy. In his session at DevOps Summit, Pradeep Prabhu, Co-Founder & CEO of Cloudmunch, covered the critical practices that enterprises should consider to seamlessly integrate Agile and DevOps processes, barriers to implementing this in the enterprise, and pr...
The cloud promises new levels of agility and cost-savings for Big Data, data warehousing and analytics. But it’s challenging to understand all the options – from IaaS and PaaS to newer services like HaaS (Hadoop as a Service) and BDaaS (Big Data as a Service). In her session at @BigDataExpo at @ThingsExpo, Hannah Smalltree, a director at Cazena, will provide an educational overview of emerging “as-a-service” options for Big Data in the cloud. This is critical background for IT and data profes...
Eighty percent of a data scientist’s time is spent gathering and cleaning up data, and 80% of all data is unstructured and almost never analyzed. Cognitive computing, in combination with Big Data, is changing the equation by creating data reservoirs and using natural language processing to enable analysis of unstructured data sources. This is impacting every aspect of the analytics profession from how data is mined (and by whom) to how it is delivered. This is not some futuristic vision: it's ha...
The principles behind DevOps are not new - for decades people have been automating system administration and decreasing the time to deploy apps and perform other management tasks. However, only recently did we see the tools and the will necessary to share the benefits and power of automation with a wider circle of people. In his session at DevOps Summit, Bernard Sanders, Chief Technology Officer at CloudBolt Software, explored the latest tools including Puppet, Chef, Docker, and CMPs needed to...
With the Apple Watch making its way onto wrists all over the world, it’s only a matter of time before it becomes a staple in the workplace. In fact, Forrester reported that 68 percent of technology and business decision-makers characterize wearables as a top priority for 2015. Recognizing their business value early on, FinancialForce.com was the first to bring ERP to wearables, helping streamline communication across front and back office functions. In his session at @ThingsExpo, Kevin Roberts...
Let’s face it, embracing new storage technologies, capabilities and upgrading to new hardware often adds complexity and increases costs. In his session at 18th Cloud Expo, Seth Oxenhorn, Vice President of Business Development & Alliances at FalconStor, will discuss how a truly heterogeneous software-defined storage approach can add value to legacy platforms and heterogeneous environments. The result reduces complexity, significantly lowers cost, and provides IT organizations with improved effi...
Cognitive Computing is becoming the foundation for a new generation of solutions that have the potential to transform business. Unlike traditional approaches to building solutions, a cognitive computing approach allows the data to help determine the way applications are designed. This contrasts with conventional software development that begins with defining logic based on the current way a business operates. In her session at 18th Cloud Expo, Judith S. Hurwitz, President and CEO of Hurwitz & ...
It's easy to assume that your app will run on a fast and reliable network. The reality for your app's users, though, is often a slow, unreliable network with spotty coverage. What happens when the network doesn't work, or when the device is in airplane mode? You get unhappy, frustrated users. An offline-first app is an app that works, without error, when there is no network connection.
Data-as-a-Service is the complete package for the transformation of raw data into meaningful data assets and the delivery of those data assets. In her session at 18th Cloud Expo, Lakshmi Randall, an industry expert, analyst and strategist, will address: What is DaaS (Data-as-a-Service)? Challenges addressed by DaaS Vendors that are enabling DaaS Architecture options for DaaS
One of the bewildering things about DevOps is integrating the massive toolchain including the dozens of new tools that seem to crop up every year. Part of DevOps is Continuous Delivery and having a complex toolchain can add additional integration and setup to your developer environment. In his session at @DevOpsSummit at 18th Cloud Expo, Miko Matsumura, Chief Marketing Officer of Gradle Inc., will discuss which tools to use in a developer stack, how to provision the toolchain to minimize onboa...