Copper North Progress at Carmacks Project, Yukon

VANCOUVER, BRITISH COLUMBIA -- (Marketwired) -- 09/02/14 -- Copper North Mining Corp. ("Copper North" or the "Company") (TSX VENTURE:COL) is pleased to update its progress on the re-engineering of the Carmacks Project in north central Yukon. Several initiatives are now underway for improving the operations plan and reducing the capital cost of development of the Carmacks Project.

Initial investigations focused on the recovery of gold and silver alongside the leaching of copper; resulting in an increase in mine revenues, a minor increase in capital expenditure, and a reduction of the cost to produce copper, after deduction of gold and silver credits.

With the completion of the Preliminary Economic Assessment ("PEA"), efforts are now focused on evaluating alternative processing plans and opportunities for the reduction of capital expense for the mine facilities (see May 30, 2014 news release).

The addition of a gold and silver leach, alongside the copper leach, warranted a review of the optimal leach plan to maximize both copper and precious metal recovery. A mini-study comparing vat leaching of copper to heap leaching of copper utilizing an on/off leach pad indicated that the capital costs are similar; however, there may be significant operational benefits from using vat leaching.

Vat Leach Alternative

The vat leach process of submerging the crushed ore in weak sulphuric acid, removes much of the operating complexity of leach pads and simplifies environmental management of an on/off leach pad, especially under winter weather conditions. Secondly, it provides for preparation of optimal conditions for cyanide leaching of the spent copper leach material for high recovery of gold and silver. The rapid leach time expected in vat leaching (3 to 5 weeks) provides for an early start for cyanidation of recovery of gold and silver.

A bulk sample is being prepared to undertake the vat leach test work and prepare the leached materials for the cyanidation test work. This is the key additional information necessary to finalize the new processing and development plan and commence the preparation of a new feasibility study and environmental assessment report for re-entry to the permitting process.

Benchmarking and Capital Expenditure Reduction Opportunities

Comparison of capital costs for similar projects have indicated that there are opportunities for the reduction of capital expenditures; particularly, for equipment used in the processing area. Copper North has met with three well accredited engineering institutes in China to discuss the provision of detailed engineering and procurement of certain equipment for the processing or Carmacks ores.

Proposals for engineering and preliminary cost estimates for the SXEW and sulphuric acid plant have been received and indicate that there is potential for 20 to 40% reduction in some components of the development plan at the Carmacks Project. Copper North is advancing discussions with the engineering groups to provide the Company with a detailed proposal for feasibility study level engineering and procurement from China for a range of equipment including the SXEW plant, acid plant, gold-silver recovery unit, electrical components and other mechanical equipment used in materials transfer. This work will be done in cooperation with other engineering groups that will be reviewing and making adjustments from the PEA to adapt to the new development plan that is in progress.

Management is pleased with its progress in identifying and pursuing opportunities for both reducing development costs for the project and improving operations. The metallurgical test work is expected to take approximate three to four months to complete. This work is key to finalizing the development plan and undertaking detailed engineering for a new feasibility study. Expansion of the management team is required to meet the growing engineering and project management needs. Planning for this step is in progress.

Dr. Harlan Meade, P.Geo., is a Qualified Person as defined under National Instrument 43-101 standards, and has prepared and is responsible for the contents of this news release.

On behalf of the Board of Directors:

Dr. Harlan Meade, President, CEO and Director

About Copper North

Copper North is a Canadian mineral exploration and development company. Copper North's assets include the Carmacks Project located in the Yukon, the Thor property located in British Columbia, and the Redstone property located in the Northwest Territories. Copper North trades on the TSX Venture Exchange under the symbol COL.

This news release includes certain forward-looking information or forward-looking statements for the purposes of applicable securities laws. These statements include, among others, statements with respect to results from previous exploration on the Carmacks Project; proposed exploration and development plans, their timing and results achieved from such activity; the potential for reducing capital and operating costs; development, engineering, and permitting activities and their cost and timing; potential operating and economic benefits from using the vat leach process; and future economic operating results. These statements address future events and conditions and, as such, involve known and unknown risks, uncertainties and other factors, which may cause the actual results, performance or achievements to differ materially from those anticipated in such statements. Important factors that could cause actual results to differ materially from the Company's expectations include, among others, the timing and success of future exploration, development, metallurgical, and engineering activities; exploration and development risks; market prices; exploitation and exploration results; availability of capital and financing; general economic, market or business conditions; uninsured risks; regulatory changes; defects in title; availability of personnel, materials and equipment; unanticipated environmental impacts on operations and other exploration risks detailed herein and from time to time in the filings made by the Company with securities regulators. In making the forward-looking statements, the Company has applied several material assumptions including, but not limited to, the proposed exploration and development of the Carmacks Project will proceed as planned; vat leaching will provide expected operational and economic benefits; market fundamentals will result in sustained metals and mineral prices; and any additional financing needed will be available on reasonable terms. The Company expressly disclaims any intention or obligation to update or revise any forward-looking statements whether as a result of new information, future events or otherwise except as otherwise required by applicable securities legislation.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Contacts:
Copper North Mining Corp.
Harlan Meade
Chief Executive Officer
604.638.2505
604.669.2926 (FAX)
[email protected]
www.coppernorthmining.com

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
DX World EXPO, LLC, a Lighthouse Point, Florida-based startup trade show producer and the creator of "DXWorldEXPO® - Digital Transformation Conference & Expo" has announced its executive management team. The team is headed by Levent Selamoglu, who has been named CEO. "Now is the time for a truly global DX event, to bring together the leading minds from the technology world in a conversation about Digital Transformation," he said in making the announcement.
"Space Monkey by Vivent Smart Home is a product that is a distributed cloud-based edge storage network. Vivent Smart Home, our parent company, is a smart home provider that places a lot of hard drives across homes in North America," explained JT Olds, Director of Engineering, and Brandon Crowfeather, Product Manager, at Vivint Smart Home, in this SYS-CON.tv interview at @ThingsExpo, held Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA.
DevOps is under attack because developers don’t want to mess with infrastructure. They will happily own their code into production, but want to use platforms instead of raw automation. That’s changing the landscape that we understand as DevOps with both architecture concepts (CloudNative) and process redefinition (SRE). Rob Hirschfeld’s recent work in Kubernetes operations has led to the conclusion that containers and related platforms have changed the way we should be thinking about DevOps and...
SYS-CON Events announced today that Conference Guru has been named “Media Sponsor” of the 22nd International Cloud Expo, which will take place on June 5-7, 2018, at the Javits Center in New York, NY. A valuable conference experience generates new contacts, sales leads, potential strategic partners and potential investors; helps gather competitive intelligence and even provides inspiration for new products and services. Conference Guru works with conference organizers to pass great deals to gre...
The Internet of Things will challenge the status quo of how IT and development organizations operate. Or will it? Certainly the fog layer of IoT requires special insights about data ontology, security and transactional integrity. But the developmental challenges are the same: People, Process and Platform. In his session at @ThingsExpo, Craig Sproule, CEO of Metavine, demonstrated how to move beyond today's coding paradigm and shared the must-have mindsets for removing complexity from the develop...
In his Opening Keynote at 21st Cloud Expo, John Considine, General Manager of IBM Cloud Infrastructure, led attendees through the exciting evolution of the cloud. He looked at this major disruption from the perspective of technology, business models, and what this means for enterprises of all sizes. John Considine is General Manager of Cloud Infrastructure Services at IBM. In that role he is responsible for leading IBM’s public cloud infrastructure including strategy, development, and offering m...
Companies are harnessing data in ways we once associated with science fiction. Analysts have access to a plethora of visualization and reporting tools, but considering the vast amount of data businesses collect and limitations of CPUs, end users are forced to design their structures and systems with limitations. Until now. As the cloud toolkit to analyze data has evolved, GPUs have stepped in to massively parallel SQL, visualization and machine learning.
The next XaaS is CICDaaS. Why? Because CICD saves developers a huge amount of time. CD is an especially great option for projects that require multiple and frequent contributions to be integrated. But… securing CICD best practices is an emerging, essential, yet little understood practice for DevOps teams and their Cloud Service Providers. The only way to get CICD to work in a highly secure environment takes collaboration, patience and persistence. Building CICD in the cloud requires rigorous ar...
"Evatronix provides design services to companies that need to integrate the IoT technology in their products but they don't necessarily have the expertise, knowledge and design team to do so," explained Adam Morawiec, VP of Business Development at Evatronix, in this SYS-CON.tv interview at @ThingsExpo, held Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA.
To get the most out of their data, successful companies are not focusing on queries and data lakes, they are actively integrating analytics into their operations with a data-first application development approach. Real-time adjustments to improve revenues, reduce costs, or mitigate risk rely on applications that minimize latency on a variety of data sources. In his session at @BigDataExpo, Jack Norris, Senior Vice President, Data and Applications at MapR Technologies, reviewed best practices to ...
Widespread fragmentation is stalling the growth of the IIoT and making it difficult for partners to work together. The number of software platforms, apps, hardware and connectivity standards is creating paralysis among businesses that are afraid of being locked into a solution. EdgeX Foundry is unifying the community around a common IoT edge framework and an ecosystem of interoperable components.
"ZeroStack is a startup in Silicon Valley. We're solving a very interesting problem around bringing public cloud convenience with private cloud control for enterprises and mid-size companies," explained Kamesh Pemmaraju, VP of Product Management at ZeroStack, in this SYS-CON.tv interview at 21st Cloud Expo, held Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA.
Large industrial manufacturing organizations are adopting the agile principles of cloud software companies. The industrial manufacturing development process has not scaled over time. Now that design CAD teams are geographically distributed, centralizing their work is key. With large multi-gigabyte projects, outdated tools have stifled industrial team agility, time-to-market milestones, and impacted P&L stakeholders.
"Akvelon is a software development company and we also provide consultancy services to folks who are looking to scale or accelerate their engineering roadmaps," explained Jeremiah Mothersell, Marketing Manager at Akvelon, in this SYS-CON.tv interview at 21st Cloud Expo, held Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA.
Enterprises are adopting Kubernetes to accelerate the development and the delivery of cloud-native applications. However, sharing a Kubernetes cluster between members of the same team can be challenging. And, sharing clusters across multiple teams is even harder. Kubernetes offers several constructs to help implement segmentation and isolation. However, these primitives can be complex to understand and apply. As a result, it’s becoming common for enterprises to end up with several clusters. Thi...