VAL-D'OR, QUEBEC -- (Marketwired) -- 09/22/16 -- Metanor Resources Inc. ("Metanor") (TSX VENTURE: MTO) is pleased to present the highlights from the positive preliminary economic assessment study (PEA) completed by GoldMinds Geoservices Inc. on its Barry gold project (Mining Lease BM number 886) which is located 100 km east of Lebel sur Quevillon and 115 km south of the Bachelor Mine in Quebec.

Highlights of PEA Barry ((i)) all in CAD dollars, include:


--  Net present value (NPV) before taxes (at 6%) of $53.5 million;
--  Internal rate of return (IRR) before taxes of 198%;
--  NPV after taxes (at 6%) of $25.9 million;
--  IRR after taxes of 94%;
--  Capital startup of $8.5 million;
--  Payback of 0.71 years with a gold price of $1,560 / oz;
--  All-in production cost of $1,114 / oz (US $891 / oz);
--  For the life of the mine, a production of 193,457 ounces of gold over 9
    years;
--  An average of 21,495 ounces of gold production with up to 37,573 ounces
    in year 2;
--  Milling of 1,200 tonnes per day at the Bachelor plant, with an average
    grade of 1.75 g/t diluted for the life of the mine including the first 3
    years at 2.61 g/t with a metallurgical recovery of 95%;
--  Sterile ration mineralization of 2.17 to 1.

Mr Ghislain Morin, President and CEO of Metanor Resources Inc., declared, on behalf of the board of directors: "This positive preliminary economic study is an important milestone for Metanor. We point out that the deposit is located on a Mining Lease previously granted, the deposit is ready to be exploited and it has the potential for expansion. Moreover, there are no steaming agreements covering the Barry project. We will be moving quickly with startup planned for the summer of 2017, following a feasibility study which will include current drilling results. "

The Study

The Barry gold mine could potentially support an open pit mine with a conventional treatment plant using mineral industry standards, including: crushing, grinding, gravity concentration, cyanide leaching tanks, adsorption of gold by coal activated desorption of coal, electrolytic sensing, refining and reactivation of coal in addition to the destruction of cyanides released from the leach circuit. The Bachelor processing plant has been resized for an annual capacity of 420,000 tons in this preliminary technical and economic study (PEA). The anticipated gold recovery is expected to exceed 95%. No provision has been made for the treatment of low mineralized material and content for material that could be mined by underground method. The calculation of the tax and mining rights was conducted by the firm Raymond Chabot Grant Thornton (RCGT) of Val d'Or from a cash flow document prepared by GMG. The current scenario plans for transport by road train of 150 tons. An average milling index of 13.3 kWh / t is used.

The pit resources in all categories totaled 2.23Mt @ 1.54 g / t measured, 270kt @ 1.40 g / t Indicated, and 1.17Mt @ 2.69 g / t inferred. The pit resources are derived from the total mineral resources using a model of blocks 3m E x 3m N x 3m Z - rounded - capped at 35 g / t, with a cutoff grade above 0.66 g / t.


--------------------------------------------------------
Classification                         Mineral Resources
                    ------------------------------------
                         Tonnage    Grade Au  Au content
                    ------------------------------------
                               T         g/t          Oz
--------------------------------------------------------
Measured               2,225,000        1.54     101,000
--------------------------------------------------------
Indicated                270,000        1.40      12,000
--------------------------------------------------------
Measure + indicated    2,490,000        1.52     122,000
--------------------------------------------------------
Inferred               1,170,000        2.69     101,000
--------------------------------------------------------

--------------------------------------------------------



----------------------------------------------------------------------------
Classification                                Waste                    Total
                    --------------------------------------------------------
                       Tonnage  Grade Au Au content   Tonnage    Sterile/ore
                    --------------------------------------------------------
                             T       g/t         Oz         T
----------------------------------------------------------------------------
Measured             4,175,000      0.24     33,000 6,400,000
----------------------------------------------------------------------------
Indicated              515,000      0.21      3,400   780,000
----------------------------------------------------------------------------
Measure + indicated  4,690,000      0.24     36,000 7,180,000
----------------------------------------------------------------------------
Inferred             2,660,000      0.07      6,000 3,825,000
----------------------------------------------------------------------------
                                                                        2.01
----------------------------------------------------------------------------


---------------------------------------------------------------------------
Technical Summary
---------------------------------------------------------------------------
Mine life (LOM)                                                     9 years
Pit resources                                                       3.612Mt
Average diluted grade gold                                         1.75 g/t
Uncovering rate (sterile ration: ore)                                2.17:1
Tonnage treated per year                                           420,000t
Average annual production sold                                    21,495 oz
Gold produced and sold total                                     193,457 oz

Main Capital cost                                                       CAD
Overburden stripping                                                      0
Processing plant                                                     $1.1 M
Road repairs (40 km)                                                   $2 M
Mine, Drilling, Feasibility                                         $2.85 M
Tailings                                                            $0.55 M
Infrastructure                                                         $2 M
Total starting capital cost                                          $8.5 M

Operation cost (per ton processed)                                      CAD
Mining cost                                                        $27.28/t
Processing cost                                                    $19.90/t
Exploration (resources renewal)                                     $2.01/t
Accommodation & employee transportation                             $1.88/t
Increasing of the tailings pond capacity                            $0.15/t
Administrative fees                                                 $6,76/t

Financial results before taxes with a price
 of gold at 1,560 / oz (CAD)
NPV at 6%                                                           $53.50M
IRR                                                                    198%
Cost for the production of one ounce                               $1114/oz
Capital reimbursement period                                        0.58 yr
Available Cash Flow                                                $61.15 M

Financial results after taxes with a price of
 gold at 1,560 / oz (CAD)
NPV at 6%                                                            $25.9M
IRR                                                                     94%
Capital reimbursement period                                        0.71 yr
Available Cash flow                                                 $30.95M
---------------------------------------------------------------------------

The financial analysis using a price of gold of CAD$1,710, representing a 10% increase from the $1,560 used in the PEA would generate a NPV of $78.07 million with an IRR of 246% before taxes.

((i)) Cautionary statement NI 43-101: The Mineral resources presented here are not mineral reserves, because they have not demonstrated economic viability. The PEA is preliminary in nature and includes inferred resources that are considered speculative geologically to have economic considerations that would categorize them into mineral reserves. There is no certainty that the conclusions of the PEA will be realized. The technical report will be filed within 45 days on SEDAR.

About GoldMinds Geoservices Inc.

Goldminds Geoservices Inc. is a consulting engineering firm specializing in the technical reports NI 43-101, the estimation of mineral resources, drilling program management, geological exploration and geotechnical studies. Goldminds Geoservices Inc. was founded in 2012 by Claude Duplessis, P.Eng., Who was the owner of Geostat Systems International Inc. founded in 1981 by Michel David. Geostat was specializes in geostatistics, orebody modeling, estimation of mineral resources, exploration, pre-feasibility study, and other services. In 2008, Geostat Systems International Inc. was sold to SGS based in Geneva, Switzerland and Mr. Duplessis worked as director / consultant of SGS Geostat division in Blainville until 2011.

Qualified Persons

Pascal Hamelin, P. Eng., Vice-president of Operations, is the Qualified Person under NI 43-101, responsible for reviewing and approving the technical information contained in this news release.

Claude Duplessis, Ing., Gaston Gagnon, Ing, and Gilbert Rousseau, Ing, of Goldminds Geoservices Inc., are the independent qualified person under NI 43-101 who have prepared and reviewed the technical information contained in this release.

Cautionary and Forward-Looking Statements

This press release includes certain statements that may be deemed "forward-looking statements".

The potential quantity and grade is conceptual in nature as there has been insufficient exploration to define a mineral resource and it is uncertain if further exploration will result in the target being delineated as a mineral resource. All statements in this discussion, other than those of historical fact, that address future exploration drilling, exploration activities and projected exploration, including costs and other estimates upon which such projections are based, and events or developments that the company expects, are considered forward-looking statements. Although the Company believes the expectations expressed in these forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance and actual results or developments may differ materially from those forward-looking statements.

Neither the TSX Venture Exchange, nor its Regulation Services Provider accepts responsibility for the adequacy or accuracy of this release.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
DevOps and microservices are permeating software engineering teams broadly, whether these teams are in pure software shops but happen to run a business, such Uber and Airbnb, or in companies that rely heavily on software to run more traditional business, such as financial firms or high-end manufacturers. Microservices and DevOps have created software development and therefore business speed and agility benefits, but they have also created problems; specifically, they have created software sec...
Just over a week ago I received a long and loud sustained applause for a presentation I delivered at this year’s Cloud Expo in Santa Clara. I was extremely pleased with the turnout and had some very good conversations with many of the attendees. Over the next few days I had many more meaningful conversations and was not only happy with the results but also learned a few new things. Here is everything I learned in those three days distilled into three short points.
Why do your mobile transformations need to happen today? Mobile is the strategy that enterprise transformation centers on to drive customer engagement. In his general session at @ThingsExpo, Roger Woods, Director, Mobile Product & Strategy – Adobe Marketing Cloud, covered key IoT and mobile trends that are forcing mobile transformation, key components of a solid mobile strategy and explored how brands are effectively driving mobile change throughout the enterprise.
In this strange new world where more and more power is drawn from business technology, companies are effectively straddling two paths on the road to innovation and transformation into digital enterprises. The first path is the heritage trail – with “legacy” technology forming the background. Here, extant technologies are transformed by core IT teams to provide more API-driven approaches. Legacy systems can restrict companies that are transitioning into digital enterprises. To truly become a lea...
24Notion is full-service global creative digital marketing, technology and lifestyle agency that combines strategic ideas with customized tactical execution. With a broad understand of the art of traditional marketing, new media, communications and social influence, 24Notion uniquely understands how to connect your brand strategy with the right consumer. 24Notion ranked #12 on Corporate Social Responsibility - Book of List.
SYS-CON Events announced today that Roundee / LinearHub will exhibit at the WebRTC Summit at @ThingsExpo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. LinearHub provides Roundee Service, a smart platform for enterprise video conferencing with enhanced features such as automatic recording and transcription service. Slack users can integrate Roundee to their team via Slack’s App Directory, and '/roundee' command lets your video conference ...
Web Real-Time Communication APIs have quickly revolutionized what browsers are capable of. In addition to video and audio streams, we can now bi-directionally send arbitrary data over WebRTC's PeerConnection Data Channels. With the advent of Progressive Web Apps and new hardware APIs such as WebBluetooh and WebUSB, we can finally enable users to stitch together the Internet of Things directly from their browsers while communicating privately and securely in a decentralized way.
More and more companies are looking to microservices as an architectural pattern for breaking apart applications into more manageable pieces so that agile teams can deliver new features quicker and more effectively. What this pattern has done more than anything to date is spark organizational transformations, setting the foundation for future application development. In practice, however, there are a number of considerations to make that go beyond simply “build, ship, and run,” which changes ho...
"My role is working with customers, helping them go through this digital transformation. I spend a lot of time talking to banks, big industries, manufacturers working through how they are integrating and transforming their IT platforms and moving them forward," explained William Morrish, General Manager Product Sales at Interoute, in this SYS-CON.tv interview at 18th Cloud Expo, held June 7-9, 2016, at the Javits Center in New York City, NY.
A strange thing is happening along the way to the Internet of Things, namely far too many devices to work with and manage. It has become clear that we'll need much higher efficiency user experiences that can allow us to more easily and scalably work with the thousands of devices that will soon be in each of our lives. Enter the conversational interface revolution, combining bots we can literally talk with, gesture to, and even direct with our thoughts, with embedded artificial intelligence, wh...
SYS-CON Events announced today the Kubernetes and Google Container Engine Workshop, being held November 3, 2016, in conjunction with @DevOpsSummit at 19th Cloud Expo at the Santa Clara Convention Center in Santa Clara, CA. This workshop led by Sebastian Scheele introduces participants to Kubernetes and Google Container Engine (GKE). Through a combination of instructor-led presentations, demonstrations, and hands-on labs, students learn the key concepts and practices for deploying and maintainin...
Adobe is changing the world though digital experiences. Adobe helps customers develop and deliver high-impact experiences that differentiate brands, build loyalty, and drive revenue across every screen, including smartphones, computers, tablets and TVs. Adobe content solutions are used daily by millions of companies worldwide-from publishers and broadcasters, to enterprises, marketing agencies and household-name brands. Building on its established design leadership, Adobe enables customers not o...
Kubernetes is a new and revolutionary open-sourced system for managing containers across multiple hosts in a cluster. Ansible is a simple IT automation tool for just about any requirement for reproducible environments. In his session at @DevOpsSummit at 18th Cloud Expo, Patrick Galbraith, a principal engineer at HPE, discussed how to build a fully functional Kubernetes cluster on a number of virtual machines or bare-metal hosts. Also included will be a brief demonstration of running a Galera M...
All clouds are not equal. To succeed in a DevOps context, organizations should plan to develop/deploy apps across a choice of on-premise and public clouds simultaneously depending on the business needs. This is where the concept of the Lean Cloud comes in - resting on the idea that you often need to relocate your app modules over their life cycles for both innovation and operational efficiency in the cloud. In his session at @DevOpsSummit at19th Cloud Expo, Valentin (Val) Bercovici, CTO of So...
What are the new priorities for the connected business? First: businesses need to think differently about the types of connections they will need to make – these span well beyond the traditional app to app into more modern forms of integration including SaaS integrations, mobile integrations, APIs, device integration and Big Data integration. It’s important these are unified together vs. doing them all piecemeal. Second, these types of connections need to be simple to design, adapt and configure...