Turquoise Hill announces third quarter 2016 production

VANCOUVER, BC--(Marketwired - October 19, 2016) - Turquoise Hill Resources today announced third quarter 2016 production for Oyu Tolgoi.

Jeff Tygesen, Turquoise Hill Chief Executive Officer, said, "Oyu Tolgoi performed as expected during the third quarter as open-pit operations focused on Phases 3 and 6 after the high-gold Phase 2 was nearly complete in Q2'16. Despite the lower copper and gold production in the quarter, we are confident in our ability to achieve the higher end of our annual guidance."

Oyu Tolgoi set an all-time high in Q3'16 for quarterly material mined of more than 25 million tonnes. This record includes stripping for Phase 4, which is the next area of high-grade ore. In Q3'16, concentrator throughput declined 4.0% over Q2'16 due to planned maintenance and conveyor belt repairs. Copper production in Q3'16 declined 9.9% over Q2'16, as a result of lower recovery from Phase 6 ore. As expected, gold production in Q3'16 declined 47.1% over Q2'16 due to lower grades from the completion of mining Phase 2.

The Company continues to expect Oyu Tolgoi to produce 175,000 to 195,000 tonnes of copper in concentrates and 255,000 to 285,000 ounces of gold in concentrates for 2016.

Underground development

Good progress continues with underground development. During Q3'16, work began for Shaft 5 sinking and the convey-to-surface box cut excavation while construction of critical on-site facilities continued. Oyu Tolgoi recently signed an additional underground mining and support services contract with Dayan Contract Mining, a joint venture between Hasu Megawatt and Redpath, for the sinking of Shafts 2 and 5. At the end of Q3'16, the underground workforce was approximately 1,600 people and is expected to reach 2,400 people by the end of 2016.

Recent press speculation has referenced a seven to nine year ramp up period needed for the Oyu Tolgoi underground mine to reach full production. Based on the 2014 Oyu Tolgoi Technical Report (2014 Technical Report) issued in October 2014, ramp up to full production is expected to take approximately seven years. It is expected that the underground production schedule in the Company's upcoming 2016 Oyu Tolgoi Technical Report will be consistent with the 2014 Technical Report.

Additionally, the timing and amount of future dividend payments to Turquoise Hill shareholders will be based on a number of factors, including timing of underground production commencement, copper price and beginning of shareholder loan repayments, and determined at the sole discretion of the Turquoise Hill Board of Directors. The Board regularly reviews the Company's dividend policy and any payment will be based on future economic conditions.

                                                                            
Oyu Tolgoi Production Data                                                  
All data represents full production and sales on a 100% basis               
                                                             9      9   Full
                         3Q     4Q     1Q     2Q     3Q months months   Year
                       2015   2015   2016   2016   2016   2015   2016   2015
----------------------------------------------------------------------------
                                                                            
Open pit material                                                           
 mined ('000 tonnes) 23,969 23,708 22,867 22,716 25,739 68,063 71,322 91,771
Ore treated ('000                                                           
 tonnes)              8,632  9,369  9,662  9,525  9,146 25,168 28,333 34,537
Average mill head                                                           
 grades:                                                                    
  Copper (%)           0.75   0.69   0.70   0.64   0.66   0.66   0.67   0.67
  Gold (g/t)           0.56   0.92   0.63   0.33   0.21   0.73   0.39   0.78
  Silver (g/t)         1.90   1.67   1.92   1.92   1.99   1.52   1.95   1.56
Concentrates                                                                
 produced ('000                                                             
 tonnes)              210.3  231.8  229.5  207.1  203.2  556.7  639.8  788.5
  Average                                                                   
   concentrate grade                                                        
   (% Cu)              26.6   24.7   25.1   24.9   22.9   26.0   24.4   25.6
Production of metals                                                        
 in concentrates:                                                           
  Copper ('000                                                              
   tonnes)             56.0   57.3   57.6   51.7   46.6  144.9  155.9  202.2
  Gold ('000 ounces)    123    207    144     70     37    446    251    653
  Silver ('000                                                              
   ounces)              388    355    395    391    361    869  1,147  1,223
Concentrate sold                                                            
 ('000 tonnes)        226.0  236.2  213.1  227.4  206.2  583.5  646.6  819.8
Sales of metals in                                                          
 concentrates:                                                              
  Copper ('000                                                              
   tonnes)             58.2   54.7   51.2   54.4   45.7  146.5  151.3  201.3
  Gold ('000 ounces)    200    160    175     95     38    577    307    737
  Silver ('000                                                              
   ounces)              334    360    305    395    341    798  1,041  1,158
Metal recovery (%)                                                          
  Copper               86.4   88.4   85.6   83.3   78.0   87.3   82.4   87.6
  Gold                 76.4   74.2   72.2   69.3   62.0   74.4   69.7   74.4
  Silver               73.0   70.8   66.4   65.9   61.7   69.6   64.7   69.9
                                                                            
                                                                            

About Turquoise Hill Resources

Turquoise Hill Resources (NYSE: TRQ) (NASDAQ: TRQ) (TSX: TRQ) is an international mining company whose primary operation is its 66% interest in the Oyu Tolgoi copper-gold-silver mine in southern Mongolia.

Follow us on Twitter @TurquoiseHillRe

Forward-looking statements

Certain statements made herein, including statements relating to matters that are not historical facts and statements of the Company's beliefs, intentions and expectations about developments, results and events which will or may occur in the future, constitute "forward-looking information" within the meaning of applicable Canadian securities legislation and "forward-looking statements" within the meaning of the "safe harbor" provisions of the U.S. Private Securities Litigation Reform Act of 1995. Forward-looking information and statements relate to future events or future performance, reflect current expectations or beliefs regarding future events and are typically identified by words such as "anticipate", "could", "should", "expect", "seek", "may", "intend", "likely", "plan", "estimate", "will", "believe" and similar expressions suggesting future outcomes or statements regarding an outlook. These include, but are not limited to, statements respecting anticipated business activities, planned expenditures, corporate strategies and other statements that are not historical facts.

Forward-looking statements and information are made based upon certain assumptions and other important factors that, if untrue, could cause the actual results, performance or achievements of the Company to be materially different from future results, performance or achievements expressed or implied by such statements or information. There can be no assurances that such statements or information will prove accurate. Such statements and information contained herein represent the Company's best judgment as of the date hereof based on information currently available. The Company does not assume any obligation to update any forward-looking statements or information or to conform these forward-looking statements or information to actual results, except as required by law.

Important factors that could cause actual results to differ from these forward-looking statements and information are included in the "Risk Factors" section of the Annual Information Form dated as of March 15, 2016 in respect of the year ended December 31, 2015.

Contact

Investors and Media
Tony Shaffer
Office: +1 604 648 3934
Email: [email protected]

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
SYS-CON Events announced today that TidalScale will exhibit at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. TidalScale is the leading provider of Software-Defined Servers that bring flexibility to modern data centers by right-sizing servers on the fly to fit any data set or workload. TidalScale’s award-winning inverse hypervisor technology combines multiple commodity servers (including their ass...
As hybrid cloud becomes the de-facto standard mode of operation for most enterprises, new challenges arise on how to efficiently and economically share data across environments. In his session at 21st Cloud Expo, Dr. Allon Cohen, VP of Product at Elastifile, will explore new techniques and best practices that help enterprise IT benefit from the advantages of hybrid cloud environments by enabling data availability for both legacy enterprise and cloud-native mission critical applications. By rev...
As popularity of the smart home is growing and continues to go mainstream, technological factors play a greater role. The IoT protocol houses the interoperability battery consumption, security, and configuration of a smart home device, and it can be difficult for companies to choose the right kind for their product. For both DIY and professionally installed smart homes, developers need to consider each of these elements for their product to be successful in the market and current smart homes.
Join IBM November 1 at 21st Cloud Expo at the Santa Clara Convention Center in Santa Clara, CA, and learn how IBM Watson can bring cognitive services and AI to intelligent, unmanned systems. Cognitive analysis impacts today’s systems with unparalleled ability that were previously available only to manned, back-end operations. Thanks to cloud processing, IBM Watson can bring cognitive services and AI to intelligent, unmanned systems. Imagine a robot vacuum that becomes your personal assistant tha...
Companies are harnessing data in ways we once associated with science fiction. Analysts have access to a plethora of visualization and reporting tools, but considering the vast amount of data businesses collect and limitations of CPUs, end users are forced to design their structures and systems with limitations. Until now. As the cloud toolkit to analyze data has evolved, GPUs have stepped in to massively parallel SQL, visualization and machine learning.
In his Opening Keynote at 21st Cloud Expo, John Considine, General Manager of IBM Cloud Infrastructure, will lead you through the exciting evolution of the cloud. He'll look at this major disruption from the perspective of technology, business models, and what this means for enterprises of all sizes. John Considine is General Manager of Cloud Infrastructure Services at IBM. In that role he is responsible for leading IBM’s public cloud infrastructure including strategy, development, and offering ...
SYS-CON Events announced today that N3N will exhibit at SYS-CON's @ThingsExpo, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. N3N’s solutions increase the effectiveness of operations and control centers, increase the value of IoT investments, and facilitate real-time operational decision making. N3N enables operations teams with a four dimensional digital “big board” that consolidates real-time live video feeds alongside IoT sensor data a...
In his session at 21st Cloud Expo, Raju Shreewastava, founder of Big Data Trunk, will provide a fun and simple way to introduce Machine Leaning to anyone and everyone. Together we will solve a machine learning problem and find an easy way to be able to do machine learning without even coding. Raju Shreewastava is the founder of Big Data Trunk (www.BigDataTrunk.com), a Big Data Training and consulting firm with offices in the United States. He previously led the data warehouse/business intellige...
In a recent survey, Sumo Logic surveyed 1,500 customers who employ cloud services such as Amazon Web Services (AWS), Microsoft Azure, and Google Cloud Platform (GCP). According to the survey, a quarter of the respondents have already deployed Docker containers and nearly as many (23 percent) are employing the AWS Lambda serverless computing framework. It’s clear: serverless is here to stay. The adoption does come with some needed changes, within both application development and operations. Tha...
SYS-CON Events announced today that Avere Systems, a leading provider of enterprise storage for the hybrid cloud, will exhibit at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 - Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. Avere delivers a more modern architectural approach to storage that doesn't require the overprovisioning of storage capacity to achieve performance, overspending on expensive storage media for inactive data or the overbui...
With major technology companies and startups seriously embracing Cloud strategies, now is the perfect time to attend 21st Cloud Expo October 31 - November 2, 2017, at the Santa Clara Convention Center, CA, and June 12-14, 2018, at the Javits Center in New York City, NY, and learn what is going on, contribute to the discussions, and ensure that your enterprise is on the right path to Digital Transformation.
Data scientists must access high-performance computing resources across a wide-area network. To achieve cloud-based HPC visualization, researchers must transfer datasets and visualization results efficiently. HPC clusters now compute GPU-accelerated visualization in the cloud cluster. To efficiently display results remotely, a high-performance, low-latency protocol transfers the display from the cluster to a remote desktop. Further, tools to easily mount remote datasets and efficiently transfer...
Digital transformation is changing the face of business. The IDC predicts that enterprises will commit to a massive new scale of digital transformation, to stake out leadership positions in the "digital transformation economy." Accordingly, attendees at the upcoming Cloud Expo | @ThingsExpo at the Santa Clara Convention Center in Santa Clara, CA, Oct 31-Nov 2, will find fresh new content in a new track called Enterprise Cloud & Digital Transformation.
SYS-CON Events announced today that mruby Forum will exhibit at the Japan External Trade Organization (JETRO) Pavilion at SYS-CON's 21st International Cloud Expo®, which will take place on Oct 31 – Nov 2, 2017, at the Santa Clara Convention Center in Santa Clara, CA. mruby is the lightweight implementation of the Ruby language. We introduce mruby and the mruby IoT framework that enhances development productivity. For more information, visit http://forum.mruby.org/.
Though cloud is the future of enterprise computing, a smooth transition of legacy applications and systems is critical for seamless business operations. IT professionals are eager to start leveraging the cost, scale and other benefits of cloud, but with massive investments already in place in existing infrastructure and a number of compliance and resource hurdles, it can be challenging to move to a cloud-based infrastructure.