Condor Announces 2017 Third Quarter Results

CALGARY, AB--(Marketwired - November 14, 2017) - Condor Petroleum Inc. ("Condor" or the "Company") (TSX: CPI), a Canadian based oil and gas company focused on exploration and production activities in Turkey and Kazakhstan, is pleased to announce the release of its unaudited interim condensed consolidated financial statements for the three and nine months ended September 30, 2017, together with the related management's discussion and analysis. These documents will be made available under Condor's profile on SEDAR at www.sedar.com and on the Condor website at www.condorpetroleum.com. All financial amounts in this news release are presented in Canadian dollars, unless otherwise stated.

Q3 2017 Highlights

  • Construction of the Poyraz Ridge gas processing facility in Turkey has been completed. Pre-commissioning activities have successfully been performed, introducing gas to the various processing components.
  • Construction of the 16 km Poyraz Ridge sales gas pipeline has also been completed and is undergoing acceptance testing. Commercial production with initial rates targeting 10 MMscf/day is expected to commence in the fourth quarter of 2017.
  • The Poyraz 3 and Poyraz West 4 development wells in Turkey have been completed and tied into the processing facilities.
  • The Yakamoz 1 exploration well in Turkey was drilled to a total depth of 2,250 meters encountering numerous gas shows while drilling. Though the well was abandoned without testing, post-well remapping of the Yakamoz prospect indicates the well was drilled off-structure and side-tracking alternatives are being evaluated.
  • Production from Shoba and Taskuduk in Kazakhstan averaged 457 bopd for the three months and 410 bopd for the nine months ended September 30, 2017 and the operating netback which is defined as crude oil sales revenue less production costs, royalty expense and transportation and selling expense, averaged $19.79 per barrel in the third quarter of 2017 and $18.47 per barrel for the nine months ended September 30, 2017.
  • The Company has referred the Zharkamys exploration contract extension case to the Supreme Court of Kazakhstan and the hearing is scheduled to commence on November 29, 2017. The on-going court proceedings related to Zharkamys do not affect the Company's Shoba and Taskuduk oilfields which are each governed by separate production contracts.
  • During the first quarter of 2017, the Company established and received funds from a USD 10.0 million secured non-revolving credit facility which bears interest at 14% and matures on January 31, 2020 and issued to the lender a warrant certificate exercisable into one million common shares of Condor at $2.35 per share on or before January 31, 2020.
  • The Company recorded net loss of $2.5 million for the three months ended September 30, 2017 (2016: $1.7 million) and $66.5 million for the nine months ended September 30, 2017 (2016: $8.7 million) which includes $56.6 million of exploration and evaluation expense pertaining to the derecognition of the Zharkamys contract in the first quarter of 2017.

Operations

The Shoba and Taskuduk oilfields in Kazakhstan produced 42,059 barrels of oil or an average of 457 bopd for the three months ended September 30, 2017 and 111,806 barrels of oil or an average of 410 bopd for the nine months ended September 30, 2017. For the three and nine months ended September 30, 2016 the Company produced 5,903 barrels of oil or an average of 64 bopd. Production increased as there was no production in 2016 until mid-September when production resumed at Shoba following the signing of the Shoba production contract.

In Turkey, construction of the Poyraz Ridge gas processing facility is complete. Construction of the 6" sales gas pipeline is also complete after receiving approvals for all the surface right-of-way access rights. Production is expected to commence in the fourth quarter of 2017 at an initial rate of 10 MMscf/day following formal commissioning of the facility and the pipeline and obtaining the customary government approvals.

The Poyraz 3 and Poyraz West 4 development wells in Turkey have been completed and tied into the processing facilities.

The Yakamoz 1 exploration well in Turkey was drilled to a total depth of 2,250 meters to test a "new" sub thrust-fold play type located 2 km from the Poyraz Ridge gas field. The well confirmed that an active petroleum system extends to the north and west of Poyraz Ridge and, as predicted, numerous gas shows proved an extensive fracture system prevails along the Miocene-Eocene sub-thrust trend. Though Yakamoz 1 was abandoned without testing, the well provided critical structural and stratigraphic information that can be tied back to the regional 2D seismic as it relates to trap, reservoir and seal within this fairway. Based on the new velocity-depth information, re-mapping of the Yakamoz prospect concluded the well was drilled off-structure. Condor is currently integrating this data into a revised geological model with a view to side-tracking the Yakamoz 1 well in addition to high grading prospective areas for future 3D seismic and additional exploration drilling along and sub-parallel to this trend.

The net loss for the nine months ended September 30, 2017 of $66.5 million (2016: $8.7 million) includes $56.6 million of exploration and evaluation expense pertaining to the derecognition of the Zharkamys contract in the first quarter of 2017 and $1.6 million of exploration and evaluation expense related to the Yakamoz 1 well. Cash used in operations amounted to $1.5 million for the three months ended September 30, 2017 compared to $2.7 million in the third quarter of 2016. Capital expenditures for the three months ended September 30, 2017 amounted to $2.8 million (2016: $6.6 million) and for both periods relates mainly to Poyraz Ridge field development in Turkey.

Zharkamys exploration contract

The Company's Zharkamys exploration contract ("Zharkamys Contract") with the Ministry of Energy of the Government of Kazakhstan ("Ministry") was due to expire on December 14, 2016. Prior to this date, the Kazakhstan Chamber of International Commerce and subsequently the Kazakhstan Civil Court ("Civil Court") confirmed that a force majeure event had occurred which, under Kazakhstan subsurface use law, can be the basis for the Zharkamys Contract validity period to be extended for a period of 630 days. In May 2017, the Kazakhstan Court of Appeal ("Court of Appeal"), pursuant to an appeal filed by the Ministry, released its ruling dated April 14, 2017 that the force majeure event is not recognized and reversed the decision of the Civil Court. As a result of the Court of Appeal ruling, there is uncertainty regarding the Company's future legal rights to have the Zharkamys Contract extended and the related exploration and evaluation assets were derecognized.

The Company has referred the case to the Supreme Court of Kazakhstan ("Supreme Court"), the country's highest legal body and the hearing is scheduled to commence on November 29, 2017. A positive ruling by the Supreme Court to uphold the Civil Court force majeure ruling would likely allow the Company to apply to the Ministry for the 630 day extension of Zharkamys Contract. Conversely, a decision by the Supreme Court to uphold the findings of the Court of Appeal would likely result in the Zharkamys Contract reverting back to the Ministry. The on-going court proceedings do not affect the Company's production rights for the Shoba and Taskuduk oilfields which are each governed by separate production contracts.

Credit Facility

During the first quarter of 2017 the Company established and received funds from a USD 10.0 million secured non-revolving credit facility which bears interest at 14% and matures on January 31, 2020 ("Credit Facility"). Interest for the first year of the Credit Facility is due on January 31, 2018 followed by eight payments of USD 1.25 million of principal plus interest due quarterly in arrears commencing March 31, 2018. Condor also issued to the lender a warrant certificate exercisable into one million common shares of Condor at $2.35 per share on or before January 31, 2020. The loan proceeds are available to fund capital expenditures related to drilling, infrastructure and workovers at Poyraz Ridge and for general corporate purposes.

NON-GAAP FINANCIAL MEASURES

The Company refers to "operating netback" in this news release, a term with no standardized meaning as prescribed by GAAP and which may not be comparable with similar measures presented by other issuers. This additional information should not be considered in isolation or as a substitute for measures prepared in accordance with GAAP. Operating netback is calculated as crude oil sales revenue less production costs, royalty expense and transportation and selling expense on a dollar basis and divided by the sales volume for the period on a per barrel basis. This non-GAAP measure is commonly used in the oil and gas industry to assist in measuring operating performance against prior periods on a comparable basis and has been presented in order to provide an additional measure for analyzing the Company's crude oil sales on a per barrel basis and ability to generate funds.

FORWARD-LOOKING STATEMENTS

Certain statements in this news release constitute forward-looking statements under applicable securities legislation. Such statements are generally identifiable by the terminology used, such as "anticipate'', "appear", "believe'', "intend", "expect", "plan", "estimate", "budget'', "outlook'', "scheduled", "may", "will", "should", "could", "would", "in the process of" or other similar wording. Forward-looking information in this news release includes, but is not limited to, information concerning: initial production rates and the expected timing thereof; the timing and ability to commission the Poyraz Ridge facility and pipeline and obtain the customary government approvals to commence production; the ability of the drilled wells to become producing wells; projections and timing with respect to crude oil and gas production; expected markets and prices for future oil and gas sales; the timing and ability to obtain various approvals for the Company's exploration and development activities; the timing and ability to access oil and gas pipelines and oil and gas domestic and export sales markets; anticipated capital expenditures and cash flows; sources and availability of financing for potential budgeting shortfalls; the timing and ability to obtain future funding on favourable terms; general business strategies and objectives; possible outcomes regarding the Zharkamys Contract including the possibility that the term may be extended or, conversely, that it may revert back to the Ministry; the timing and ability to obtain exploration and production contract extensions; the potential for additional contractual work commitments; the ability to meet and fund the contractual work commitments; the satisfaction of the work commitments; the results of non-fulfillment of work commitments; the expectations related to future general and administrative and other expenses; projections relating to the adequacy of the Company's provision for taxes; the timing and ability to collect VAT; expected rates of return; and treatment under governmental regulatory regimes and tax laws.

By its very nature, such forward-looking information requires Condor to make assumptions that may not materialize or that may not be accurate. Forward-looking information is subject to known and unknown risks and uncertainties and other factors, which may cause actual results, levels of activity and achievements to differ materially from those expressed or implied by such information. Such risks and uncertainties include, but are not limited to: regulatory changes; the timing of regulatory approvals; the risk that actual minimum work programs will exceed the initially estimated amounts; the results of exploration and development drilling and related activities; imprecision of reserves and resources estimates and ultimate recovery of reserves; historical production and testing rates may not be indicative of future production rates, capabilities or ultimate recovery; the historical composition and quality of oil and gas may not be indicative of future composition and quality; general economic, market and business conditions; industry capacity; uncertainty related to marketing and transportation; competitive action by other companies; fluctuations in oil and natural gas prices; the effects of weather and climate conditions; fluctuation in interest rates and foreign currency exchange rates; the ability of suppliers to meet commitments; actions by governmental authorities, including increases in taxes; decisions or approvals of administrative tribunals and the possibility that government policies or laws may change or government approvals may be delayed or withheld; changes in environmental and other regulations; risks associated with oil and gas operations, both domestic and international; international political events; and other factors, many of which are beyond the control of Condor. Capital expenditures may be affected by cost pressures associated with new capital projects, including labour and material supply, project management, drilling rig rates and availability, and seismic costs.

These risk factors are discussed in greater detail in filings made by Condor with Canadian securities regulatory authorities including the Company's Annual Information Form, which may be accessed through the SEDAR website (www.sedar.com).

Readers are cautioned that the foregoing list of important factors affecting forward-looking information is not exhaustive. The forward-looking information contained in this news release are made as of the date of this news release and, except as required by applicable law, Condor does not undertake any obligation to update publicly or to revise any of the included forward-looking information, whether as a result of new information, future events or otherwise. The forward-looking information contained in this news release is expressly qualified by this cautionary statement.

ABBREVIATIONS

The following is a summary of abbreviations used in this news release:

bopd   Barrels of oil per day                                               
MM     Million                                                              
Q      Quarter                                                              
scf    Standard cubic feet                                                  
USD    United States dollars                                                
%      Percent                                                              
/      Per                                                                  

The TSX does not accept responsibility for the adequacy or accuracy of this news release.

For further information, please contact:
Don Streu
President and CEO
or
Sandy Quilty
Vice President of Finance and CFO
403-201-9694

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
Mobile device usage has increased exponentially during the past several years, as consumers rely on handhelds for everything from news and weather to banking and purchases. What can we expect in the next few years? The way in which we interact with our devices will fundamentally change, as businesses leverage Artificial Intelligence. We already see this taking shape as businesses leverage AI for cost savings and customer responsiveness. This trend will continue, as AI is used for more sophistica...
Nordstrom is transforming the way that they do business and the cloud is the key to enabling speed and hyper personalized customer experiences. In his session at 21st Cloud Expo, Ken Schow, VP of Engineering at Nordstrom, discussed some of the key learnings and common pitfalls of large enterprises moving to the cloud. This includes strategies around choosing a cloud provider(s), architecture, and lessons learned. In addition, he covered some of the best practices for structured team migration an...
Most technology leaders, contemporary and from the hardware era, are reshaping their businesses to do software. They hope to capture value from emerging technologies such as IoT, SDN, and AI. Ultimately, irrespective of the vertical, it is about deriving value from independent software applications participating in an ecosystem as one comprehensive solution. In his session at @ThingsExpo, Kausik Sridhar, founder and CTO of Pulzze Systems, discussed how given the magnitude of today's application ...
Recently, REAN Cloud built a digital concierge for a North Carolina hospital that had observed that most patient call button questions were repetitive. In addition, the paper-based process used to measure patient health metrics was laborious, not in real-time and sometimes error-prone. In their session at 21st Cloud Expo, Sean Finnerty, Executive Director, Practice Lead, Health Care & Life Science at REAN Cloud, and Dr. S.P.T. Krishnan, Principal Architect at REAN Cloud, discussed how they built...
The “Digital Era” is forcing us to engage with new methods to build, operate and maintain applications. This transformation also implies an evolution to more and more intelligent applications to better engage with the customers, while creating significant market differentiators. In both cases, the cloud has become a key enabler to embrace this digital revolution. So, moving to the cloud is no longer the question; the new questions are HOW and WHEN. To make this equation even more complex, most ...
In his session at 21st Cloud Expo, Raju Shreewastava, founder of Big Data Trunk, provided a fun and simple way to introduce Machine Leaning to anyone and everyone. He solved a machine learning problem and demonstrated an easy way to be able to do machine learning without even coding. Raju Shreewastava is the founder of Big Data Trunk (www.BigDataTrunk.com), a Big Data Training and consulting firm with offices in the United States. He previously led the data warehouse/business intelligence and B...
As you move to the cloud, your network should be efficient, secure, and easy to manage. An enterprise adopting a hybrid or public cloud needs systems and tools that provide: Agility: ability to deliver applications and services faster, even in complex hybrid environments Easier manageability: enable reliable connectivity with complete oversight as the data center network evolves Greater efficiency: eliminate wasted effort while reducing errors and optimize asset utilization Security: imple...
In his Opening Keynote at 21st Cloud Expo, John Considine, General Manager of IBM Cloud Infrastructure, led attendees through the exciting evolution of the cloud. He looked at this major disruption from the perspective of technology, business models, and what this means for enterprises of all sizes. John Considine is General Manager of Cloud Infrastructure Services at IBM. In that role he is responsible for leading IBM’s public cloud infrastructure including strategy, development, and offering m...
With tough new regulations coming to Europe on data privacy in May 2018, Calligo will explain why in reality the effect is global and transforms how you consider critical data. EU GDPR fundamentally rewrites the rules for cloud, Big Data and IoT. In his session at 21st Cloud Expo, Adam Ryan, Vice President and General Manager EMEA at Calligo, examined the regulations and provided insight on how it affects technology, challenges the established rules and will usher in new levels of diligence arou...
The past few years have brought a sea change in the way applications are architected, developed, and consumed—increasing both the complexity of testing and the business impact of software failures. How can software testing professionals keep pace with modern application delivery, given the trends that impact both architectures (cloud, microservices, and APIs) and processes (DevOps, agile, and continuous delivery)? This is where continuous testing comes in. D
Modern software design has fundamentally changed how we manage applications, causing many to turn to containers as the new virtual machine for resource management. As container adoption grows beyond stateless applications to stateful workloads, the need for persistent storage is foundational - something customers routinely cite as a top pain point. In his session at @DevOpsSummit at 21st Cloud Expo, Bill Borsari, Head of Systems Engineering at Datera, explored how organizations can reap the bene...
Digital transformation is about embracing digital technologies into a company's culture to better connect with its customers, automate processes, create better tools, enter new markets, etc. Such a transformation requires continuous orchestration across teams and an environment based on open collaboration and daily experiments. In his session at 21st Cloud Expo, Alex Casalboni, Technical (Cloud) Evangelist at Cloud Academy, explored and discussed the most urgent unsolved challenges to achieve f...
The dynamic nature of the cloud means that change is a constant when it comes to modern cloud-based infrastructure. Delivering modern applications to end users, therefore, is a constantly shifting challenge. Delivery automation helps IT Ops teams ensure that apps are providing an optimal end user experience over hybrid-cloud and multi-cloud environments, no matter what the current state of the infrastructure is. To employ a delivery automation strategy that reflects your business rules, making r...
The 22nd International Cloud Expo | 1st DXWorld Expo has announced that its Call for Papers is open. Cloud Expo | DXWorld Expo, to be held June 5-7, 2018, at the Javits Center in New York, NY, brings together Cloud Computing, Digital Transformation, Big Data, Internet of Things, DevOps, Machine Learning and WebRTC to one location. With cloud computing driving a higher percentage of enterprise IT budgets every year, it becomes increasingly important to plant your flag in this fast-expanding busin...
In a recent survey, Sumo Logic surveyed 1,500 customers who employ cloud services such as Amazon Web Services (AWS), Microsoft Azure, and Google Cloud Platform (GCP). According to the survey, a quarter of the respondents have already deployed Docker containers and nearly as many (23 percent) are employing the AWS Lambda serverless computing framework. It’s clear: serverless is here to stay. The adoption does come with some needed changes, within both application development and operations. Tha...